Misplaced Pages

Fort McHenry Tunnel

Article snapshot taken from Wikipedia with creative commons attribution-sharealike license. Give it a read and then ask your questions in the chat. We can research this topic together.

The Fort McHenry Tunnel is a four-tube, bi-directional tunnel that carries traffic on Interstate 95 (I-95) underneath the Baltimore Harbor . Named for nearby Fort McHenry , the tunnel is the lowest point in the Interstate Highway System under water.

#533466

81-671: Construction began in May 1980; the tunnel opened on November 23, 1985. Having consumed some $ 750 million (equivalent to $ 2.1 billion in 2023), it was the most expensive Interstate project until surpassed by the Big Dig in Boston . As of 2009, it was used by 43.4 million vehicles annually. Tolls are collected in both directions. The toll for cars is $ 3 with a Maryland E-ZPass and $ 4 with another state's E-ZPass. Vehicles without an E-ZPass pay more, as do those with more than two axles—up to $ 45 for

162-748: A 6+ axle vehicle without an E-ZPass. All-electronic tolling using E-ZPass or toll-by-plate started in March 2020 as a result of the COVID-19 pandemic and was made permanent in August 2020. A project to demolish the toll plaza and replace it with overhead gantries for open road tolling started in 2022. The tunnel crosses the Patapsco River , just south of Fort McHenry; it connects the Locust Point and Canton areas of Baltimore City . Plans for

243-587: A Third Harbor Tunnel plan that was hugely controversial in its own right, because it would have disrupted the Maverick Square area of East Boston . It was never built. A major reason for the all-day congestion was that the Central Artery carried not only north–south traffic, but it also carried east–west traffic. Boston's Logan Airport lies across Boston Harbor in East Boston; and before

324-650: A bust of shipbuilder Donald McKay in East Boston ; blue interior lighting of the Zakim Bridge; and the Miller's River Littoral Way walkway and lighting under the loop ramps north of the Charles River . Extensive landscape planting, as well as a maintenance program to support the plantings, was requested by many community members during public meetings. The Big Dig separated the co-mingled traffic from

405-749: A gap in I-95 through Maryland. Soon after the Fort McHenry Tunnel opened, the nearby Baltimore Harbor Tunnel , which had opened to traffic in 1957, was extensively rehabilitated. The Fort McHenry Tunnel continues to be a vital transportation link in the Mid-Atlantic region. After the Francis Scott Key Bridge collapsed on March 26, 2024, the tunnel became one of the primary alternate routes for drivers and trucks containing non-hazardous loads. Big Dig The Big Dig

486-399: A number of state-of-the-art construction techniques. Because the old elevated highway (which remained in operation throughout the construction process) rested on pylons located throughout the designated dig area, engineers first utilized slurry wall techniques to create 120-foot-deep (37 m) concrete walls upon which the highway could rest. These concrete walls also stabilized the sides of

567-478: A second crossing of the Baltimore Harbor that would become the Fort McHenry Tunnel began in the late 1960s. Early plans called for an 8-lane double-deck bridge to carry I-95 over the harbor just south of Fort McHenry. In 1975, plans were changed to a tunnel after it was determined that a bridge would hurt Fort McHenry's status as a national monument. The state of Maryland originally intended to build

648-402: A short portion of I-93, but additional lanes and direct connections are provided for this traffic. The result was a 62% reduction in vehicle hours of travel on I-93, the airport tunnels, and the connection from Storrow Drive, from an average 38,200 hours per day before construction (1994–1995) to 14,800 hours per day in 2004–2005, after the project was largely complete. The savings for travelers

729-500: A targeted completion of 2022. It is working on the new Dallas Fort Worth International Airport Southwest End-Around Taxiway, with an expected completion date of 2021. In 2018, it started working on a master plan update for San Antonio International Airport . Parsons Brinckerhoff partnered with rival engineering firm Bechtel to build the troubled Big Dig in Boston, Massachusetts. The Big Dig, or Central Artery/Tunnel project as it

810-510: A traditional cut-and-cover method had been applied. Other challenges included existing subway tunnels crossing the path of the underground highway. To build slurry walls past these tunnels, it was necessary to dig beneath the tunnels and to build an underground concrete bridge to support the tunnels' weight, without interrupting rail service. The project was managed by the Massachusetts Turnpike Authority, with

891-474: A year by increasing economic productivity and decreasing motor vehicle operating costs. That study did not look at highways outside the Big Dig construction area and did not take into account new congestion elsewhere. Towards the end of the Big Dig in 2003, it was estimated that the demolition of the Central Artery highway would cause a $ 732 million increase in property value in Boston's financial district, with

SECTION 10

#1732775674534

972-477: Is an American multinational engineering and design firm. The firm operates in the fields of strategic consulting, planning, engineering, construction management, energy, infrastructure and community planning. It is a subsidiary of WSP Global . In 2013, the company was named the tenth largest U.S.-based engineering/design firm by Engineering News Record . In 2020, it was ranked #7 of the Top 500 Design Firms and #2 of

1053-733: Is involved in Long Island Rail Road 's East Side Access to Grand Central Terminal in New York City , with a planned opening of December 2022. It is also involved with the redevelopment of LaGuardia Airport in New York City, announced in 2015, with an expected completion date of 2022. In 2018, it was selected as the lead firm for the Charlotte Douglas International Airport Airfield Expansion, with

1134-579: Is now called WSP. Following the acquisition of Louis Berger Group by WSP Global in 2018 for $ 400 million, the operations of Louis Berger Group in the United States were merged with WSP USA's. WSP USA acquired two US-based environmental consulting firms over the next two years: Ecology & Environment (E & E) in 2019, and LT Environmental in 2020. In 2021, WSP purchased Golder Associates, and in 2022 WSP acquired Wood PLC’s Environment & Infrastructure Solutions, Inc. business. The firm

1215-603: Is supported by two forked towers connected to the span by cables and girders. It was the first bridge in the country to employ this method and it was, at the time, the widest cable-stayed bridge in the world, having since been surpassed by the Eastern span replacement of the San Francisco–Oakland Bay Bridge . Meanwhile, construction continued on the Tobin Bridge approach. By the time all parties agreed on

1296-752: The American Recovery and Reinvestment Act of 2009 . Nashua Street Park on the Boston side was completed in 2003, by McCourt Construction with $ 7.9 million in funding from MassDOT. As of 2017, $ 30.5 million had been transferred to the Massachusetts Department of Conservation and Recreation to complete five projects. Another incomplete but required project is the South Bank Bridge over the MBTA Commuter Rail tracks at North Station (connecting Nashua Street Park to

1377-540: The Charles River crossing had been a source of major controversy throughout the design phase of the project. Many environmental advocates preferred a river crossing entirely in tunnels, but this, along with 27 other plans, was rejected as too costly. Finally, with a deadline looming to begin construction on a separate project that would connect the Tobin Bridge to the Charles River crossing, Salvucci overrode

1458-503: The Charles River , created the Rose Kennedy Greenway in the space vacated by the previous I-93 elevated roadway, and funded more than a dozen projects to improve the region's public transportation system. Planning for the project began in 1982; the construction work was carried out between 1991 and 2006; and the project concluded on December 31, 2007. The project's general contractor was Bechtel and Parsons Brinckerhoff

1539-794: The Charles River Dam and lock, a maintenance facility, and a planned pedestrian walkway across the Charles River next to the MBTA Commuter Rail drawbridge at North Station (connecting Nashua Street Park and North Point Park). MassDOT is funding the South Bank Park, and replacement of the North Washington Street Bridge (construction Aug 2018–23). EF Education is funding public greenspace improvements as part of its three-phase expansion at North Point. Remaining funding may be used to construct

1620-1214: The Hampton Roads Bridge-Tunnel in Virginia (1957); the Pell Bridge in Newport, Rhode Island (1969); the Strategic Petroleum Reserve (United States) (1980); the I-95 / Fort McHenry Tunnel (1980); the U.S. 25E Cumberland Gap Tunnel at the Tennessee/Kentucky border, the H-3 Highway in Oahu, Hawaii (1997); the Sabiya Power Station in Kuwait (2000) and the rapid transit systems of San Francisco (1972); Atlanta (1979); Singapore (1987); Taipei (1996); and Caracas (1983). Parsons Brinckerhoff

1701-599: The North-South Rail Link , which would have connected North and South Stations (the major passenger train stations in Boston), but this aspect of the project was ultimately dropped by the state transportation administration early in the Dukakis administration. Negotiations with the federal government had led to an agreement to widen some of the lanes in the new harbor tunnel, and accommodating these would require

SECTION 20

#1732775674534

1782-625: The Red and Blue subway lines, and to restore the Green Line streetcar service to the Arborway in Jamaica Plain have not been completed. The Red and Blue subway line connection underwent initial design, but no funding has been designated for the project. The Arborway Line restoration has been abandoned, following a final court decision in 2011. The original Big Dig plan also included

1863-480: The Artery Arts Program was seen as a potential liability, even though there was support and interest from the public and professional arts organizations in the area. At the beginning of the highway design process, a temporary arts program was initiated, and over 50 proposals were selected. However, development began on only a few projects before funding for the program was cut. Permanent public art that

1944-536: The Big Dig and the Turnpike's Boston Extension from the 1960s being financially and legally joined by the legislature as the Metropolitan Highway System . Design and construction was supervised by a joint venture of Bechtel Corporation and Parsons Brinckerhoff . Because of the enormous size of the project—too large for any company to undertake alone—the design and construction of the Big Dig

2025-648: The Big Dig was passed by the US Congress , but it was vetoed by President Ronald Reagan for being too expensive. When Congress overrode the veto, the project had its green light and ground was first broken in 1991. In 1997, the state legislature created the Metropolitan Highway System and transferred responsibility for the Central Artery and Tunnel "CA/T" Project from the Massachusetts Highway Department and

2106-590: The Big Dig, the only access to the airport from downtown was through the paired Callahan and Sumner tunnels. Traffic on the major highways from west of Boston—the Massachusetts Turnpike and Storrow Drive —mostly traveled on portions of the Central Artery to reach these tunnels. Getting between the Central Artery and the tunnels involved short diversions onto city streets, increasing local congestion. A number of public transportation projects were included as part of an environmental mitigation for

2187-644: The Big Dig. The most expensive was the building of the Phase II Silver Line tunnel under Fort Point Channel , done in coordination with Big Dig construction. Silver Line buses now use this tunnel and the Ted Williams Tunnel to link South Station and Logan Airport. Construction of the MBTA Green Line extension beyond Lechmere to Medford/Tufts station opened on December 12, 2022. As of 2023 , promised projects to connect

2268-680: The Central Artery became chronically gridlocked. The Sargent moratorium led to the rerouting of I-95 away from Boston around the Route ;128 beltway and the conversion of the cleared land in the southern part of the city into the Southwest Corridor linear park , as well as a new right-of-way for the Orange Line subway and Amtrak . Parts of the planned I-695 right-of-way remain unused and under consideration for future mass-transit projects. The original 1948 Master Plan included

2349-484: The Central Artery, an elevated expressway which eventually was constructed between the downtown area and the waterfront. Governor John Volpe interceded in the 1950s to change the design of the last section of the Central Artery, putting it underground through the Dewey Square Tunnel . While traffic moved somewhat better, the other problems remained. There was chronic congestion on the Central Artery (I-93),

2430-709: The I-93 design, construction of the Tobin connector (today known as the "City Square Tunnel" for a Charlestown area it bypasses) was far along, significantly adding to the cost of constructing the US Route 1 interchange and retrofitting the tunnel. Boston blue clay and other soils extracted from the path of the tunnel were used to cap many local landfills , fill in the Granite Rail Quarry in Quincy , and restore

2511-604: The Inner Belt, was subsequently renamed Interstate 695 . (The law establishing the Interstate highway system was enacted in 1956.) The Inner Belt District was to pass to the west of the downtown core, through the neighborhood of Roxbury and the cities of Brookline , Cambridge , and Somerville . Earlier controversies over impact of the Boston extension of the Massachusetts Turnpike , particularly on

Fort McHenry Tunnel - Misplaced Pages Continue

2592-454: The MTA's representative. Eventually, MTA combined some of its employees with joint venture employees in an integrated project organization. This was intended to make management more efficient, but it hindered MTA's ability to independently oversee project activities because MTA and the joint venture had effectively become partners in the project. In addition to political and financial difficulties,

2673-545: The Massachusetts Governor's Office to the Massachusetts Turnpike Authority (MTA). The MTA, which had little experience in managing an undertaking of the scope and magnitude of the CA/T Project, hired a joint venture to provide preliminary designs, manage design consultants and construction contractors, track the project's cost and schedule, advise MTA on project decisions, and (in some instances) act as

2754-598: The Massachusetts Turnpike and the Sumner and Callahan tunnels. While only one net lane in each direction was added to the north–south I-93, several new east–west lanes became available. East–west traffic on the Massachusetts Turnpike/I-90 now proceeds directly through the Ted Williams Tunnel to Logan Airport and Route 1A beyond. Traffic between Storrow Drive and the Callahan and Sumner Tunnels still uses

2835-805: The North Point Inlet pedestrian bridge, and a pedestrian walkway over Leverett Circle . Before being replaced with surface access during the reconstruction of the Science Park MBTA Green Line station, Leverett Circle had pedestrian bridges with stairs that provided elevated access between the station, the Charles River Parks, and the sidewalk to the Boston Museum of Science . The replacement ramps would comply with Americans with Disabilities Act requirements and allow easy travel by wheelchair or bicycle over

2916-578: The Top 100 Pure Designers by the same magazine. On October 31, 2014, Parsons Brinckerhoff became a wholly owned independent subsidiary of WSP Global , a Canadian-based professional services firm. Parsons Brinckerhoff was renamed to WSP|Parsons Brinckerhoff, then to WSP in 2017. Part of WSP Global, WSP USA is one of the largest professional services firms in the world, with approximately 31,500 employees in 500 offices serving 39 countries. Founded in 1885 in New York City by civil engineer William Barclay Parsons , among Parsons Brinckerhoff's earliest projects

2997-460: The busy intersection. While not a legally mandated requirement, public art was part of the urban design planning process (and later design development work) through the Artery Arts Program. The intent of the program was to integrate public art into highway infrastructure (retaining walls, fences, and lighting) and the essential elements of the pedestrian environment (walkways, park landscape elements, and bridges). As overall project costs increased,

3078-521: The circle. All southbound lanes of I-93 opened to traffic on March 5, 2005, including the left lane of the Zakim Bridge, and all of the refurbished Dewey Square Tunnel . By the end of December 2004, 95% of the Big Dig was completed. Major construction remained on the surface, including construction of final ramp configurations in the North End and in the South Bay interchange, and reconstruction of

3159-451: The city, not reduced or eliminated (although some trips are now faster). The report states, "Ultimately, many motorists going to and from the suburbs at peak rush hours are spending more time stuck in traffic, not less." The Globe also asserted that their analysis provides a fuller picture of the traffic situation than a state-commissioned study done two years earlier, in which the Big Dig was credited with helping to save at least $ 167 million

3240-591: The decades passed and other planned expressways were cancelled, continually escalating vehicular traffic that was well beyond its design capacity. Local businesses again wanted relief, city leaders sought a reuniting of the waterfront with the city, and nearby residents desired removal of the matte green-painted elevated road which mayor Thomas Menino called Boston's "other Green Monster " (as an unfavorable comparison to Fenway Park 's famed left-field wall). MIT engineers Bill Reynolds and (eventual state Secretary of Transportation) Frederick P. Salvucci envisioned moving

3321-400: The eastbound lanes on January 19. The next phase, moving the elevated Interstate 93 underground, was completed in two stages: northbound lanes opened on March 29, 2003, and southbound lanes (in a temporary configuration) on December 20, 2003. A tunnel underneath Leverett Circle connecting eastbound Storrow Drive to I-93 North and the Tobin Bridge opened December 19, 2004, easing congestion at

Fort McHenry Tunnel - Misplaced Pages Continue

3402-524: The elevated six-lane highway through the center of downtown Boston, which was, in the words of Pete Sigmund, "like a funnel full of slowly-moving, or stopped, cars (and swearing motorists)." In 1959, the 1.5-mile-long (2.4 km) road section carried approximately 75,000 vehicles a day, but by the 1990s, this had grown to 190,000 vehicles a day. Traffic jams of 16 hours were predicted for 2010. The expressway had tight turns, an excessive number of entrances and exits, entrance ramps without merge lanes, and as

3483-435: The excavation and the possibility of disrupting the homes of millions of rats , causing them to roam the streets of Boston in search of new housing. By the time the federal environmental clearances were delivered in 1994, the process had taken some seven years, during which time inflation greatly increased the project's original cost estimates. Reworking such a busy corridor without seriously restricting traffic flow required

3564-450: The excavation to take place below. Construction crews also used ground freezing (an artificial induction of permafrost ) to help stabilize surrounding ground as they excavated the tunnel. This was the largest tunneling project undertaken beneath railroad lines anywhere in the world. The ground freezing enabled safer, more efficient excavation , and also assisted in environmental issues, as less contaminated fill needed to be exported than if

3645-733: The firm. He is known for his co-invention of the third rail. The firm has worked on some of the most notable infrastructure projects of the 20th century, including: the Detroit–Windsor Tunnel (1930); the Scheldt Tunnel in Antwerp , Belgium (1933); The Buzzards Bay Railroad Bridge on Cape Cod, Massachusetts (1935); The 1939 World's Fair in New York City; the Garden State Parkway in New Jersey (1957);

3726-514: The heavily populated neighborhood of Brighton , and the additional large amount of housing that would have had to be destroyed led to massive community opposition to both the Inner Belt and the Boston section of I-95. By 1970, building demolition and land clearances had been completed along the I-95 right of way through the neighborhoods of Roxbury, Jamaica Plain , the South End and Roslindale , which led to secession threats by Hyde Park , Boston's youngest and southernmost neighborhood (which I-95

3807-526: The impact of the Central Artery/Tunnel Project on the community, representing the neighborhoods to government agencies, keeping the community informed, developing a list of priorities of immediate neighborhood concerns, and promoting responsible and appropriate development of the post-construction artery corridor in the North End and Waterfront neighborhoods. The political, financial and residential obstacles were magnified when several environmental and engineering obstacles occurred. The downtown area through which

3888-455: The mainline roadway. The Connector ultimately used a pair of ramps that had been constructed for Interstate 695 , enabling the mainline I-93 to carry more traffic that would have used I-695 under the original Master Plan. When construction began, the project cost, including the Charles River crossing, was estimated at $ 5.8 billion. Eventual cost overruns were so high that the chairman of the Massachusetts Turnpike Authority, James Kerasiotes ,

3969-436: The objections and chose a variant of the plan known as "Scheme Z". This plan was considered to be reasonably cost-effective, but had the drawback of requiring highway ramps stacked up as high as 100 feet (30 m) immediately adjacent to the Charles River. The city of Cambridge objected to the visual impact of the chosen Charles River crossing design. The city sued to revoke the project's environmental certificate and forced

4050-401: The opening ceremony was held for the I-90 Connector Tunnel, extending the Massachusetts Turnpike (Interstate 90) east into the Ted Williams Tunnel , and onwards to Boston Logan International Airport . The Ted Williams tunnel had been completed and was in limited use for commercial traffic and high-occupancy vehicles since late 1995. The westbound lanes opened on the afternoon of January 18 and

4131-413: The original project plan were dropped due to the massive cost overruns on the highway portion of the project. $ 99.1 million was allocated for mitigating improvements to the Charles River Basin , including the construction of North Point Park in Cambridge and Paul Revere Park in Charlestown. The North Bank Bridge, providing pedestrian and bicycle connectivity between the parks, was not funded until

SECTION 50

#1732775674534

4212-431: The poor construction, it has been estimated that the Big Dig's life span will be far short of the original specification that taxpayers paid for. The tunnels still have "thousands of leaks" and substandard materials. Subsequent to the fatal tunnel ceiling collapse, light fixtures have been found to have been incorrectly installed and corroding, posing a risk of failure and falling to the tunnel roadway. Parsons Brinckerhoff

4293-439: The project planners to redesign the river crossing again. Swiss engineer Christian Menn took over the design of the bridge. He suggested a cradle cable-stayed bridge that would carry ten lanes of traffic. The plan was accepted and construction began on the Leonard P. Zakim Bunker Hill Memorial Bridge . The bridge employed an asymmetrical design and a hybrid of steel and concrete was used to construct it. The distinctive bridge

4374-453: The project received resistance from residents of Boston's historic North End, who in the 1950s had seen 20% of the neighborhood's businesses displaced by development of the Central Artery. In 1993, the North End Waterfront Central Artery Committee (NEWCAC) created, co-founded by Nancy Caruso, representing residents, businesses, and institutions in the North End and Waterfront neighborhoods of Boston. The NEWCAC Committee's goal included lessening

4455-414: The project was completed in December 2007 at a cost of over $ 8.08 billion (in 1982 dollars, $ 21.5 billion adjusted for inflation), a cost overrun of about 190%. As a result of a death, leaks, and other design flaws, the Parsons Brinckerhoff and Bechtel consortium agreed to pay $ 407 million in restitution and several smaller companies agreed to pay a combined sum of approximately $ 51 million. This project

4536-441: The proposed South Bank Park, which is currently a parking lot under the Zakim Bridge at the Charles River locks). Improvements in the lower Charles River Basin include the new walkway at Lovejoy Wharf (constructed by the developer of 160 North Washington Street, the new headquarters of Converse ), the Lynch Family Skate Park (constructed in 2015 by the Charles River Conservancy), rehabilitation of historic operations buildings for

4617-439: The replacement parks providing an additional $ 252 million in value. Additionally, as a result of the Big Dig, a large amount of waterfront space was opened up, which is now a high-rent residential and commercial area called the Seaport District . The development of Seaport alone was estimated to create $ 7 billion in private investment and 43,000 jobs. Parsons Brinckerhoff WSP USA , formerly Parsons Brinckerhoff ,

4698-422: The site, preventing cave-ins during the continued excavation process. The multi-lane Interstate highway also had to pass under South Station 's seven railroad tracks, which carried over 40,000 commuters and 400 trains per day. To avoid multiple relocations of train lines while the tunneling advanced, as had been initially planned, a specially designed jack was constructed to support the ground and tracks to allow

4779-464: The surface of Spectacle Island in the Boston Harbor Islands National Recreation Area . The Storrow Drive Connector , a companion bridge to the Zakim, began carrying traffic from I-93 to Storrow Drive in 1999. The project had been under consideration for years, but was opposed by the wealthy residents of the Beacon Hill neighborhood. However, it finally was accepted because it would funnel traffic bound for Storrow Drive and downtown Boston away from

4860-420: The surface streets. The final ramp downtown—exit 16A (formerly 20B) from I-93 south to Albany Street —opened January 13, 2006. In 2006, the two Interstate 93 tunnels were dedicated as the Thomas P. O'Neill Jr. Tunnel , after the former Democratic speaker of the House of Representatives from Massachusetts who pushed to have the Big Dig funded by the federal government. The Commonwealth of Massachusetts

4941-408: The tunnel to be deeper and mechanically vented; this left no room for the rail lines, and having diesel trains (then in use) passing through the tunnel would have substantially increased the cost of the ventilation system. The project was conceived in the 1970s by the Boston Transportation Planning Review to replace the rusting elevated six-lane Central Artery. The expressway separated downtown from

SECTION 60

#1732775674534

5022-471: The tunnel with a reinforced concrete box design , but plans were changed in February 1976 to use a steel tubular design after a dispute with the Federal Highway Administration . The tunnel was to be constructed using the immersed tube method , with prefabricated tubes sunken into the harbor. Construction began in May 1980 by K-R-T (a joint venture between Peter Kiewit Sons Company , Raymond International Builders, and Tidewater Construction Corporation), and

5103-517: The tunnel without endangering the existing elevated highway above. Eventually, they created horizontal braces as wide as the tunnel, then cut away the elevated highway's struts, and lowered it onto the new braces. Three alternative construction methods were studied with their corresponding structural design to address existing conditions, safety measures, and constructability. In addition to codified loads, construction loads were computed to support final design and field execution . On January 18, 2003,

5184-542: The tunnels were to be dug was largely land fill , and included existing Red Line and Blue Line subway tunnels as well as innumerable pipes and utility lines that would have to be replaced or moved. Tunnel workers encountered many unexpected geological and archaeological barriers, ranging from glacial debris to foundations of buried houses and a number of sunken ships lying within the reclaimed land. The project received approval from state environmental agencies in 1991, after satisfying concerns including release of toxins by

5265-415: The waterfront, and was increasingly choked with bumper-to-bumper traffic. Business leaders were more concerned about access to Logan Airport , and pushed instead for a third harbor tunnel. Planning for the Big Dig as a project officially began in 1982, with environmental impact studies starting in 1983. After years of extensive lobbying for federal dollars, a 1987 public works bill appropriating funding for

5346-409: The whole expressway underground. Another important motivation for the final form of the Big Dig was the abandonment of the Massachusetts Department of Public Works' intended expressway system through and around Boston. The Central Artery, as part of Mass. DPW's Master Plan of 1948, was originally planned to be the downtown Boston stretch of Interstate 95 , and was signed as such; a bypass road called

5427-429: Was a megaproject in Boston that rerouted the then elevated Central Artery of Interstate 93 that cut across Boston into the O'Neill Tunnel and built the Ted Williams Tunnel to extend Interstate 90 to Logan International Airport . Those two projects were the origin of the official name, the Central Artery/Tunnel Project ( CA/T Project ). Additionally, the project constructed the Zakim Bunker Hill Bridge over

5508-431: Was acquired by Balfour Beatty in October 2009 and operated as a wholly owned subsidiary of the Balfour Beatty plc. In October 2010 Balfour Beatty acquired Halsall Associates, which became a subsidiary of Parsons Brinckerhoff and part of its Canadian operations. On October 31, 2014, Balfour Beatty sold Parsons Brinckerhoff to WSP Global . In 2017 Parsons Brinckerhoff changed its name to WSP USA. On September 3, 2014, it

5589-458: Was also slated to go through). By 1972, with relatively little work done on the Southwest Corridor portion of I-95 and none on the potentially massively disruptive Inner Belt, Governor Francis Sargent put a moratorium on highway construction within the Route 128 corridor, except for the final short stretch of Interstate 93. In 1974, the remainder of the Master Plan was canceled. With ever-increasing traffic volumes funneled onto I-93 alone,

5670-441: Was also the lead engineering firm to build the Silver Spring, Maryland transportation center. Despite a ballooning budget and a project that has run far behind schedule, the transit center was poorly constructed and has not become operational due to poor design and workmanship. In April 2014, The Washington Post published an exposé on Parsons Brinckerhoff's troubled transit center, reporting that an independent report has found that

5751-411: Was announced that WSP Global had made an offer to purchase Parsons Brinckerhoff from Balfour Beatty plc for US$ 1.24 billion. The transaction closed on October 31, 2014 and Parsons Brinckerhoff became a wholly owned subsidiary of WSP Global. On January 10, 2017, it was announced that the brand Parsons Brinckerhoff would be retired and combined into the parent company, WSP Global. WSP|Parsons Brinckerhoff

5832-515: Was broken up into dozens of smaller subprojects with well-defined interfaces between contractors. Major heavy-construction contractors on the project included Jay Cashman , Modern Continental , Obayashi Corporation , Perini Corporation , Peter Kiewit Sons' Incorporated , J. F. White , and the Slattery division of Skanska USA. (Of those, Modern Continental was awarded the greatest gross value of contracts, joint ventures included.) The nature of

5913-458: Was completed in November 1985. Ninety percent of construction costs were covered by federal funding, while 10 percent came from state funding. The tunnel consists of 32 tube sections, each 82 feet (25 m) wide and 42 feet (13 m) tall. The east and west approaches are 1,600 feet (490 m) and 3,200 feet (980 m) long, respectively. Opened on time and under budget, the tunnel closed

5994-413: Was developed in response to traffic congestion on Boston's historically tangled streets which were laid out centuries before the advent of the automobile . As early as 1930, the city's Planning Board recommended a raised express highway running north–south through the downtown district in order to draw through traffic off the city streets. Commissioner of Public Works William Callahan promoted plans for

6075-443: Was estimated at $ 166 million annually in the same 2004–2005 time frame. Travel times on the Central Artery northbound during the afternoon peak hour were reduced 85.6%. A 2008 Boston Globe report asserted that waiting time for the majority of trips actually increased as a result of demand induced by the increased road capacity. Because more drivers were opting to use the new roads, traffic bottlenecks were only pushed outward from

6156-403: Was fired in 2000. His replacement had to commit to an $ 8.55 billion cap on federal contributions. The total expenses eventually passed $ 15 billion. Interest brought this cost to $ 21.93 billion. Several unusual engineering challenges arose during the project, requiring unusual solutions and methods to address them. At the beginning of the project, engineers had to figure out the safest way to build

6237-407: Was funded includes: super graphic text and facades of former West End houses cast into the concrete elevated highway abutment support walls near North Station by artist Sheila Levrant de Bretteville ; Harbor Fog, a sensor-activated mist, light and sound sculptural environment by artist Ross Miller in parcel 17; a historical sculpture celebrating the 18th and 19th century shipbuilding industry and

6318-534: Was officially known, was intended to replace an elevated Interstate freeway and connecting roads with a tunnel system underneath Boston. The project was beset with bad engineering, shoddy workmanship, and the death of an automobile passenger as a poor ceiling design caused a tunnel roof section to collapse on a car in the tunnel, crushing the victim. The Big Dig was years over schedule and engineering costs to several times of Bechtel/Parsons Brinckerhoff's original estimates, from $ 8 Billion to in excess of $ 24 Billion. Due to

6399-616: Was required under the Federal Clean Air Act to mitigate air pollution generated by the highway improvements. Secretary of Transportation Fred Salvucci signed an agreement with the Conservation Law Foundation in 1990 enumerating 14 specific projects the state agreed to build. This list was affirmed in a 1992 lawsuit settlement. Projects which have been completed include: However, some projects were removed: Some surface treatments that were part of

6480-606: Was the original IRT line of the New York City Subway , designed by Parsons Brinckerhoff and opened in 1904. Parsons Brinckerhoff also designed the Cape Cod Canal , which opened in 1914 and charted the course of a railway in China from Hankow (Wuhan) to Canton (Guangzhou), a line that is also still in use today. In 1906, Henry M. Brinckerhoff , a highway engineer, brought his expertise in electric railways to

6561-619: Was the engineer, who worked as a consortium, both overseen by the Massachusetts Highway Department . The Big Dig was the most expensive highway project in the United States, and was plagued by cost overruns , delays, leaks, design flaws, accusations of poor execution and use of substandard materials, criminal charges and arrests, and the death of one motorist. The project was originally scheduled to be completed in 1998 at an estimated cost of $ 2.8 billion (US$ 7.4 billion adjusted for inflation as of 2020 ). However,

#533466