59°48′N 010°22′E / 59.800°N 10.367°E / 59.800; 10.367
65-564: Lieråsen Tunnel is a single-tubed railway tunnel of the Drammen Line situated in Asker and Lier in Norway . At a length of 10.723 kilometers (6.663 mi), the double track tunnel is located immediately between Asker Station and Lier Station . It is used for a mix of short- and long-haul passenger trains and freight trains. Construction of the tunnel commenced in 1962, along with
130-695: A canal . The central portions of a rapid transit network are usually in the tunnel. Some tunnels are used as sewers or aqueducts to supply water for consumption or for hydroelectric stations. Utility tunnels are used for routing steam, chilled water, electrical power or telecommunication cables, as well as connecting buildings for convenient passage of people and equipment. Secret tunnels are built for military purposes, or by civilians for smuggling of weapons , contraband , or people . Special tunnels, such as wildlife crossings , are built to allow wildlife to cross human-made barriers safely. Tunnels can be connected together in tunnel networks . A tunnel
195-435: A fire take place mid-way through the tunnel, there would be no possibility to rescue and fire crews to attend the site. As a result, the tunnel received an upgrade in 2003, where a 390-meter (1,280 ft) crosscut was built, an improved ventilation system was installed, along with other upgrades for NOK 800 million. The most expensive part of this was the need for upgrades to the concrete, where water had started to corrode
260-449: A large factor in the decision making process. Civil engineers usually use project management techniques for developing a major structure. Understanding the amount of time the project requires, and the amount of labor and materials needed is a crucial part of project planning. The project duration must be identified using a work breakdown structure and critical path method . Also, the land needed for excavation and construction staging, and
325-458: A net being hung up over the rails to hinder rocks from falling down. The decay was so hard that it was often not possible for NSB to keep up with maintenance. A total replacement of the railway's superstructure was therefore necessary in the early 1990s. As of 1995 there were 97 daily trains carrying 13,000 passengers running through the tunnel. Tunnel safety in case of a fire was also a concern as there were originally no emergency fire exits. Should
390-504: A new section of track between the tunnel and Brakerøya Station . Inadequate geological surveys ahead of construction resulted in the tunnel being built in the middle of an altered and crushed zone, delaying construction and eventually shifting the route 300 meters (980 ft) to the southwest. The tunnel opened on 3 June 1973. In addition to providing double track, it shortened the Drammen Line by 12.4 kilometers (7.7 mi). Part of
455-467: A pipe jack, with the span of some box jacks in excess of 20 metres (66 ft). A cutting head is normally used at the front of the box being jacked, and spoil removal is normally by excavator from within the box. Recent developments of the Jacked Arch and Jacked deck have enabled longer and larger structures to be installed to close accuracy. There are also several approaches to underwater tunnels,
520-510: A pressure wave when trains meet, even though the infrastructure and curvature would allow for higher speeds. Starting 1.5 kilometers (0.93 mi) from the Lier end the tunnel has a slight S-curve with a radius of 1.5 kilometers (0.93 mi). When the Drammen Line opened on 7 October 1872, it was 53.1 kilometers (33.0 mi) long. This was originally a narrow gauge railway, but it was converted to standard gauge and electrified in 1922. The line
585-421: A specialized method called clay-kicking for digging tunnels in clay-based soils. The clay-kicker lies on a plank at a 45-degree angle away from the working face and rather than a mattock with his hands, inserts with his feet a tool with a cup-like rounded end, then turns the tool with his hands to extract a section of soil, which is then placed on the waste extract. Clay-kicking is a specialized method developed in
650-434: A tube can be sunk into a body of water, which is called an immersed tunnel. Cut-and-cover is a simple method of construction for shallow tunnels where a trench is excavated and roofed over with an overhead support system strong enough to carry the load of what is to be built above the tunnel. There are two basic forms of cut-and-cover tunnelling: Shallow tunnels are often of the cut-and-cover type (if under water, of
715-747: A tunnel than a sufficiently strong bridge). Some water crossings are a mixture of bridges and tunnels, such as the Denmark to Sweden link and the Chesapeake Bay Bridge-Tunnel in Virginia . There are particular hazards with tunnels, especially from vehicle fires when combustion gases can asphyxiate users, as happened at the Gotthard Road Tunnel in Switzerland in 2001. One of the worst railway disasters ever,
SECTION 10
#1732779976316780-432: A tunnel. Bridges usually require a larger footprint on each shore than tunnels. In areas with expensive real estate, such as Manhattan and urban Hong Kong , this is a strong factor in favor of a tunnel. Boston's Big Dig project replaced elevated roadways with a tunnel system to increase traffic capacity, hide traffic, reclaim land, redecorate, and reunite the city with the waterfront. The 1934 Queensway Tunnel under
845-553: Is allowed in this tunnel tube, and motorcyclists are directed to the other tube. Each level was built with a three-lane roadway, but only two lanes per level are used – the third serves as a hard shoulder within the tunnel. The A86 Duplex is Europe's longest double-deck tunnel. Oslo West Station Oslo West Station ( Norwegian : Oslo Vestbanestasjon ) or Oslo V , is a former railway station located in Vika in Oslo , Norway . It
910-502: Is dug through surrounding soil, earth or rock, or laid under water, and is usually completely enclosed except for the two portals common at each end, though there may be access and ventilation openings at various points along the length. A pipeline differs significantly from a tunnel, though some recent tunnels have used immersed tube construction techniques rather than traditional tunnel boring methods. A tunnel may be for foot or vehicular road traffic , for rail traffic, or for
975-505: Is intended to carry both the Istanbul metro and a two-level highway, over a length of 6.5 km (4.0 miles). The French A86 Duplex Tunnel [ fr ] in west Paris consists of two bored tunnel tubes, the eastern one of which has two levels for light motorized vehicles, over a length of 10 km (6.2 miles). Although each level offers a physical height of 2.54 m (8.3 ft), only traffic up to 2 m (6.6 ft) tall
1040-494: Is relatively long and narrow; the length is often much greater than twice the diameter , although similar shorter excavations can be constructed, such as cross passages between tunnels. The definition of what constitutes a tunnel can vary widely from source to source. For example, in the United Kingdom, a road tunnel is defined as "a subsurface highway structure enclosed for a length of 150 metres (490 ft) or more." In
1105-401: Is sometimes necessary during the excavation of a tunnel. They are usually circular and go straight down until they reach the level at which the tunnel is going to be built. A shaft normally has concrete walls and is usually built to be permanent. Once the access shafts are complete, TBMs are lowered to the bottom and excavation can start. Shafts are the main entrance in and out of the tunnel until
1170-515: Is that the open building pit is muted after tunnel construction; no roof is placed. Some tunnels are double-deck, for example, the two major segments of the San Francisco–Oakland Bay Bridge (completed in 1936) are linked by a 160-metre (540 ft) double-deck tunnel section through Yerba Buena Island , the largest-diameter bored tunnel in the world. At construction this was a combination bidirectional rail and truck pathway on
1235-698: Is the Siloam Tunnel , built in Jerusalem by the kings of Judah around the 8th century BC. Another tunnel excavated from both ends, maybe the second known, is the Tunnel of Eupalinos , which is a tunnel aqueduct 1,036 m (3,400 ft) long running through Mount Kastro in Samos , Greece. It was built in the 6th century BC to serve as an aqueduct . In Ethiopia , the Siqurto foot tunnel , hand-hewn in
1300-569: The Balvano train disaster , was caused by a train stalling in the Armi tunnel in Italy in 1944, killing 426 passengers. Designers try to reduce these risks by installing emergency ventilation systems or isolated emergency escape tunnels parallel to the main passage. Government funds are often required for the creation of tunnels. When a tunnel is being planned or constructed, economics and politics play
1365-471: The Port Authority of New York and New Jersey was not aware of this bill and had not asked for a grant for such a project. Increased taxes to finance a large project may cause opposition. Tunnels are dug in types of materials varying from soft clay to hard rock. The method of tunnel construction depends on such factors as the ground conditions, the groundwater conditions, the length and diameter of
SECTION 20
#17327799763161430-848: The Queens-Midtown Tunnel between Manhattan and the borough of Queens on Long Island ; the Detroit-Windsor Tunnel between Michigan and Ontario ; and the Elizabeth River tunnels between Norfolk and Portsmouth, Virginia ; the 1934 River Mersey road Queensway Tunnel ; the Western Scheldt Tunnel , Zeeland, Netherlands; and the North Shore Connector tunnel in Pittsburgh, Pennsylvania . The Sydney Harbour Tunnel
1495-472: The River Mersey at Liverpool was chosen over a massively high bridge partly for defense reasons; it was feared that aircraft could destroy a bridge in times of war, not merely impairing road traffic but blocking the river to navigation. Maintenance costs of a massive bridge to allow the world's largest ships to navigate under were considered higher than for a tunnel. Similar conclusions were reached for
1560-679: The United Kingdom of digging tunnels in strong clay-based soil structures. This method of cut and cover construction required relatively little disturbance of property during the renewal of the United Kingdom's then ancient sewerage systems. It was also used during the First World War by Royal Engineer tunnelling companies placing mines beneath German lines, because it was almost silent and so not susceptible to listening methods of detection. Tunnel boring machines (TBMs) and associated back-up systems are used to highly automate
1625-610: The canton of Glarus . The borehole has a diameter of 8.03 metres (26.3 ft). The four TBMs used for excavating the 57-kilometre (35 mi) Gotthard Base Tunnel , in Switzerland , had a diameter of about 9 metres (30 ft). A larger TBM was built to bore the Green Heart Tunnel (Dutch: Tunnel Groene Hart) as part of the HSL-Zuid in the Netherlands, with a diameter of 14.87 metres (48.8 ft). This in turn
1690-489: The water table . This pressurizes the ground ahead of the TBM cutter head to balance the water pressure. The operators work in normal air pressure behind the pressurized compartment, but may occasionally have to enter that compartment to renew or repair the cutters. This requires special precautions, such as local ground treatment or halting the TBM at a position free from water. Despite these difficulties, TBMs are now preferred over
1755-689: The 16th century as a metaphor for a narrow, confined space like the inside of a cask. Some of the earliest tunnels used by humans were paleoburrows excavated by prehistoric mammals. Much of the early technology of tunneling evolved from mining and military engineering . The etymology of the terms "mining" (for mineral extraction or for siege attacks ), " military engineering ", and " civil engineering " reveals these deep historic connections. Predecessors of modern tunnels were adits that transported water for irrigation , drinking, or sewerage . The first qanats are known from before 2000 BC. The earliest tunnel known to have been excavated from both ends
1820-638: The 1960s. The main idea of this method is to use the geological stress of the surrounding rock mass to stabilize the tunnel, by allowing a measured relaxation and stress reassignment into the surrounding rock to prevent full loads becoming imposed on the supports. Based on geotechnical measurements, an optimal cross section is computed. The excavation is protected by a layer of sprayed concrete, commonly referred to as shotcrete . Other support measures can include steel arches, rock bolts, and mesh. Technological developments in sprayed concrete technology have resulted in steel and polypropylene fibers being added to
1885-716: The 1971 Kingsway Tunnel under the Mersey. In Hampton Roads, Virginia , tunnels were chosen over bridges for strategic considerations; in the event of damage, bridges might prevent US Navy vessels from leaving Naval Station Norfolk . Water-crossing tunnels built instead of bridges include the Seikan Tunnel in Japan; the Holland Tunnel and Lincoln Tunnel between New Jersey and Manhattan in New York City ;
1950-489: The Lieråsen Tunnel opened. A short-coming in the tunnel's design was the lack of any lighting, emergency exits or water deviation. Specifically, the lighting made inspection difficult. This was especially important since there was nothing hindering water from dripping down on the tracks, electrical systems and signaling system. This oftentimes caused cracks in the rails and ties. Poor geological conditions resulted in
2015-709: The Middle Ages, crosses a mountain ridge. In the Gaza Strip , the network of tunnels was used by Jewish strategists as rock-cut shelters, in first links to Judean resistance against Roman rule in the Bar Kokhba revolt during the 2nd century AD. A major tunnel project must start with a comprehensive investigation of ground conditions by collecting samples from boreholes and by other geophysical techniques. An informed choice can then be made of machinery and methods for excavation and ground support, which will reduce
Lieråsen Tunnel - Misplaced Pages Continue
2080-599: The United States, the NFPA definition of a tunnel is "An underground structure with a design length greater than 23 m (75 ft) and a diameter greater than 1,800 millimetres (5.9 ft)." The word "tunnel" comes from the Middle English tonnelle , meaning "a net", derived from Old French tonnel , a diminutive of tonne ("cask"). The modern meaning, referring to an underground passageway, evolved in
2145-400: The blocky nature of rocks, the exact location of fault zones, or the stand-up times of softer ground. This may be a particular concern in large-diameter tunnels. To give more information, a pilot tunnel (or "drift tunnel") may be driven ahead of the main excavation. This smaller tunnel is less likely to collapse catastrophically should unexpected conditions be met, and it can be incorporated into
2210-502: The concrete mix to improve lining strength. This creates a natural load-bearing ring, which minimizes the rock's deformation . By special monitoring the NATM method is flexible, even at surprising changes of the geomechanical rock consistency during the tunneling work. The measured rock properties lead to appropriate tools for tunnel strengthening . In pipe jacking , hydraulic jacks are used to push specially made pipes through
2275-492: The entire length of the tunnel needed to be reinforced with concrete. By 1966 the cost estimate for the tunnel reached NOK 454 million, up from 64 million in 1959. Break-through of the main tunnel took place in October 1971. The price ended at NOK 175 million and construction employed up to 250 people on the site. Two workers were killed and two seriously wounded due to a blasting accident on 23 June 1972. The opening of
2340-409: The entire tunnelling process, reducing tunnelling costs. In certain predominantly urban applications, tunnel boring is viewed as a quick and cost-effective alternative to laying surface rails and roads. Expensive compulsory purchase of buildings and land, with potentially lengthy planning inquiries, is eliminated. Disadvantages of TBMs arise from their usually large size – the difficulty of transporting
2405-441: The final tunnel or used as a backup or emergency escape passage. Alternatively, horizontal boreholes may sometimes be drilled ahead of the advancing tunnel face. Other key geotechnical factors: For water crossings, a tunnel is generally more costly to construct than a bridge. However, both navigational and traffic considerations may limit the use of high bridges or drawbridges intersecting with shipping channels, necessitating
2470-405: The ground behind a TBM or shield. This method is commonly used to create tunnels under existing structures, such as roads or railways. Tunnels constructed by pipe jacking are normally small diameter bores with a maximum size of around 3.2 metres (10 ft). Box jacking is similar to pipe jacking, but instead of jacking tubes, a box-shaped tunnel is used. Jacked boxes can be a much larger span than
2535-640: The immersed-tube type), while deep tunnels are excavated, often using a tunnelling shield . For intermediate levels, both methods are possible. Large cut-and-cover boxes are often used for underground metro stations, such as Canary Wharf tube station in London. This construction form generally has two levels, which allows economical arrangements for ticket hall, station platforms, passenger access and emergency egress, ventilation and smoke control, staff rooms, and equipment rooms. The interior of Canary Wharf station has been likened to an underground cathedral, owing to
2600-435: The inevitable smoke and steam. A major disadvantage of cut-and-cover is the widespread disruption generated at the surface level during construction. This, and the availability of electric traction, brought about London Underground's switch to bored tunnels at a deeper level towards the end of the 19th century. Prior to the replacement of manual excavation by the use of boring machines, Victorian tunnel excavators developed
2665-468: The large TBM to the site of tunnel construction, or (alternatively) the high cost of assembling the TBM on-site, often within the confines of the tunnel being constructed. There are a variety of TBM designs that can operate in a variety of conditions, from hard rock to soft water-bearing ground. Some TBMs, the bentonite slurry and earth-pressure balance types, have pressurized compartments at the front end, allowing them to be used in difficult conditions below
Lieråsen Tunnel - Misplaced Pages Continue
2730-539: The latter would give a shorter overall line length. NSB called for prioritizing the Drammen–Hokksund segment if there was not funding for both. Construction involved building a new at-grade line from Brakerøya Station to a new Lier Station and subsequently a new tunnel through Lieråsen to Asker. Lieråsen is a granite massif and was regarded to be simple area to work in. The planning was carried out with limited geological surveys. Construction started in 1963, but it
2795-482: The lower areas below. This height difference forced the line to take the detour. The Lieråsen Tunnel was launched as a project to cut distance and travel times between Asker and Drammen, as the Drammen Line was nearly twice the length compared to a straight line. The first proposals were developed by the Norwegian State Railways (NSB) in the early 1940s, albeit at first for a single track . During
2860-629: The lower deck with automobiles above, now converted to one-way road vehicle traffic on each deck. In Turkey, the Eurasia Tunnel under the Bosphorus , opened in 2016, has at its core a 5.4 km (3.4 miles) two-deck road tunnel with two lanes on each deck. Additionally, in 2015 the Turkish government announced that it will build three -level tunnel, also under the Bosporus. The tunnel
2925-405: The municipalities of Lier, Røyken and Asker. The line is electrified at 15 kV 16.7 Hz AC . At Eriksrud, 10.48 kilometers (6.51 mi) from Asker Station, there is a switch allowing trains to change track. The tunnel has a surface profile of 70 square meters (750 sq ft). The speed is limited to 130 km/h (81 mph). This is caused by the limited profile, which creates
2990-555: The old section of the Drammen Line became the Spikkestad Line , while the rest of line was closed. Lieråsen was the longest railway tunnel in the country until the Romerike Tunnel opened in 1999. The Lieråsen Tunnel is 10.723 kilometers (6.663 mi) long and carries the double tracked, standard gauge Drammen Line between Asker Station and Lier Station . Running through the mountain of Lieråsen, it passes through
3055-483: The older method of tunnelling in compressed air, with an airlock/decompression chamber some way back from the TBM, which required operators to work in high pressure and go through decompression procedures at the end of their shifts, much like deep-sea divers . In February 2010, Aker Wirth delivered a TBM to Switzerland, for the expansion of the Linth–Limmern Power Stations located south of Linthal in
3120-540: The operation of empty and loaded trains at the same time. The temporary way is replaced by the permanent way at completion, thus explaining the term " Perway ". The vehicles or traffic using a tunnel can outgrow it, requiring replacement or enlargement: An open building pit consists of a horizontal and a vertical boundary that keeps groundwater and soil out of the pit. There are several potential alternatives and combinations for (horizontal and vertical) building pit boundaries. The most important difference with cut-and-cover
3185-465: The part closest to Asker. The traffic was characterized by a high portion of rush-hour traffic between Røyken and Oslo, and a more even traffic through the day from Røyken to Drammen. The compromise was selected, whereby the 13 kilometers (8 mi) from Asker to Spikkestad Station was kept and named the Spikkestad Line, while the remaining 14 kilometers (9 mi) were closed on the same day
3250-452: The process of double tracking the Drammen Line between Asker and Sandvika , NSB launched a proposal to build two additional sections of double track, one from Hokksund to Drammen and one from Brakerøya to Asker. For the latter two main proposals were made: one which would run from the old Lier Station to Asker and a shorter direct tunnel. The advantage of the former was the ability to still serve Lierbyen and smaller construction costs, while
3315-522: The project is completed. If a tunnel is going to be long, multiple shafts at various locations may be bored so that entrance to the tunnel is closer to the unexcavated area. Once construction is complete, construction access shafts are often used as ventilation shafts , and may also be used as emergency exits. The New Austrian Tunnelling method (NATM)—also referred to as the Sequential Excavation Method (SEM) —was developed in
SECTION 50
#17327799763163380-490: The proper machinery must be selected. Large infrastructure projects require millions or even billions of dollars, involving long-term financing, usually through issuance of bonds . The costs and benefits for an infrastructure such as a tunnel must be identified. Political disputes can occur, as in 2005 when the US House of Representatives approved a $ 100 million federal grant to build a tunnel under New York Harbor. However,
3445-487: The reinforcements. The National Rail Administration and the government are working on plans for a future high-speed railway which would include upgrading the Vestfold Line to 250 kilometers per hour (160 mph). There are no plans for upgrades between Drammen and Oslo, which would make the Lieråsen Tunnel a bottleneck in the new system. Tunnel A tunnel is an underground or undersea passageway. It
3510-482: The risk of encountering unforeseen ground conditions. In planning the route, the horizontal and vertical alignments can be selected to make use of the best ground and water conditions. It is common practice to locate a tunnel deeper than otherwise would be required, in order to excavate through solid rock or other material that is easier to support during construction. Conventional desk and preliminary site studies may yield insufficient information to assess such factors as
3575-542: The sheer size of the excavation. This contrasts with many traditional stations on London Underground , where bored tunnels were used for stations and passenger access. Nevertheless, the original parts of the London Underground network, the Metropolitan and District Railways, were constructed using cut-and-cover. These lines pre-dated electric traction and the proximity to the surface was useful to ventilate
3640-555: The trains on the Vestfold Line and the Sørlandet Line . Part of the financing of the tunnel was channeled from a surcharge which NSB imposed on all tickets running through Lieråsen. A major discussion arose regarding the use of the old track between Asker and Drammen. That part of the line remained single track. Three main proposals were made: closing down that line entirely, keeping it for local traffic and only keeping
3705-400: The tunnel drive, the depth of the tunnel, the logistics of supporting the tunnel excavation, the final use and the shape of the tunnel and appropriate risk management. There are three basic types of tunnel construction in common use. Cut-and-cover tunnels are constructed in a shallow trench and then covered over. Bored tunnels are constructed in situ, without removing the ground above. Finally,
3770-436: The tunnel on 3 June 1973 resulted in a shortening of the Drammen Line by 12,438 meters (7.729 mi), cutting the distance from Drammen Station to the then terminus of Oslo West Station to 40.5 kilometers (25.2 mi). Travel time from Drammen to Oslo was also cut, from between 55 and 50 minutes to 30. This allowed for the new Class 69 commuter trains to be put into service on the Drammen Line. The time saving also targeted
3835-428: The two most common being bored tunnels or immersed tubes , examples are Bjørvika Tunnel and Marmaray . Submerged floating tunnels are a novel approach under consideration; however, no such tunnels have been constructed to date. During construction of a tunnel it is often convenient to install a temporary railway, particularly to remove excavated spoil , often narrow gauge so that it can be double track to allow
3900-478: Was S-shaped between Drammen and Asker, first heading northwards to Lier, where it connected to the Lier Line . It then headed south to Røyken and then northwards again to Asker. The reason for this route was the need to limit the gradient of the line to accommodate freight trains. Specifically, there is a steep slope just west of Spikkestad with a height difference of about 100 meters (330 ft) in comparison to
3965-575: Was constructed to provide a second harbour crossing and to alleviate traffic congestion on the Sydney Harbour Bridge , without spoiling the iconic view. Other reasons for choosing a tunnel instead of a bridge include avoiding difficulties with tides, weather, and shipping during construction (as in the 51.5-kilometre or 32.0-mile Channel Tunnel ), aesthetic reasons (preserving the above-ground view, landscape, and scenery), and also for weight capacity reasons (it may be more feasible to build
SECTION 60
#17327799763164030-403: Was soon discovered that there were long altered zones running through the area where the tunnel was to run. Specifically, a 2-kilometer (1.2 mi) long crushed zone was located there. After two years the route was therefore shifted about 300 meters (980 ft) to the southeast to avoid these zones. This resulted in a slight S-curve on the Lier end. Construction continued slowly, as nearly
4095-732: Was superseded by the Madrid M30 ringroad , Spain, and the Chong Ming tunnels in Shanghai , China. All of these machines were built at least partly by Herrenknecht . As of August 2013 , the world's largest TBM was " Big Bertha ", a 17.5-metre (57.5 ft) diameter machine built by Hitachi Zosen Corporation , which dug the Alaskan Way Viaduct replacement tunnel in Seattle, Washington (US). A temporary access shaft
4160-521: Was the Oslo Port Line that went partially through some of the most trafficked streets in Oslo. The station building was designed by architect Georg Andreas Bull in the then-fashionable Italiante style and built of plastered brickwork. The facade against City Hall Square is flanked by two low towers. Windows and doors are arched. After the station closed, the building was used by, among others,
4225-576: Was the terminus of the Drammen Line between 1872 and 1980, until the Oslo Tunnel opened. The station remained in use until 1989, when all traffic was moved to the new Oslo Central Station . Until its closure it was the main station for trains on the Sørland Line , the Drammen Line and the Vestfold Line . There was no passenger rail connection to Oslo Ø , the eastern station that served the eastern lines and trains to Bergen. The only connection
#315684