134-576: Bergen Light Rail ( Norwegian : Bybanen ) is a light rail system in Bergen , Norway . The first stage of the project was a twenty-station stretch between the city center and Nesttun , where the first 15 stations comprising a 9.8-kilometre (6.1 mi) stretch opened in 2010, and the second was a 3.6-kilometre (2.2 mi) stretch from Nesttun to Lagunen which opened in June 2013. A third stretch from Lagunen to Bergen Airport, Flesland opened in 2017. The second line between Kaigaten and Fyllingsdalen opened on 21 November 2022. Further plans for

268-537: A bus rapid transit . The plans launched by the city administration most closely resembled the Environmental Tram, with slight changes. The initial plans involved a line from the city center via Nesttun to the airport at Flesland . It became part of a political compromise, the Bergen Program, which ensured a number of road investments at the same time as the light rail system, all financed through

402-594: A limited company wholly owned by Vestland County Council. This company is responsible for the maintenance of the right-of-way and the vehicles, and for extensions. Light rail operations are based on contracts granted after public tender competitions held by Bybanen AS. The time tables are decided by Skyss, another unit in Vestland County Council that administers all public transport in Vestland, including buses, boats and ferries. The light rail operation

536-538: A refinery at Mongstad in Lindås. In 1971, details about the suspension bridge were again discussed, with three different proposals with the main span of between 1,090 and 1,210 meters (3,580 and 3,970 ft) with 160-meter (520 ft) tall pylons. There were protests from the Salhus area, as the suspension bridge would have resulted in the demolishing of part of the residential area. In 1972, discussion started with

670-551: A suspension bridge crossing between Frekhaug and Salhus . In 1962, the issue was brought up again, this time as a pontoon bridge. The depth and steepness of the fjord would make it impossible to fasten the bridge to the sea bottom. However, a method without lateral anchorage had been developed for the Hobart Bridge in Australia. Another alternative was launched in 1963, involving a submerged floating tunnel through

804-499: A 3 kilometer long tunnel to the Fyllingsdalen terminal. Plans for the expansion northwards from the city center to Åsane have not been conclusive, due to disagreements on which path to follow through the city center. The proposed construction along Bryggen is formally adopted by the city council of Bergen, but controverses and continuing debates on an alternative tunnel solution has paused the process. An important stop mid-way

938-580: A branch of Osterfjorden which was suitable to connect the parts. There were problems welding the high-strength low-alloy steel , which resulted in the work being halted for several days before an agreement was reached between the contractor and the Public Roads Administration. On 26 January 1994, the steel frame which would be used to fasten the pontoon bridge to the cable-stayed bridge, came adrift during transport in Skagerrak , and

1072-435: A cable-stayed bridge, a pontoon bridge and a viaduct which connects the two. The cable-stayed bridge consists of a 99.3-meter (326 ft) tall H-pylon with a foundation at Klauvaneset on the mainland of Bergen. It supports a 172-meter (564 ft) main span , with the other end being fixed in a foundation 30-meter (98 ft) below mean sea level , which is anchored in the ridge Klauvaskallen. The whole cable-stayed bridge

1206-474: A capacity of between 1,960 and 7,910 kilonewtons (440,000 and 1,780,000  lb f ). They can be tightened at the connection with the roadwall. The floating section consists of a steel box girder placed on top of ten floating pontoons. The pontoon section is anchored only at both ends, on the underwater foundation at Kauvaskallen and on Flatøy. It is fastened using flexible plate connections fastened by bolts and cables under tension. These are flexible around

1340-505: A continuous concrete floating caisson between the abutments, and a steel version incorporating a truss bridge carrying concrete pontoons. However, they were both rejected in favor of a concrete or steel box section borne on concrete pontoons. Design of the bridge was awarded to Aas-Jakobsen and Det Norske Veritas , the former who also performed dynamic analysis and structural engineering . Architects were Hindhammer–Sundt–Thomassen, Lund & Løvseth, and Lund & Slaatto. An H pylon

1474-449: A corresponding increase of public transport. Further out is a large corporate center with many of Bergen's largest employers, such as Telenor , Equinor and BKK. The area was built without sufficient roads or public transport. Building the light rail line to Flesland has greatly improved the access to the airport from the city, offering a reasonably priced service for locals and employees at the airport. Another incentive to build to Flesland

SECTION 10

#1732801742673

1608-435: A distinct dialect at the level of farm clusters. Dialects are in some cases so dissimilar as to be unintelligible to unfamiliar listeners. Many linguists note a trend toward regionalization of dialects that diminishes the differences at such local levels; there is, however, a renewed interest in preserving dialects. Norwegian nouns are inflected for number (singular/plural) and for definiteness (indefinite/definite). In

1742-548: A few dialects, definite nouns are also inflected for the dative case . Norwegian nouns belong to three noun classes (genders): masculine, feminine and neuter. All feminine nouns can optionally be inflected using masculine noun class morphology in Bokmål due to its Danish heritage. In comparison, the use of all three genders (including the feminine) is mandatory in Nynorsk. All Norwegian dialects have traditionally retained all

1876-418: A garage with place for three. There is sufficient area for further expansion, but tracks have not been laid. When the light rail line is expanded to Flesland, a new main depot is planned in an area with cheaper land, and Kronstad depot will be converted to a pure overnighting facility. As of 2024, there are 35 stops along the two lines. The stations and the visual profile of the system as a whole are designed by

2010-496: A gradient of 5.7 degrees. It consists of spans between 18 and 33 meters (59 and 108 ft), with the roadway also built as an orthotropic deck with 12-millimeter (0.47 in) thick plates. Overall, the construction of the bridge used 24,000 tonnes (24,000 long tons; 26,000 short tons) of concrete, of which 10,000 tonnes (9,800 long tons; 11,000 short tons) in the pontoons. The bridge was coated with 40,000 litres (8,800 imp gal; 11,000 US gal) of paint. The bridge

2144-462: A length of 42 meters (137 ft 10 in). The early vehicles got extended, and the first 42-meter tram was put in traffic on 4 August 2016. During the following year, all trams were extended to 42 meters, and from then, all new trams are 42 meters at time of purchase. All stations are built for extended trams. There is a slightly elevated driver's cab at each end. Eight motors provide a total of 360 kW (480 hp) for three bogies. This allows

2278-430: A massive investment in motorways. This included European Route E39 north and south of the center, the road to the airport, and west to Loddefjord and Storavatnet. Bridges were constructed to Lindås , Askøy and Sotra , and large parking garages were built in the city center. Despite this congestion continued, and it was no better in the 2000s than in the 1970s. Proposals to build bus lanes and traffic signal preemption

2412-426: A maximum speed of 70 km/h (43 mph), limited to 50 km/h (31 mph) in city streets and 25 km/h (16 mph) in the depots. Acceleration is 1.25 m/s/s (2.8 mph/s), and they are capable of operating on a 7.0% gradient . Current is collected via a pantograph, at 750 volts direct current . Each tram is sufficiently powerful to haul another unit in case of emergencies. Maximum capacity

2546-433: A more extensive system, the Environmental Tram, which more closely resembles the current proposals. From the city center, it would run northwards via Åsane to Flaktveit and southwards via Rådal to the airport (not via Nesttun). The southern section would have branches from Hop to Nesttun and Midttun , and from Minde westwards to Fyllingsdalen and Loddefjord. Later, Bergen Sporvei's successor, Gaia Trafikk , proposed building

2680-441: A new Norwegian language at the age of 22. He traveled around the country collecting words and examples of grammar from the dialects and comparing the dialects among the different regions. He examined the development of Icelandic , which had largely escaped the influences under which Norwegian had come. He called his work, which was published in several books from 1848 to 1873, Landsmål , meaning 'national language'. The name Landsmål

2814-501: A noun, unlike English which has a separate article, the , to indicate the same. In general, almost all nouns in Bokmål follow these patterns (like the words in the examples above): In contrast, almost all nouns in Nynorsk follow these patterns (the noun gender system is more pronounced than in Bokmål): There is in general no way to infer what grammatical gender a specific noun has, but there are some patterns of nouns where

SECTION 20

#1732801742673

2948-550: A pontoon bridge were presented to the Standing Committee on Transport and Communications on 31 March 1981. They supported the choice of a pontoon bridge. The decision to construct the bridge was taken by parliament on 9 December 1987, but they demanded that a larger ship channel be constructed. Detailed planning started in March 1990, and at first two technical methods for constructing the pontoon bridge were considered:

3082-551: A pontoon bridge with a movable section to allow passage of ship traffic. In 1967, a new proposal was launched, in which a seaway tunnel would be blasted out in the rock on the Bergen side. The Alversund Bridge was a toll bridge which was paying for the debt accumulated in its construction. By 1968, the debt would be paid off, but the Norwegian Public Roads Administration launched a plan whereby

3216-702: A single ticket is NOK 44. The tickets are part of the same ticketing system as the buses in Bergen and Vestland. In 2007, the Planning Office ordered 12 Variobahn trams from Stadler Rail , with an additional four on option. The first tram arrived on 7 December 2009, and was used for testing in the months leading up to the opening. Before the opening, five more trams were in place. The first trams were 32.180 m (105 ft 6.9 in) long and 2.65 meters (8 ft 8 in) wide, weighing 35.7 tonnes (35.1 long tons; 39.4 short tons). They had five articulated sections, and were expandable with another two modules to

3350-402: Is 280 passengers. The entire tram is step-free , including between the cars and the platforms. Seats are designed for travel times up to 60 minutes. There are five slide and plug doors on each side; three are double, with a total width of 1,300-millimeter (4 ft 3 in), while the last is a single 800-millimeter (2 ft 7 in) door. Stop buttons are only available at the doors, but

3484-510: Is 369 meters (1,211 ft) long, with a 190-meter (620 ft) long viaduct, supported by six pairs of pillars. The cable-stayed bridge allows for a sailing channel which is 32 meters (105 ft) tall and 50 meters (160 ft) wide. The main span is built in lightweight LC55 concrete , while the viaduct and pylon is built with conventional C45 concrete. Inside the pylons is a 1.6-by-2.0-meter (5 ft 3 in by 6 ft 7 in) hollow area. The bridge has 48 cables, 12 on each side of

3618-697: Is 500 meters (1,600 ft) deep, making the method prohibitively expensive. The choice of a cable-stayed section allowed reduced traffic hazards in storms, a reduction in corrosion on the bridge deck, and improved passage of water beneath the bridge in support of wildlife. The contract for construction of the pontoon bridge was awarded in August 1991 to a consortium , Arbeidsfellesskapet Salhus Bru, which consisted of Norwegian Contractors , Aker Entreprenør , Veidekke and Kværner Eureka . The components were built in Moss and Fredrikstad and then shipped to Lonevågen ,

3752-413: Is Bokmål will study Nynorsk as a mandatory subject throughout both elementary and high school. A 2005 poll indicates that 86.3% use primarily Bokmål as their daily written language, 5.5% use both Bokmål and Nynorsk, and 7.5% use primarily Nynorsk. Thus, 13% are frequently writing Nynorsk, though the majority speak dialects that resemble Nynorsk more closely than Bokmål. Broadly speaking, Nynorsk writing

3886-581: Is a North Germanic language from the Indo-European language family spoken mainly in Norway , where it is an official language. Along with Swedish and Danish , Norwegian forms a dialect continuum of more or less mutually intelligible local and regional varieties; some Norwegian and Swedish dialects , in particular, are very close. These Scandinavian languages, together with Faroese and Icelandic as well as some extinct languages , constitute

4020-440: Is a pitch-accent language with two distinct pitch patterns, like Swedish. They are used to differentiate two-syllable words with otherwise identical pronunciation. For example, in many East Norwegian dialects, the word bønder ('farmers') is pronounced using the simpler tone 1, while bønner ('beans' or 'prayers') uses the more complex tone 2. Though spelling differences occasionally differentiate written words, in most cases

4154-411: Is a language form based on Norwegian dialects and puristic opposition to Danish. The now-abandoned official policy to merge Bokmål and Nynorsk into one common language called Samnorsk through a series of spelling reforms has created a wide spectrum of varieties of both Bokmål and Nynorsk. The unofficial form known as Riksmål is considered more conservative than Bokmål and is far closer to Danish while

Bergen Light Rail - Misplaced Pages Continue

4288-435: Is a steel box girder bridge with ten pontoons , which because of the fjord's depth are not laterally anchored. The roadway sits on an orthotropic deck . The pontoons and the cable-stayed bridge are built in concrete, with the main span being supported with 48 cables. The fjord end of the main span is supported by a 30-meter (98 ft) deep foundation, where the two bridges meet. From there and for 414 meters (1,358 ft),

4422-736: Is comparable with that of French on English after the Norman conquest . In the late Middle Ages, dialects began to develop in Scandinavia because the population was rural and little travel occurred. When the Reformation came from Germany, Martin Luther 's High German translation of the Bible was quickly translated into Swedish, Danish, and Icelandic. Norway entered a union with Denmark in 1397 and Danish, over time, replaced Middle Norwegian as

4556-411: Is currently handled by Tide Buss og Bane AS. Stadler has the responsibility for maintenance of the trams for the first seven years, as part of the purchase contract. The line is operated on a four/five-minute headway by all-stops trams, with an eight-minute headway in off-peak times and a 20 minutes headway at night. The travel time from Byparken to Bergen airport is 44 minutes. In 2024, the full price of

4690-420: Is made with 14-to-20-millimeter (0.55 to 0.79 in) thick steel plates. They are longitudinally stiffened by trapezoidal stiffeners supported by cross frames at most every 4.5 meters (15 ft). Two full bulkheads have been used for every pontoon pilaster, made from welded steel plates 8 to 50 millimeters (0.31 to 1.97 in) thick. External brackets built into the bulkheads transfer the support forces to

4824-487: Is made with steel with a higher yield point. The inside of the girder has two dehumidifiers which ensure that it does not rust. The clearance under the girder is 5.5 meters (18 ft). The two bridges are connected with a 414.5-meter (1,360 ft) long steel viaduct, which runs on top of the floating bridge, bringing the road from 11.0 to 34.4 meters (36.1 to 112.9 ft) above mean sea level. The viaduct weighs 1,600 tonnes (1,600 long tons ; 1,800 short tons ) and has

4958-656: Is monitored by 132 sensors, including sensors on hatches to the pontoons, on doors to the steel box girder, for corrosion, strain gauges on the girder and on flexible elements, and weather information. On the cable-stayed section, the bridge is marked with navigation lights, as well as the center of the sailing area having a racon . The bridge is the second-longest bridge in Norway, behind the Drammen Bridge . Ship services in Nordhordland started in 1866, and in 1923

5092-423: Is now considered their classic forms after a reform in 1917. Riksmål was, in 1929, officially renamed Bokmål (literally 'book language'), and Landsmål to Nynorsk (literally 'new Norwegian'). A proposition to substitute Danish-Norwegian ( dansk-norsk ) for Bokmål lost in parliament by a single vote. The name Nynorsk , the linguistic term for modern Norwegian , was chosen to contrast with Danish and emphasise

5226-556: Is regulated by the Norwegian Academy , which determines acceptable spelling, grammar, and vocabulary. There is also an unofficial form of Nynorsk, called Høgnorsk , discarding the post-1917 reforms, and thus close to Ivar Aasen's original Landsmål. It is supported by Ivar Aasen-sambandet , but has found no widespread use. In 2010, 86.5% of the pupils in the primary and lower secondary schools in Norway receive education in Bokmål, while 13.0% receive education in Nynorsk. From

5360-754: Is rising in the first syllable and falling in the second syllable or somewhere around the syllable boundary. The pitch accents (as well as the peculiar phrase accent in the low-tone dialects) give the Norwegian language a "singing" quality that makes it easy to distinguish from other languages. Accent 1 generally occurs in words that were monosyllabic in Old Norse , and accent 2 in words that were polysyllabic. The Norwegian alphabet has 29 letters. The letters c , q , w , x and z are only used in loanwords . As loanwords are assimilated into Norwegian, their spelling might change to reflect Norwegian pronunciation and

5494-526: Is sometimes interpreted as 'rural language' or 'country language', but this was clearly not Aasen's intended meaning. The name of the Danish language in Norway was a topic of hot dispute throughout the 19th century. Its proponents claimed that it was a language common to Norway and Denmark, and no more Danish than Norwegian. The proponents of Landsmål thought that the Danish character of the language should not be concealed. In 1899, Bjørnstjerne Bjørnson proposed

Bergen Light Rail - Misplaced Pages Continue

5628-413: Is supplied from six rectifiers , specified so the system can operate with two rectifiers out of service. In the city center the overhead wire has been designed to minimize the number of poles, while in the suburban areas a conventional system has a carrier wire above the power wire. The line is double track, allowing visual signaling and speed adjustment on all at-grade stretches. In city streets S60 track

5762-539: Is the Norwegian School of Economics . The terminus will probably be Åsane Senter or Nyborg; the former shopping center has set aside areas for a station. At Åsane, a major bus terminal would allow connections to the northern parts of Bergen, suburbs further north and areas in Nordhordland . An important political argument for prioritizing this line is to share the investments and effects with all parts of

5896-422: Is to use the place name where the station is located, and naming after institutions or facilities nearby is not permitted unless they are in the immediate vicinity. Brann stadion, named for the football venue , was declared a borderline case, but within the rules, while Troldhaugen was not permitted because the area is not in the vicinity of the station. Initial works commenced in August 2007, when Pastasentralen

6030-459: Is to write in dialect for informal use. When writing an SMS, Facebook update, or fridge note, many people, especially young ones, write approximations of the way they talk rather than using Bokmål or Nynorsk. There is general agreement that a wide range of differences makes it difficult to estimate the number of different Norwegian dialects. Variations in grammar, syntax, vocabulary, and pronunciation cut across geographical boundaries and can create

6164-534: Is today to a large extent the same language as Bokmål though somewhat closer to the Danish language. It is regulated by the unofficial Norwegian Academy , which translates the name as 'Standard Norwegian'. The other is Høgnorsk ('High Norwegian'), a more purist form of Nynorsk, which maintains the language in an original form as given by Ivar Aasen and rejects most of the reforms from the 20th century; this form has limited use. Nynorsk and Bokmål provide standards for how to write Norwegian, but not for how to speak

6298-565: Is used; on private right-of-way, S49 track. The minimum curve radius is 25 metres (82 ft 0 in) and tracks in city streets are laid within a rubber jacket to reduce noise. In the tunnels, only one tram can operate in each direction; this is regulated by lights and an automatic Train Protection system. Signaling uses the German BOStrab system, not traditional Norwegian light signals. The line has traffic signal preemption, so

6432-496: Is widespread in western Norway, though not in major urban areas, and also in the upper parts of mountain valleys in the southern and eastern parts of Norway. Examples are Setesdal , the western part of Telemark county ( fylke ) and several municipalities in Hallingdal , Valdres , and Gudbrandsdalen . It is little used elsewhere, but 30–40 years ago, it also had strongholds in many rural parts of Trøndelag (mid-Norway) and

6566-505: The Brann Stadion stop serves the Brann Stadion football venue. Wergeland is at the mouth of the 1.1-kilometer (0.68 mi) Fageråstunnelen , S-shaped with a 6.0% gradient and a curve radius of 150 meters (492 ft 2 in). From the southern portal the line changes to conventional railway track with ballast , allowing trams to operate at 80 km/h (50 mph). The next stops are Sletten , Slettebakken and Fantoft ,

6700-634: The British Isles , France ( Normandy ), North America, and Kievan Rus . In all of these places except Iceland and the Faroes, Old Norse speakers went extinct or were absorbed into the local population. Around 1030, Christianity came to Scandinavia , bringing with it an influx of Latin borrowings and the Roman alphabet . These new words were related to church practices and ceremonies, although many other loanwords related to general culture also entered

6834-613: The Germanic peoples living in Scandinavia during the Viking Age . Today there are two official forms of written Norwegian, Bokmål (Riksmål) and Nynorsk (Landsmål), each with its own variants. Bokmål developed from the Dano-Norwegian language that replaced Middle Norwegian as the elite language after the union of Denmark–Norway in the 16th and 17th centuries and then evolved in Norway, while Nynorsk

SECTION 50

#1732801742673

6968-721: The Homer M. Hadley Memorial Bridge and the Hood Canal Bridge in the United States. Instead, an orthotropic deck was chosen, such as the Bergsøysund Bridge had used. The choice of a box girder bridge and the orthotropic deck were chosen because it gave the lower material use. Conventional pontoon bridges have lateral anchorage systems which fasten the bridge to the seabed. The technique had previously been used down to 140 meters (460 ft), but Salhusfjorden

7102-686: The Norwegian Public Roads Administration started looking at rectifying the situation by building a ring road around the city, and by alternative means of public transport. Prior to the shortening of the main Bergen Line railway with the Ulriken Tunnel , the Bergen–Nesttun Line was an important commuter rail service, feeding suburban residents from Fana into the city center. In 1917, the section

7236-574: The 1959 standard. Therefore, a small minority of Nynorsk enthusiasts use a more conservative standard called Høgnorsk . The Samnorsk policy had little influence after 1960, and was officially abandoned in 2002. While the sound systems of Norwegian and Swedish are similar, considerable variation exists among the dialects. The retroflex consonants only appear in East Norwegian dialects as a result of sandhi , combining / ɾ / with / d / , / l / , / n / , / s / , and / t / . The realization of

7370-475: The 20th century, being used by large newspapers, encyclopedias, and a significant proportion of the population of the capital Oslo, surrounding areas, and other urban areas, as well as much of the literary tradition. Since the reforms of 1981 and 2003 (effective in 2005), the official Bokmål can be adapted to be almost identical with modern Riksmål. The differences between written Riksmål and Bokmål are comparable to American and British English differences . Riksmål

7504-488: The Bergen-based design groups Cubus and Fuggi Baggi Design, and Copenhagen -based Kontrapunkt. Most of the stations are at street level, and have facilities for buying tickets and dynamic displays that show when the next tram will arrive. The platforms have step-free access to the trams, allowing unhindered accessibility by wheelchairs and perambulators . The municipal government has permitted denser development around

7638-501: The Dano-Norwegian koiné , known as "cultivated everyday speech." A small adjustment in this direction was implemented in the first official reform of the Danish language in Norway in 1862 and more extensively after his death in two official reforms in 1907 and 1917. Meanwhile, a nationalistic movement strove for the development of a new written Norwegian. Ivar Aasen , a botanist and self-taught linguist, began his work to create

7772-455: The Ministry of Culture, official spelling, grammar, and vocabulary for the Norwegian language. The board's work has been subject to considerable controversy throughout the years. Both Nynorsk and Bokmål have a great variety of optional forms. The Bokmål that uses the forms that are close to Riksmål is called moderate or conservative , depending on one's viewpoint, while the Bokmål that uses

7906-479: The North Germanic languages. Faroese and Icelandic are not mutually intelligible with Norwegian in their spoken form because continental Scandinavian has diverged from them. While the two Germanic languages with the greatest numbers of speakers, English and German, have close similarities with Norwegian, neither is mutually intelligible with it. Norwegian is a descendant of Old Norse , the common language of

8040-470: The administration denied this, resulting in a lawsuit. On 26 January 1996, Nordhordland District Court supported the administration, but gave the plaintiff partial support, claiming the administration should take part of the costs through improper choice of material. The Public Roads Administration was sentenced to pay NOK 34 million to Kværner. Both sides appealed to Gulating Court of Appeal , which on 18 February 1998 refuted all of Kværner's claim regarding

8174-402: The airport. Four-car trains would operate at ten-minute headways . The suggestion was discussed by the city council in 1973, but no decision was taken. As an alternative, expansion of the railway from Bergen to Eidsvåg , Åsane and Nesttun was proposed. Fast commuter trains could then be supplemented with buses. During the 1980s and 1990s, a toll ring was constructed around Bergen to finance

SECTION 60

#1732801742673

8308-412: The bridge. The roadway lies on top of an orthotropic deck on a steel box girder, which is 15.9 meters (52 ft) wide, 5.50 meters (18.0 ft) tall and 1,246 meters (4,088 ft) long. The steel box girder weighs 14,150 tonnes (13,930 long tons ; 15,600 short tons ), of which 3,000 tonnes (3,000 long tons; 3,300 short tons) is high-strength low-alloy steel . The girder has an octagonal shape and

8442-430: The bridge. A grade-separated crossing was built on both sides of the bridge. The intersection on Flatøy was also built as a bus interchange , and became the terminus of many bus routes in Nordhordland. Express buses would from there run directly to the city center of Bergen. The bridge project cost NOK 910 million, of which NOK 513 was for the pontoon bridge, NOK 81 million was for the cable-stayed bridge, NOK 25 million

8576-585: The city. Several politicians, including the majority in Hordaland County Council , have stated that in the long run they want the light rail line extended northwards to Knarvik and westwards to Straume and Kleppestø . The building of the line is the responsibility of Bybanen Utbygging, which is a unit in Vestland County Council. Due to the present pause in the construction process, Bybanen Utbygging will be reduced in size in 2024. The physical infrastructure and trams are owned by Bybanen AS,

8710-412: The company changed its name to Keolis Norge AS. Along with the establishment of the light rail service, the public transport in Bergen underwent other changes. Skyss was established in 2007 to administer the public transport system, manage routes and market public transport, which would be operated by private companies based on public service obligations. At the same time, a new electronic ticketing system

8844-486: The defendants legal costs of NOK 910,000. The bridge was officially opened by King Harald V on 22 September 1994. It was the second pontoon bridge in Norway, after the Bergsøysund Bridge which opened in 1992. The last tolls were collected on 31 December 2005. In 2008, there were 19,700 travelers on the bridge each day, 14 percent of which used public transport . In 2009, the bridge had an average daily traffic (ADT) of 14,698 vehicles, up from 7975 in 2000. Following

8978-520: The eastern side of Store Lungegårdsvann to the Fløen stop. It continues into a tunnel and stops under the hospital area, where a large underground stop has been constructed, with exits to both Haukeland University Hospital , which is Western Norway's largest work place, and Haraldsplass Diakonale Sykehus. The next stop after the tunnel is Kronstad, where line 2 intersects with line 1. It then continues over Mindemyren industrial area to Kristianborg, and through

9112-644: The eighth grade onwards, pupils are required to learn both. Out of the 431 municipalities in Norway, 161 have declared that they wish to communicate with the central authorities in Bokmål, 116 (representing 12% of the population) in Nynorsk, while 156 are neutral. Of 4,549 state publications in 2000, 8% were in Nynorsk, and 92% in Bokmål. The large national newspapers ( Aftenposten , Dagbladet , and VG ) are published in Bokmål or Riksmål. Some major regional newspapers (including Bergens Tidende and Stavanger Aftenblad ), many political journals, and many local newspapers use both Bokmål and Nynorsk. A newer trend

9246-630: The fares would be kept the same and the extra revenue used to finance a bridge from Flatøy to Lindås. This allowed the Alversund Bridge to open in 1958, and the ferry service from Flatøy and Meland to move to Knarvik. The proposal to cross Salhusfjorden was launched during the planning of the Alversund Bridge. Cost estimates were made based on the Golden Gate Bridge in the United States, but it proved too expensive for

9380-403: The first car was purchased. A car ferry service between Isdalstø in Lindås and Steinestø in Åsane on the mainland was established on 7 July 1936. A plan was launched whereby all traffic from Nordhordland would be collected in one place and transported across Salhusfjorden to Åsane. By moving the ferry quay from Isdalstø to Knarvik , the length of the ferry service could be reduced. However,

9514-485: The first centuries AD in what is today Southern Sweden. It is the earliest stage of a characteristically North Germanic language, and the language attested in the Elder Futhark inscriptions, the oldest form of the runic alphabets . A number of inscriptions are memorials to the dead, while others are magical in content. The oldest are carved on loose objects, while later ones are chiseled in runestones . They are

9648-423: The fjord. It was estimated to cost between NOK 19.5 and 26 million. Norwegian expatriate Leif J. Sverdrup , co-founder of Sverdrup & Parcel of the United States, inspected the fjord in 1965 and was later hired to plan the bridge in cooperation with Oslo-based civil engineering consultants Prosjektering. Municipal engineers started measuring currents in 1966. Prosjektering and Sverdrup & Parcel recommended

9782-501: The forms that are close to Nynorsk is called radical . Nynorsk has forms that are close to the original Landsmål and forms that are close to Bokmål. Opponents of the spelling reforms aimed at bringing Bokmål closer to Nynorsk have retained the name Riksmål and employ spelling and grammar that predate the Samnorsk movement. Riksmål and conservative versions of Bokmål have been the de facto standard written language of Norway for most of

9916-576: The gender can be inferred. For instance, all nouns ending in - nad will be masculine in both Bokmål and Nynorsk (for instance the noun jobbsøknad , which means 'job application'). Most nouns ending in - ing will be feminine, like the noun forventning ('expectation'). Nordhordland Bridge The Nordhordland Bridge ( Norwegian : Nordhordlandsbrua ) is a combined cable-stayed and pontoon bridge which crosses Salhusfjorden between Klauvaneset (in Bergen Municipality ) and

10050-417: The historical connection to Old Norwegian. Today, this meaning is often lost, and it is commonly mistaken as a "new" Norwegian in contrast to the "real" Norwegian Bokmål. Bokmål and Nynorsk were made closer by a reform in 1938. This was a result of a state policy to merge Nynorsk and Bokmål into a single language, to be called Samnorsk . A 1946 poll showed that this policy was supported by 79% of Norwegians at

10184-534: The horizontal axis at right angles towards the axis of the bridge, allowing for deformation caused by the tide . The fastening on Flatøy consists of a massive concrete block 22 by 20 meters (72 by 66 ft) long and 14.5 meters (48 ft) tall which was poured into a blast-out foundation pit in bedrock. Vertical pretension rock anchors have also been installed, with 12 at Klauvaskallen and 14 at Flatøy, giving 42 and 44 meganewtons (9,400,000 and 9,900,000 lb f ) of support, although they were only built to increase

10318-542: The initial public service obligation to operate the line: Fjord1 Partner , Norges Statsbaner , Tide Bane and Veolia Transport Norge . On 3 April 2009, the public transport agency Skyss announced that Fjord1 Partner, a joint venture between Fjord1 AS and Keolis , had won the tender competition. Fjord1 Partner received 324 applications for their 26 jobs as drivers and 10 jobs as traffic controllers. In 2014 Fjord1 AS sold their shares in Fjord1 Partner to Keolis, and

10452-566: The island of Flatøy (in Alver Municipality ) in Vestland county, Norway . It is 1,614 meters (5,295 ft) long, of which the pontoon section is 1,246 meters (4,088 ft) long. The cable-stayed section consists of a single 99-meter (325 ft) tall H-pylon which has a length of 368 meters (1,207 ft) and a main span of 172 meters (564 ft). This allows for a clearance of 32 meters (105 ft). The floating section

10586-467: The language of the elite, the church, literature, and the law. When the union with Denmark ended in 1814, the Dano-Norwegian koiné had become the mother tongue of around 1% of the population. From the 1840s, some writers experimented with a Norwegianised Danish by incorporating words that were descriptive of Norwegian scenery and folk life, and adopting a more Norwegian syntax. Knud Knudsen proposed to change spelling and inflection in accordance with

10720-610: The language. The Scandinavian languages at this time are not considered to be separate languages, although there were minor differences among what are customarily called Old Icelandic, Old Norwegian , Old Gutnish , Old Danish, and Old Swedish . The economic and political dominance of the Hanseatic League between 1250 and 1450 in the main Scandinavian cities brought large Middle Low German –speaking populations to Norway. The influence of their language on Scandinavian

10854-555: The language. No standard of spoken Norwegian is officially sanctioned, and most Norwegians speak their own dialects in all circumstances. Thus, unlike in many other countries, the use of any Norwegian dialect, whether it coincides with the written norms or not, is accepted as correct spoken Norwegian. However, in areas where East Norwegian dialects are used, a tendency exists to accept a de facto spoken standard for this particular regional dialect, Urban East Norwegian or Standard East Norwegian (Norwegian: Standard østnorsk ), in which

10988-531: The languages in Europe, Norwegian derives from Proto-Indo-European . As early Indo-Europeans spread across Europe, they became isolated from each other and new languages developed. In northwest Europe, the Germanic languages evolved, further branching off into the North Germanic languages , of which Norwegian is one. Proto-Norse is thought to have evolved as a northern dialect of Proto-Germanic during

11122-428: The last trip ran on 31 January 1965. During the 1970s, plans had existed for an extensive rapid transit system, with an underground section in the city center. Inspired by the successful Oslo Metro that had opened in 1966, similar plans were developed. The proposed network was close to the current long-term plans for the light rail system, and consisted of three branches from the city center to Flaktveit , Olsvik and

11256-526: The later serving a large complex of student dormitories. Southwards is the 1.2-kilometer (0.75 mi) Fantoft Tunnel , followed by the Paradis stop. The line continues along the Nesttunvannet inlet to Hop , along the former right-of-way of Bergen's first motorway. Nesttun Terminal was the terminus between 2010 and 2013 when the extension to Lagunen was finished. After the completion to Nesttun,

11390-435: The light rail routes on buses—this would give higher operating costs for public transport or higher investment costs for roads. Around the stations, high-density commercial and residential centers can be established. Opponents of the project argued that it is unfair that public transport be funded by car drivers through toll roads. Protests from people in northern and western areas of the city have risen, since they are paying for

11524-609: The line was extended southwards to Rådal at Lagunen Storsenter . Construction began in January 2011, on its own right-of-way parallel to the existing road;, the track was completed in October 2012. The first test run to Lagunen was conducted on 6 December 2012, and the line was opened to the public on 22 June 2013. The light rail is connected from Lagunen via Sandsli and Kokstad to Bergen Airport, Flesland. Both Sørås and Indre Steinsvik have experienced rapid housing construction without

11658-593: The line, the Byparken stop, is a transit mall at the heart of the city center and has interchange with all buses serving the city center. The line runs south along Kaigaten, with Nonneseter stop serving the railway station and Bergen busstasjon serving the bus station . Southwards, the line runs in a grass right-of-way through Nygård and Florida , serving the campus of the University of Bergen . The line passes over Nygård Bridge before coming to Danmarks plass ,

11792-502: The minimal pairs are written alike, since written Norwegian has no explicit accent marks. In most eastern low-tone dialects, accent 1 uses a low flat pitch in the first syllable, while accent 2 uses a high, sharply falling pitch in the first syllable and a low pitch in the beginning of the second syllable. In both accents, these pitch movements are followed by a rise of intonational nature (phrase accent)—the size (and presence) of which signals emphasis or focus, and corresponds in function to

11926-519: The municipal administration and then sent to the borough councils in Fana, Årstad and Bergenhus . Four names were changed: Nonneseteren from Jernbanen, Florida from Strømmen, Brann stadion from Nymark and Hop from Troldhaugen. Brann stadion and Troldhaugen were afterwards considered by the municipal administration, because they could be in violation of the Place Name Act . The general rule

12060-430: The neutral name Riksmål , meaning 'national language' like Landsmål , and this was officially adopted along with the 1907 spelling reform. The name Riksmål is sometimes interpreted as 'state language', but this meaning is secondary at best. (Compare to Danish rigsmål from where the name was borrowed.) After the personal union with Sweden was dissolved in 1905, both languages were developed further and reached what

12194-414: The normal accent in languages that lack lexical tone , such as English. That rise culminates in the final syllable of an accentual phrase, while the utterance-final fall common in most languages is either very small or absent. There are significant variations in pitch accent between dialects. Thus, in most of western and northern Norway (the so-called high-pitch dialects) accent 1 is falling, while accent 2

12328-584: The oldest written record of any Germanic language. East Germanic languages West Germanic languages Icelandic Faroese Norwegian Danish Swedish Around 800 AD, the script was simplified to the Younger Futhark , and inscriptions became more abundant. At the same time, the beginning of the Viking Age led to the spread of Old Norse to Iceland , Greenland , and the Faroe Islands . Viking colonies also existed in parts of

12462-586: The only island platform on the system. In this area, the track is on maize, a type of surface that allows emergency vehicles to drive safely, but makes the surface look unsafe for cars. Line 1 goes on to the Kronstad stop, almost at the door of the Bergen University College , where it meets line number 2, which has a different route from the city centre, passing under the hospital of Haukeland. From Kronstad, line 1 follows Inndalsveien, where

12596-651: The plans to connect Meland, Flatøy and Lindøy with bridges. This was passed by the Parliament of Norway in May 1975, and consisted of the Krossnessundet Bridge between Flatøy and Meland, which opened in November 1978. The Hagelsund Bridge opened on 1 April 1982 and connected Flatøy to Lindås and Knarvik, thus also connecting Meland and Lindås. Both bridges were partially financed with tolls. The plans for

12730-406: The pontoons. The girder was built in sections of 21, 36, and 42 meters (69, 118, and 138 ft), which were subsequently welded together into 11 modules with a skew angle of 1.2 to 1.3 degrees. The girder has a constant cross-section throughout the length, except at the anchoring points to the pontoons. The section from the land anchoring to the first pontoon is subject to the most stress, and

12864-442: The principles of Norwegian orthography, e.g. zebra in Norwegian is written sebra . Due to historical reasons, some otherwise Norwegian family names are also written using these letters. Some letters may be modified by diacritics : é , è , ê , ó , ò , and ô . In Nynorsk, ì and ù and ỳ are occasionally seen as well. The diacritics are not compulsory, but may in a few cases distinguish between different meanings of

12998-465: The project involve mooted extensions to Åsane and Storavatnet . Plans for rail transit have existed since the 1970s, following the 1965 closing of the Bergen Tramway . A rapid transit design was first discarded, and in the 1990s a light rail line was proposed. The decision to start construction was made in 2005. The first stage was built by the municipality with financing from the state and

13132-458: The pylon on each side of the roadway. The distance between the cables is 12.00 meters (39.37 ft) on the main span, and 9.33 meters (30.6 ft) on the viaduct. Combined, the cables are 4,432 meters (14,541 ft) long; each cable consists of 67 to 230 twined cables, each with a 7-millimeter (0.28 in) diameter. The cables have a weight of between 1.5 and 14.5 tonnes (1.5 and 14.3 long tons ; 1.7 and 16.0 short tons ) each, and they have

13266-644: The removal of the tolls, the ADT increased from 9912 in 2005 to 12,249 in 2006. In 2010, the bridge was one of twelve finalists in Teknisk Ukeblad ' s competition for the most beautiful bridge in Norway. In December 2010, Bergen City Council approved the Nordhordland Package, which would result in NOK 3.8 billion being used on road investments in Åsane and Nordhordland. Two-thirds of the financing

13400-527: The rhotic / ɾ / depends on the dialect. In Eastern, Central, and Northern Norwegian dialects, it is a flap [ ɾ ] , whereas in Western and Southern Norway, and for some speakers also in Eastern Norway, it is uvular [ ʁ ] or [ χ ] . And in the dialects of North-Western Norway, it is realized as [ r ] , much like the trilled ⟨rr⟩ of Spanish. Norwegian

13534-547: The roadwall has a 5.7 percent gradient on a viaduct anchored to the pontoon bridge. The bridge carries two lanes of European Route E39 , also called the Coastal Highway, and one pedestrian and bicycle path, and connects the district of Nordhordland to Bergen . Plans for a bridge had existed since the 1960s, and after the decision to construct the bridge was passed by the Parliament of Norway in 1989, construction started in 1991. Total costs, including auxiliary roads,

13668-451: The safety factor. There are ten lightweight concrete pontoons, with 113.25-meter (371.6 ft) spans between them. The pontoons are between 7.0 and 8.6 meters (23.0 and 28.2 ft) in height. The draught varies between 4.3 to 5.6 meters (14 to 18 ft). Each pontoon consists of nine watertight cells which are partially filled with ballast for trim. The cells are dimensioned so two adjacent cells can fill with water without endangering

13802-606: The southern part of northern Norway ( Nordland county). Today, Nynorsk is the official language of not only four of the nineteen Norwegian counties but also various municipalities in five other counties. NRK , the Norwegian broadcasting corporation, broadcasts in both Bokmål and Nynorsk, and all governmental agencies are required to support both written languages. Bokmål is used in 92% of all written publications, and Nynorsk in 8% (2000). Like some other European countries, Norway has an official "advisory board"— Språkrådet (Norwegian Language Council)— that determines, after approval from

13936-444: The state, the remainder by the county, the municipality and through the toll ring. The arguments for light rail were mainly related to the environment , urban development and reduction in road congestion. Light rail is estimated to increase the use of public transport from Fana, reducing both local and global pollution. The roads do not have capacity for further growth, and any increase in public transport would need to be taken along

14070-458: The station's name. The melodies for the stops between Byparken and Nesttun were composed by Snorre Valen , while the voice was recorded by Heidi Lambach. Currently there are 34 Variobahn trams in operation. The system is standard gauge with 2.65-meter (8 ft 8 in)-wide cars, with the platforms built to allow 44-meter (144 ft 4 in) long trams. The line has no terminal balloon loops , so trams must be bi-directional. The current

14204-608: The stations, where it wants most new housing and commercial property to be built. Development projects for Slettebakken, Wergeland, Paradis, Lagunen, Sandsli, Kokstad and Mindemyren have been announced by private developers. Many of the stations are in primarily residential areas, and the projects have met resistance from residents who fear that the character of their neighborhoods will be altered. 60°23′33″N 5°19′24″E  /  60.39250°N 5.32333°E  / 60.39250; 5.32333 Norwegian language Norwegian ( endonym : norsk [ˈnɔʂːk] )

14338-468: The steel boxes, and sentenced the administration to pay NOK 7.5 million. In addition, Kværner had to pay the administration NOK 19.5 million in penalties for overrunning the contract date. However, the court's decision was not unanimous. The plaintiff appealed to case to the Supreme Court, who unanimously confirmed the ruling of Gulating Court of Appeal. In addition, the plaintiff was sentenced to pay

14472-550: The stop is intertwined with the airport terminal. The official opening of the last part of line 1 took place on 21 April 2017. Line 2 between Bergen city center and Fyllingsdalen was officially opened on 21 November 2022. Line 2 starts in Kaigaten, just across the intersection from the starting point of line 1. Line 1 and 2 both stop at Nonneseter outside Bergen railway station, and continue to Bergen busstasjon, which line 2 stops behind. The two lines then depart, and line 2 runs on

14606-427: The system but will not receive the benefits. Another issue has been speed: the line to Nesttun has 15 stops in 10 kilometers (6.2 mi), giving an average speed of 28 km/h (17 mph). For people living south of Nesttun, this will give a longer travel time to the city center than with direct buses that do not make intermediate stops. The naming of the stations caused local debate. A draft for names were made by

14740-401: The three grammatical genders from Old Norse to some extent. The only exceptions are the dialect of Bergen and a few upper class sociolects at the west end of Oslo that have completely lost the feminine gender. According to Marit Westergaard , approximately 80% of nouns in Norwegian are masculine. Norwegian and other Scandinavian languages use a suffix to indicate definiteness of

14874-442: The time. However, opponents of the official policy still managed to create a massive protest movement against Samnorsk in the 1950s, fighting in particular the use of "radical" forms in Bokmål text books in schools. In the reform in 1959, the 1938 reform was partially reversed in Bokmål, but Nynorsk was changed further towards Bokmål. Since then Bokmål has reverted even further toward traditional Riksmål, while Nynorsk still adheres to

15008-534: The toll ring. However, a lack of funds made it necessary to build the line to Nesttun only, instead of all the way to the airport. The initial decision was taken by Bergen City Council on 13 March 2000, in the Parliament of Norway in 2002, and with the financing secured, by the city council in 2005. Only the Progress Party and the Pensioners' Party voted against light rail. Forty per cent is financed by

15142-552: The toll road ring, based on the Bergen Program . Ownership, maintenance and further extensions and vehicles are the responsibility of Hordaland County Municipality through its wholly owned subsidiary Bybanen AS. Operation is governed by public service obligation contracts issued by the county public transport authority Skyss . From 2010 to 2017 the line and its 20 Variobahn trams were operated by Keolis Norge (formerly Fjord1 Partner). The first public transport in Bergen

15276-474: The tolls would continue to be collected and used to finance a bridge across Salhusfjorden. This was opposed by a group of locals, who brought the issue to the courts, claiming it to be illegal, as a bridge would never be built. Both Oslo District Court and Eidsivating Court of Appeal concluded that the tolls were legal, and the issue was rejected by the Supreme Court . Protests were also raised against

15410-410: The trams always stop at all stops. Between the seats there is a minimum width of 720 mm (2 ft 4 in), which allows wheelchair and buggy access along the full length of the car. All stations are announced visually and orally. The trams have wireless Internet access . However, it is reserved for the onboard Infotainment system. All stations are announced with a short distinctive melody and

15544-572: The trams send a signal to the traffic light control when the driver starts the door-closing signal to give the tram priority at traffic lights. The depot is at Kronstad, at a former yard used by the Norwegian State Railways , where a track that connects the light rail network to the Bergen Line. The depot was finished in 2009, and has room for 16 40-meter (131 ft 3 in) trams plus a workshop with space for two trams and

15678-403: The two trams to be repaired. This caused the summer schedule to be reduced to a 30-minute headway. From 1 November, the line started running every six minutes during the rush hour. On 22 June, the first part of the line was officially opened by Queen Sonja of Norway . The first part of line number 1 is 9.8-kilometre (6.09 mi) and runs from the city center to Nesttun. The northernmost part of

15812-426: The unofficial Høgnorsk is more conservative than Nynorsk and is far closer to Faroese , Icelandic and Old Norse . Norwegians are educated in both Bokmål and Nynorsk. Each student gets assigned a native form based on which school they go to, whence the other form (known as Sidemål ) will be a mandatory school subject from elementary school through high school. For instance, a Norwegian whose main language form

15946-401: The use of a pontoon bridge, as it would limit the vessel size and thus the commercial development in the inner parts of the fjord. In the 1970s, National Road 1 (today part of E39) was established through Knarvik towards Sognefjorden , resulting in upgrades to the roads in Nordhordland, and making the crossing one of the main routes from the north. At the same time, it was decided to establish

16080-447: The vocabulary coincides with Bokmål. Outside Eastern Norway , this spoken variation is not used. From the 16th to the 19th centuries, Danish was the standard written language of Norway. As a result, the development of modern written Norwegian has been subject to strong controversy related to nationalism , rural versus urban discourse, and Norway's literary history. Historically, Bokmål is a Norwegianised variety of Danish, while Nynorsk

16214-568: The word, e.g.: for ('for/to'), fór ('went'), fòr ('furrow') and fôr ('fodder'). Loanwords may be spelled with other diacritics, most notably ï, ü , á and à . The two legally recognized forms of written Norwegian are Bokmål (literally 'book tongue') and Nynorsk ('new Norwegian'), which are regulated by the Language Council of Norway ( Språkrådet ). Two other written forms without official status also exist. One, called Riksmål ('national language'),

16348-472: Was NOK 910 million. Part of the contract payment was subject to a court case which the contractors lost. The bridge opened on 22 September 1994, and remained a toll road until 31 December 2005. In 2014, it had an average daily traffic of 16,580 vehicles. Tolls were reinstated on the bridge in 2019 to finance other road projects in the area. The bridge is the second-longest in Norway, and the second pontoon bridge in Norway. The bridge consists of three sections,

16482-412: Was built for cars, and the oldest was upgraded and used by the light rail line. In several places the road needed to be dug up to remove pipes and cables. In November 2009, Gulating Court of Appeal ruled that the power company BKK had to pay 80 million NOK for the moving of power lines, and could not charge the costs to the project. By June 2008, the first tracks had been laid. Four companies bid for

16616-399: Was chosen instead of an A pylon both because it was more functional, and would be more aesthetic in conjunction with the other bridges in the area, particularly three suspension bridges. The technology for the bridge was based on recent technology for pontoon bridges combined with Norwegian offshore technology. Among the technologies initially considered, but later ruled out, was that used in

16750-457: Was demolished to make room for a temporary bus terminal that would allow Kaigaten to be closed for construction. Contracts for building the line were awarded to Svein Boasson, NCC Construction , Fyllingen Maskinstasjon and Veidekke Entreprenør . The contract for laying the tracks was awarded to Baneservice . Construction started in January 2008. To pass over Strømmen , a fourth Nygård Bridge

16884-758: Was developed based upon a collective of spoken Norwegian dialects. Norwegian is one of the two official languages in Norway, along with Sámi , a Finno-Ugric language spoken by less than one percent of the population. Norwegian is one of the working languages of the Nordic Council . Under the Nordic Language Convention , citizens of the Nordic countries who speak Norwegian have the opportunity to use it when interacting with official bodies in other Nordic countries without being liable for any interpretation or translation costs. Like most of

17018-764: Was disregarded by the Public Roads Administration . In 1995, the municipal bus company Bergen Sporvei made a proposal to establish what they called the Lightning Tram, from Varden in Fyllingsdalen via a tunnel to Møhlenpris and the city center, then make a 120° turn and return along the route of the Bergen trolleybus to Birkelundstoppen . The same year, the Norwegian Society for the Conservation of Nature proposed

17152-417: Was introduced. Because of delays from Stadler's subcontractors, five instead of eight trams were available when the line opened on 22 June 2010. Skyss had planned to operate with a ten-minute headway until August, but had a 15-minute headway until 16 August. To compensate, none of the parallel bus routes ceased until then. On 7 June, two trams collided at low speed at Byparken, causing a derailment and forced

17286-419: Was necessary to heat the steel to 150 °C (302 °F) before and after welding, and Kværner had problems finding an adequate process during late 1992. In January 1993, an appropriate process had been found, although experimentation with various methods continued for another six months. Kværner felt that the Public Roads Administration should bear the extra costs, demanding NOK 108 million in compensation, but

17420-453: Was severely damaged, causing a delay in the project. As the bridge had the longest laterally unsupported span in the world, the construction was watched by many international delegations. The construction of the bridge also involved other investments in road infrastructure. This included 5.7 kilometers (3.5 mi) of new highways, 4.2 kilometers (2.6 mi) of local roads, and the 785-meter (2,575 ft) long Hordvik Tunnel just south of

17554-408: Was that there was sufficient available land at Kokstad which allowed a large depot to be constructed there. During the first years, there was a small depot at Kronstad, which got to small after the second extension. The track between Lagunen and Birkelandsskiftet was officially opened on 15 August 2016. The last part of the track was awaiting the opening of the new terminal building of Bergen airport, as

17688-481: Was the Bergen Tramway , which operated between 1897 and 1965. It was limited to the inner parts of the city and did not reach the suburbs. The city council therefore decided to close it, arguing that the future lay in private cars, diesel buses and trolleybuses . In the 1960s, the removal on restriction on car sales created more traffic than the roads could handle and consequently both buses and cars began increasingly being stuck in rush-hour queues . The municipality and

17822-493: Was the most heavily trafficked railway in the country, with a travel time between 20 and 27 minutes. There were up to 27 trains per day, of which five continued to Garnes . In 1918, the line was proposed for doubling and electrification : the latter was completed in 1954. The same year, annual ridership were down to 870,000 passengers. After the opening of the Ulriken Tunnel commuter trains were kept for six months, with

17956-451: Was used for the waterway, NOK 115 million was used on planning, and NOK 176 million was used on auxiliary roads and the tunnel. The bridge was financed with NOK 41 million in state grants, NOK 139 million from tolls paid in advance, and NOK 730 million in debt which would be repaid by the tolls. Interest during construction cost NOK 138 million. The construction involved 1,150,000 man-hours. The use of high-strength steel caused problems as it