Misplaced Pages

Nanticoke Solar Facility

Article snapshot taken from Wikipedia with creative commons attribution-sharealike license. Give it a read and then ask your questions in the chat. We can research this topic together.

A feed-in tariff ( FIT , FiT , standard offer contract , advanced renewable tariff , or renewable energy payments ) is a policy mechanism designed to accelerate investment in renewable energy technologies by offering long-term contracts to renewable energy producers. This means promising renewable energy producers an above-market price and providing price certainty and long-term contracts that help finance renewable energy investments. Typically, FITs award different prices to different sources of renewable energy in order to encourage the development of one technology over another. For example, technologies such as wind power and solar PV are awarded a higher price per kWh than tidal power . FITs often include a "digression": a gradual decrease of the price or tariff in order to follow and encourage technological cost reductions .

#512487

90-583: The Nanticoke Solar Facility is a 44 MW solar power station in Nanticoke , Ontario , Canada . It is located on the site of the defunct Nanticoke Generating Station , which operated from 1972 to 2013 and was the largest coal-fired power plant in North America. The facility is owned and operated by Nanticoke Solar LP, a joint venture of Ontario Power Generation (80%), the Six Nations of

180-467: A National Historic Site of Canada in 1924. Following the phase-out of coal power in the province, Ontario Power Generation announced in July 2015 that it would not be converting the facility to biomass or natural gas and that remaining equipment would be sold or repurposed elsewhere. The two smokestacks were imploded using controlled demolition on February 28, 2018. OPG established Nanticoke Solar LP as

270-432: A FIT can be differentiated based on marginal cost . In this policy structure, the tariff price ranges from just above the spot rate to the price required to reach the government's optimal production level. Firms with lower marginal costs are offered lower prices, while those with higher marginal costs are subjected to higher tariff prices. This policy aims to decrease the profitability of certain production sites and promote

360-449: A bonus for each kWh produced, marketed or consumed. For electricity generated from solar or radiant heat only, the bonus is 300% of the price per kWh of electricity produced by the market operator defined by Law 02-01 of 22 Dhu El Kaada 1422 corresponding to 5 February 2002 until the minimum contribution of solar energy represents 25% of all primary energy. For electricity generated from facilities using solar thermal systems solar-gas hybrid,

450-427: A desired power output varies depending on the location, the efficiency of the solar panels, the slope of the site, and the type of mounting used. Fixed tilt solar arrays using typical panels of about 15% efficiency on horizontal sites, need about 1 hectare (2.5 acres)/MW in the tropics and this figure rises to over 2 hectares (4.9 acres) in northern Europe. Because of the longer shadow the array casts when tilted at

540-749: A detailed analysis by the European Commission concluded that "well-adapted feed-in tariff regimes are generally the most efficient and effective support schemes for promoting renewable electricity." This conclusion was supported by other analyses, including by the International Energy Agency , the European Federation for Renewable Energy, and by the Deutsche Bank . As of 2019, over 50 countries had enacted FIT policies. In environmental economics ,

630-458: A joint venture with First Nations to build and operate a new solar facility on the site. The Nanticoke Solar Facility is Ontario Power Generation's first solar facility. Contracts were let in 2016 and construction began in 2018. The 192,000-panel solar farm was completed in March 2019 but demolition of the old Nanticoke GS structures continued even after construction was completed. The last sections of

720-427: A life of 25 to 75 years, and normally do not require replacement during the life of a photovoltaic power station. The performance of a solar park depends on the climatic conditions, the equipment used and the system configuration. The primary energy input is the global light irradiance in the plane of the solar arrays, and this in turn is a combination of the direct and the diffuse radiation. In some regions soiling ,

810-507: A measure more directly comparable to other forms of power generation. Most solar parks are developed at a scale of at least 1 MW p . As of 2018, the world's largest operating photovoltaic power stations surpassed 1 gigawatt . At the end of 2019, about 9,000 solar farms were larger than 4 MW AC (utility scale), with a combined capacity of over 220 GW AC . Most of the existing large-scale photovoltaic power stations are owned and operated by independent power producers , but

900-442: A more cost-effective way to accelerate the development of renewable energy. Feed-in tariff laws were in place in 46 jurisdictions globally by 2007. Information about solar tariffs may be found in a consolidated form, however not all of the countries are listed in this source. To cover the additional costs of producing electricity from renewables and for the costs of diversification, producers of electricity from renewables receive

990-525: A more widespread distribution of generators. However, it may result in less cost-effective production of renewable electricity as the most efficient sites might be underutilized. The second objective of the differentiated tariff policy is to decrease the overall cost of the program. Under a uniform tariff system, all producers receive the same price, which can exceed the price necessary to incentivize production, resulting in surplus revenue and profit . A differentiated tariff seeks to provide each producer with

SECTION 10

#1732780296513

1080-459: A multitude of solar panels , mounted on support structures and interconnected to deliver a power output to electronic power conditioning subsystems. The majority are free-field systems using ground-mounted structures, usually of one of the following types: Many projects use mounting structures where the solar panels are mounted at a fixed inclination calculated to provide the optimum annual output profile. The panels are normally oriented towards

1170-453: A new solar park, and can be a significant contributor to the cost. Most stations are sited within a few kilometres of a suitable grid connection point. This network needs to be capable of absorbing the output of the solar park when operating at its maximum capacity. The project developer will normally have to absorb the cost of providing power lines to this point and making the connection; in addition often to any costs associated with upgrading

1260-458: A non-discriminatory manner to all renewable energy producers. Because purchase prices are based on costs, efficiently operated projects yield a reasonable rate of return. This principle was stated in the act: "The compensation rates ... have been determined by means of scientific studies, subject to the proviso that the rates identified should make it possible for an installation – when managed efficiently – to be operated cost-effectively, based on

1350-588: A number of Standard Offer Contracts, including Standard Offer fixed prices on the expected long-run cost of generation. The long-run estimates of electricity costs were based on the belief (widely held at the time) that oil and gas prices would continue to increase. This led to an escalating schedule of fixed purchase prices, designed to reflect the long-run avoided costs of new electrical generation. By 1992, private power producers had installed approximately 1,700 MW of wind capacity in California, some of which

1440-565: A result, PURPA contracts came to be viewed as an expensive burden on electricity ratepayers. Another source of opposition to PURPA stemmed from the fact that it was designed to encourage non-utility generation. This was interpreted as a threat by many large utilities, particularly by monopolistic suppliers. As a result of its encouragement of non-utility generation, PURPA has also been interpreted as an important step toward increasing competition. In 1990, Germany adopted its " Stromeinspeisungsgesetz " (StrEG), or "Law on Feeding Electricity into

1530-600: A revised Renewable Energy Sources Act entered into force. Specific deployment corridors now stipulate the extent to which renewable energy is to be expanded in the future and the funding rates (feed-in tariffs) for new capacity will gradually no longer be set by the government but will be determined by auction; starting with ground-mounted solar plant. This represented a major change in policy and will be further extended as of 2017 with tender processes for onshore and offshore wind. FiTs have both increased and decreased electricity prices. Increases in electricity rates occurred when

1620-505: A significant premium compared to the average rate of 0.34 yuan per kilowatt-hour paid to coal-fired electricity generators. Czech Republic introduced a tariff with law no. 180/2005 in 2005. The tariff is guaranteed for 15–30 years (depending on source). Supported sources are small hydropower (up to 10 MW), biomass, biogas, wind, and photovoltaics. As of 2010 , the highest tariff was 12.25 CZK /kWh for small photovoltaic. In 2010, over 1200 MW of photovoltaics were installed, but at

1710-479: A solar farm in space—collecting solar power from a photovoltaic cell and beaming energy down to Earth—constituted an early feasibility demonstration completed. Such setups are not limited by cloud cover or the Sun’s cycle. Most solar parks are ground mounted PV systems, also known as free-field solar power plants. They can either be fixed tilt or use a single axis or dual axis solar tracker . While tracking improves

1800-565: A solar park, for example at times of low demand or high availability of other generators. Some countries make statutory provision for priority access to the grid for renewable generators, such as that under the European Renewable Energy Directive . In recent years, PV technology has improved its electricity generating efficiency , reduced the installation cost per watt as well as its energy payback time (EPBT). It has reached grid parity in most parts of

1890-419: A steeper angle, this area is typically about 10% higher for an adjustable tilt array or a single axis tracker, and 20% higher for a 2-axis tracker, though these figures will vary depending on the latitude and topography. The best locations for solar parks in terms of land use are held to be brown field sites , or where there is no other valuable land use. Even in cultivated areas, a significant proportion of

SECTION 20

#1732780296513

1980-517: A usufruct system in exchange for 2% of the energy produced. The electricity companies would be obligated to purchase and transport the energy. The new tariff system also included a reduction in customs on new and renewable energy production supplies by 2% while the proportion of bank financing has been set at 40–60%. The government hoped for new and renewable energy to account for 20% Egypt's total energy mix by 2020. The European Union does not operate or necessarily encourage feed-in tariff schemes as it

2070-417: A wider range of sources. The prices revealed by these auctions and tenders have led to highly competitive prices in many regions. Amongst the prices quoted are: Solar generating stations have become progressively cheaper in recent years, and this trend is expected to continue. Meanwhile, traditional electricity generation is becoming progressively more expensive. These trends led to a crossover point when

2160-457: Is lower in temperate climates or those with more significant diffuse radiation , due to overcast conditions. So dual axis trackers are most commonly used in subtropical regions, and were first deployed at utility scale at the Lugo plant. A third approach achieves some of the output benefits of tracking, with a lesser penalty in terms of land area, capital and operating cost. This involves tracking

2250-404: Is metered in real-time with readings of its energy output provided, typically on a half-hourly basis, for balancing and settlement within the electricity market. Income is affected by the reliability of equipment within the plant and also by the availability of the grid network to which it is exporting. Some connection contracts allow the transmission system operator to curtail the output of

2340-431: Is no need for a purchase agreement with a utility, but the feed-in tariff is state-administered, so the term "feed-in tariff" (German "Einspeisetarif") is usually used. Since around 2012, other types of contracts became more usual, because PPAs were supported and for small-scale solar projects , direct use of power became more attractive when the feed-in tariff became lower than prices for power bought. On 1 August 2014,

2430-490: Is still in service today. The adoption of PURPA also led to significant renewable energy generation in other states such as Florida and Maine. This notwithstanding, PURPA retains negative connotations in the U.S. electricity industry. When oil and gas prices plummeted in the late 1980s, the Standard Offer Contracts that were signed to encourage new renewable energy development seemed high by comparison. As

2520-620: Is typically warranted at plus or minus 3% during the first year of operation. Solar power plants are developed to deliver merchant electricity into the grid as an alternative to other renewable, fossil or nuclear generating stations. The plant owner is an electricity generator. Most solar power plants today are owned by independent power producers (IPP's), though some are held by investor- or community-owned utilities. Some of these power producers develop their own portfolio of power plants, but most solar parks are initially designed and constructed by specialist project developers. Typically

2610-646: The Charanka Solar Park , where there are 17 different generation projects; Neuhardenberg , with eleven plants, and the Golmud solar park with total reported capacity over 500   MW. An extreme example would be calling all of the solar farms in the Gujarat state of India a single solar park, the Gujarat Solar Park . To avoid land use altogether, in 2022, a 5 MW floating solar park

2700-960: The World Trade Organization . There are three methods of compensation. The first form of feed-in tariff (under another name ) was implemented in the US in 1978 under President Jimmy Carter , who signed the National Energy Act (NEA). This law included five separate acts, one of which was the Public Utility Regulatory Policies Act (PURPA). The purpose of the National Energy Act was to encourage energy conservation and develop new energy resources, including renewables such as wind, solar, and geothermal power . Within PURPA

2790-514: The profit margin of big electric power companies , who reacted by lobbying the German government, which reduced subsidies in 2012. The increase in the solar energy share in Germany also had the effect of closing gas and coal-fired generation plants. Often all power produced is fed to the grid, which makes the system work rather like a PPA according to the disambiguation above, however, there

Nanticoke Solar Facility - Misplaced Pages Continue

2880-526: The utility level, rather than to a local user or users. Utility-scale solar is sometimes used to describe this type of project. This approach differs from concentrated solar power , the other major large-scale solar generation technology, which uses heat to drive a variety of conventional generator systems. Both approaches have their own advantages and disadvantages, but to date, for a variety of reasons, photovoltaic technology has seen much wider use. As of 2019 , about 97% of utility-scale solar power capacity

2970-515: The "avoided long-run marginal cost" of generation. The long-run costs referred to the anticipated cost of electricity in the years ahead. This last approach was adopted by California in its Standard Offer Contract No. 4. Another provision included in the PURPA law was that utilities were prevented from owning more than 50% of projects, to encourage new entrants. To comply with PURPA, some states began offering Standard Offer Contracts to producers. The California Public Utility Commission established

3060-452: The 'performance ratio' has been developed to evaluate the total value of these losses. The performance ratio gives a measure of the output AC power delivered as a proportion of the total DC power which the solar panels should be able to deliver under the ambient climatic conditions. In modern solar parks the performance ratio should typically be in excess of 80%. Early photovoltaic systems output decreased as much as 10%/year, but as of 2010

3150-557: The Equator, at a tilt angle slightly less than the latitude of the site. In some cases, depending on local climatic, topographical or electricity pricing regimes, different tilt angles can be used, or the arrays might be offset from the normal east–west axis to favour morning or evening output. A variant on this design is the use of arrays, whose tilt angle can be adjusted twice or four times annually to optimise seasonal output. They also require more land area to reduce internal shading at

3240-768: The Grand River Development Corporation (15%), and the Mississaugas of the Credit First Nation (5%). The Nanticoke Solar Facility and its predecessor, the Nanticoke Generating Station, is built on the site of the "Battle of Nanticoke" where the Norfolk volunteer militia routed a band of American marauders who had been pillaging area farms and terrorizing the country in 1813. The site was designated

3330-466: The Grid". The StrEG required utilities to purchase electricity generated from renewable energy suppliers at a percentage of the prevailing retail price of electricity. The percentage offered for solar and wind power was set at 90% of the residential electricity price, while other technologies such as hydro power and biomass sources were offered at percentages ranging from 65% to 80%. A project cap of 5 MW

3420-654: The accumulation of dust or organic material on the solar panels that blocks incident light, is a significant loss factor. A key determinant of the output of the system is the conversion efficiency of the solar panels, which depends in particular on the type of solar cell used. There will be losses between the DC output of the solar panels and the AC power delivered to the grid, due to a wide range of factors such as light absorption losses, mismatch, cable voltage drop, conversion efficiencies, and other parasitic losses . A parameter called

3510-409: The act proved to be a highly effective policy framework for accelerating the deployment of renewables. Important changes included: Since it was very successful, the German policy (amended in 2004, 2009, and 2012) was often used as the benchmark against which other feed-in tariff policies were considered. Other countries followed the German approach as well. Long-term contracts are typically offered in

3600-438: The advantage of the projects sharing the cost and risks of project infrastructure such as grid connections and planning approval. Solar farms can also be co-located with wind farms. Sometimes 'solar park' is used to describe a set of individual solar power stations, which share sites or infrastructure, and 'cluster' is used where several plants are located nearby without any shared resources. Some examples of solar parks are

3690-452: The amount of energy they feed into the grid. Selling the certificates is another way for renewable producers to supplement their revenues. Certificate prices fluctuate based on overall energy demand and competition among renewable producers. If the amount of renewable energy produced exceeds the required amount, certificate prices may crash, like with carbon trading in Europe. This can damage

Nanticoke Solar Facility - Misplaced Pages Continue

3780-655: The average electricity spot market price. In remote areas, electricity from solar photovoltaics can be cheaper than building new distribution lines to connect to the transmission grid. Renewable portfolio standards (RPS) and subsidies create protected markets for renewable energy. RPS requires utilities to obtain a minimum percentage of their energy from renewable sources. In some states, utilities can purchase Renewable Energy Certificates (US), Renewable Energy Certificate System (EU), or Renewable Energy Certificates Registry (Australia) to meet this requirement. These certificates are issued to renewable energy producers based on

3870-699: The bonus is 200% of the price per kWh. For contributions of solar energy below 25%, said bonus is paid under the following conditions: The price of electricity is fixed by the CREG (Gas and Electricity Regulatory Commission). According to the last decision that was made, the consumer pays for their electricity as below: Other consumers (industry, agriculture, etc.) pay 4.17 DZD/kWh. The feed-in tariff provides bonuses for electricity generated by cogeneration of 160%, taking into account thermal energy use of 20% of all primary energy used. The bonuses for solar-generated electricity and cogeneration are cumulative. Remuneration of

3960-470: The capacity of lower-cost facilities. This has led to electricity price reductions in Spain, Denmark, and Germany. Grid parity occurs when the cost of an alternative technology for electricity production matches the existing average for the area. Parity can vary both in time (i.e., during the course of the day and over the course of years) and in space (i.e., geographically). The price of electricity from

4050-621: The centre of the block. String inverters are substantially lower in capacity than central inverters, of the order of 10 kW up to 250 KW for newer models (2020), and condition the output of a single array string. This is normally a whole, or part of, a row of solar arrays within the overall plant. String inverters can enhance the efficiency of solar parks, where different parts of the array are experiencing different levels of insolation, for example where arranged at different orientations, or closely packed to minimise site area. The system inverters typically provide power output at voltages of

4140-466: The developer will plan the project, obtain planning and connection consents, and arrange financing for the capital required. The actual construction work is normally contracted to one or more engineering, procurement, and construction (EPC) contractors. Major milestones in the development of a new photovoltaic power plant are planning consent , grid connection approval, financial close , construction, connection and commissioning. At each stage in

4230-420: The economic viability of renewable producers. Quota systems favor large, vertically integrated generators and multinational electric utilities because certificates are generally denominated in units of one megawatt-hour. They are also more difficult to design and implement than an feed-in tariff. Mandating dynamic tariffs for customer-initiated meter upgrades (including for distributed energy uptake) may be

4320-478: The electricity generated by investors, taking inflation into account, while consumption is to be paid in local currency and depreciation rates reviewed after two years. The Ministry of Finance will provide concessional subsidized bank financing for households and institutions using less than 200 KW at a rate of 4% and 8% for 200–500KW. The government is preparing a law that would allow for state-owned lands to be made available for new energy production projects under

4410-676: The end of 1982, followed in 1984 by a 5.2 MW p installation in Carrizo Plain . Both have since been decommissioned (although a new plant, Topaz Solar Farm , was commissioned in Carrizo Plain in 2015). The next stage followed the 2004 revisions to the feed-in tariffs in Germany , when a substantial volume of solar parks were constructed. Several hundred installations over 1 MW p have since been installed in Germany, of which more than 50 are over 10 MW p . With its introduction of feed-in tariffs in 2008, Spain briefly became

4500-508: The end of the year, the FiT was eliminated for larger systems and reduced by 50% for smaller systems. In 2011, no photovoltaic systems were installed. On 20 September 2014, the Ministry of Electricity announced the new feed-in tariff (FIT) pricing for electricity generated from new and renewable energy sources for households and private sector companies. The FIT would be applied in two phases,

4590-801: The first Feed-in tariff mechanism for renewable power in China. As of August 2011, a national solar tariff was issued at about US$ 0.15 per kWh. China has implemented a tariff system for new onshore wind power plants aimed at supporting struggling project operators and ensuring profitability. The National Development and Reform Commission (NDRC), the country's economic planning agency, introduced four tariff categories for onshore wind projects, categorized by region. Areas with more favorable wind resources will have lower tariffs, while regions with lower output will benefit from more generous tariffs. The tariffs are set at 0.51 yuan (US$ 0.075, £0.05), 0.54 yuan, 0.58 yuan, and 0.61 yuan per kilowatt-hour. These rates represent

SECTION 50

#1732780296513

4680-428: The former Nanticoke GS were demolished on August 22, 2019. Photovoltaic power station A photovoltaic power station , also known as a solar park , solar farm , or solar power plant , is a large-scale grid-connected photovoltaic power system (PV system) designed for the supply of merchant power . They are different from most building-mounted and other decentralized solar power because they supply power at

4770-413: The funding for the feed-in tariff scheme is provided by ratepayers via a surcharge in their electricity bills. In Germany, this approach to funding the feed-in tariff added c€6.88/kWh to the electricity rate for residential consumers in 2017. However, renewable energy can reduce spot market prices via the merit order effect , the practice of using higher-cost fossil fuel facilities only when demand exceeds

4860-613: The generated electricity is guaranteed over the whole plant's lifetime. Feed-in tariffs were introduced in 2008 in South Australia and Queensland , 2009 in the Australian Capital Territory and Victoria , and 2010 in New South Wales , Tasmania , and Western Australia . The Northern Territory offers only local feed-in tariff schemes. A uniform federal scheme to supersede all State schemes

4950-690: The generator's usage, pending the outcome of an inquiry by the Victorian Competition and Efficiency Commission. This does not meet the normal definition and has been referred to as a "fake feed-in tariff". It is net metering with a payment for any kilowatt credit instead of the normal rollover. Ontario introduced a feed-in tariff in 2006, revised in 2009 and 2010, increasing from 42¢/kWh to 80.2¢/kWh for micro-scale (≤10 kW) grid-tied photovoltaic projects, and decreasing to 64.2¢/kWh for applications received after 2 July 2010. Applications received prior to then had until 31 May 2011 to install

5040-605: The grid varies widely from high-cost areas, such as Hawaii and California, to lower-cost areas, such as Wyoming and Idaho . In areas with time-of-day pricing, rates vary over the course of the day, rising during high-demand hours (e.g., 11 AM – 8 PM) and declining during low-demand hours (e.g., 8 PM – 11 AM). In some areas, wind power, landfill gas , and biomass generation are lower cost than grid electricity. Parity has been achieved in areas that use feed-in tariffs. For example, generation cost from landfill gas systems in Germany are currently lower than

5130-400: The grid, so it can accommodate the output from the plant. Therefore, solar power stations are sometimes built at sites of former coal-fired power stations to reuse existing infrastructure. Once the solar park has been commissioned, the owner usually enters into a contract with a suitable counterparty to undertake operation and maintenance (O&M). In many cases this may be fulfilled by

5220-416: The inverters or as separate units. These devices keep each solar array string close to its peak power point . There are two primary alternatives for configuring this conversion equipment; centralized and string inverters, although in some cases individual, or micro-inverters are used. Single inverters allows optimizing the output of each panel, and multiple inverters increases the reliability by limiting

5310-445: The involvement of community and utility-owned projects is increasing. Previously, almost all were supported at least in part by regulatory incentives such as feed-in tariffs or tax credits , but as levelized costs fell significantly in the 2010s and grid parity has been reached in most markets, external incentives are usually not needed. The first 1 MW p solar park was built by Arco Solar at Lugo near Hesperia, California , at

5400-413: The largest market with some 60 solar parks over 10 MW, but these incentives have since been withdrawn. The USA, China, India, France, Canada, Australia, and Italy, among others, have also become major markets as shown on the list of photovoltaic power stations . The largest sites under construction have capacities of hundreds of MW p and some more than 1 GW p . The land area required for

5490-400: The levelised cost of energy from solar parks, historically more expensive, matched or beat the cost of traditional electricity generation. This point depends on locations and other factors, and is commonly referred to as grid parity. Feed-in tariff FITs typically include three key provisions: Under a FIT, eligible renewable electricity generators are paid a cost-based price for

SECTION 60

#1732780296513

5580-413: The loss of output when an inverter fails. These units have relatively high capacity, typically of the order between 1 MW up to 7 MW for newer units (2020), so they condition the output of a substantial block of solar arrays, up to perhaps 2 hectares (4.9 acres) in area. Solar parks using centralized inverters are often configured in discrete rectangular blocks, with the related inverter in one corner, or

5670-414: The median degradation rate was 0.5%/year, with panels made after 2000 having a significantly lower degradation rate, so that a system would lose only 12% of its output performance in 25 years. A system using panels which degrade 4%/year will lose 64% of its output during the same period. Many panel makers offer a performance guarantee, typically 90% in ten years and 80% over 25 years. The output of all panels

5760-462: The necessary incentives to maintain production, aiming to achieve the optimal market quantity of renewable energy production. In the context of globalization , FITs pose challenges from a trade perspective, as their implementation in one country can impact the industries and policies of others. Ideally, these policy instruments would fall under a globally-coordinated body overseeing their implementation and regulation, which could be facilitated through

5850-467: The official date for applying the first phase as 27 October 2014 and the second phase to be applied two years after the first phase (which launched on 28 October 2016). In the initial phase, the energy tariff is structured across five categories. Residential solar generation is priced at EGP 0.848 per kilowatt-hour (KWh), while non-residential installations of less than 200 kilowatts pay EGP 0.901/KWh. For installations between 200 and 500 kilowatts,

5940-514: The order of 480 V AC up to 800 V AC . Electricity grids operate at much higher voltages of the order of tens or hundreds of thousands of volts, so transformers are incorporated to deliver the required output to the grid. Due to the long lead time, the Long Island Solar Farm chose to keep a spare transformer onsite, as transformer failure would have kept the solar farm offline for a long period. Transformers typically have

6030-520: The original EPC contractor. Solar plants' reliable solid-state systems require minimal maintenance, compared to rotating machinery. A major aspect of the O&;M contract will be continuous monitoring of the performance of the plant and all of its primary subsystems, which is normally undertaken remotely. This enables performance to be compared with the anticipated output under the climatic conditions actually experienced. It also provides data to enable

6120-414: The overall performance, it also increases the system's installation and maintenance cost. A solar inverter converts the array's power output from DC to AC , and connection to the utility grid is made through a high voltage, three phase step up transformer of typically 10  kV and above. The solar arrays are the subsystems which convert incoming light into electrical energy. They comprise

6210-507: The process, the developer will be able to update estimates of the anticipated performance and costs of the plant and the financial returns it should be able to deliver. Photovoltaic power stations occupy at least one hectare for each megawatt of rated output, so require a substantial land area; which is subject to planning approval. The chances of obtaining consent, and the related time, cost and conditions, vary by jurisdiction and location. Many planning approvals will also apply conditions on

6300-460: The rate increases to 0.973 EGP/KWh. Larger non-residential installations, ranging from 500 kilowatts to 20 megawatts, are paid in USD at a rate of US$ 0.136/KWh (with 15% of the tariff linked to an exchange rate of 7.15 EGP per USD). The highest category, spanning 20 to 50 MW, pays US$ 0.1434/KWh. Wind power tariffs vary based on operating hours, ranging from US$ 0.1148/KWh to US$ 0.046/KWh. In

6390-559: The renewable electricity they supply to the grid . This enables diverse technologies ( wind , solar , biogas , etc.) to be developed and provides investors a reasonable return. This principle was explained in Germany's 2000 Renewable Energy Sources Act : The compensation rates have been determined by means of scientific studies, subject to the provision that the rates identified should make it possible for an installation – when managed efficiently – to be operated cost-effectively, based on

6480-402: The same actuator can adjust the angle of several rows at once. Solar panels produce direct current (DC) electricity, so solar parks need conversion equipment to convert this to alternating current (AC), which is the form transmitted by the electricity grid. This conversion is done by inverters . To maximise their efficiency, solar power plants also vary the electrical load , either within

6570-422: The scheduling of both rectification and preventive maintenance. A small number of large solar farms use a separate inverter or maximizer for each solar panel, which provide individual performance data that can be monitored. For other solar farms, thermal imaging is used to identify non-performing panels for replacement. A solar park's income derives from the sales of electricity to the grid, and so its output

6660-440: The site of a solar farm can also be devoted to other productive uses, such as crop growing or biodiversity. The change in albedo affects local temperature. One study claims a temperature rise due to the heat island effect, and another study claims that surroundings in arid ecosystems become cooler. Agrivoltaics is using the same area of land for both solar photovoltaic power and agriculture . A recent study found that

6750-411: The sky, and as its elevation changes throughout the year. These arrays need to be spaced out to reduce inter-shading as the sun moves and the array orientations change, so need more land area. They also require more complex mechanisms to maintain the array surface at the required angle. The increased output can be of the order of 30% in locations with high levels of direct radiation , but the increase

6840-407: The steeper winter tilt angle. Because the increased output is typically only a few percent, it seldom justifies the increased cost and complexity of this design. To maximise the intensity of incoming direct radiation, solar panels should be orientated normal to the sun's rays. To achieve this, arrays can be designed using two-axis trackers , capable of tracking the sun in its daily movement across

6930-460: The subsequent phase, the solar generation categories were reduced to four. The residential tariff increased to 1.0288 EGP/KWh. Non-residential installations under 500 KW pay 1.0858 EGP/KWh. For installations between 500 KW and 20 MW, the rate is US$ 0.0788/KWh, and for those between 20 MW and 50 MW, it is US$ 0.084/KWh (with 30% of the tariff linked to an exchange rate of 8.88 EGP per USD). The government would purchase

7020-471: The sun in one dimension – in its daily journey across the sky – but not adjusting for the seasons. The angle of the axis is normally horizontal, though some, such as the solar park at Nellis Air Force Base, which has a 20° tilt, incline the axis towards the equator in a north–south orientation – effectively a hybrid between tracking and fixed tilt. Single axis tracking systems are aligned along axes roughly north–south. Some use linkages between rows so that

7110-571: The system to receive the higher rate. Ontario's FiT program includes a tariff schedule for larger projects up to and including 10 MW solar farms at a reduced rate. As of April 2010, several hundred projects have been approved, including 184 large scale projects, worth $ 8 billion. By April 2012, 12,000 systems had been installed and the rate decreased to 54.9¢/kWh, for applications received after 1 September 2011. The price schedule as 2013 revised solar prices down to 28–38¢/kWh. The Renewable Energy Law came into force in 2006 and brought about

7200-409: The treatment of the site after the station has been decommissioned in the future. A professional health, safety and environment assessment is usually undertaken during the design of a PV power station in order to ensure the facility is designed and planned in accordance with all HSE regulations. The availability, locality and capacity of the connection to the grid is a major consideration in planning

7290-472: The use of state-of-the-art technology and depending on the renewable energy sources naturally available in a given geographical environment. The tariff may differ by technology, location, size, and region and is typically designed to decline over time to track and encourage technological change. FITs typically offer a guaranteed purchase agreement for long periods (15–25 years) and give incentives to producers to maximize output and efficiency. In 2008,

7380-457: The use of state-of-the-art technology and depending on the renewable energy sources naturally available in a given geographical environment." Feed-in tariff policies typically target a 5–10% return. The success of photovoltaics in Germany resulted in a drop in electricity prices of up to 40% during peak output times, with savings between €520 million and €840 million for consumers. Savings for consumers have meant conversely reductions in

7470-454: The value of solar generated electricity coupled to shade-tolerant crop production created an over 30% increase in economic value from farms deploying agrivoltaic systems instead of conventional agriculture. A Solar landfill is a repurposed used landfill that is converted to a solar array solar farm. In some cases, several different solar power stations with separate owners and contractors are developed on adjacent sites. This can offer

7560-599: The world and become a mainstream power source. As solar power costs reached grid parity, PV systems were able to offer power competitively in the energy market. The subsidies and incentives, which were needed to stimulate the early market as detailed below, were progressively replaced by auctions and competitive tendering leading to further price reductions. The improving competitiveness of utility-scale solar became more visible as countries and energy utilities introduced auctions for new generating capacity. Some auctions are reserved for solar projects, while others are open to

7650-517: Was PV. In some countries, the nameplate capacity of photovoltaic power stations is rated in megawatt-peak (MW p ), which refers to the solar array's theoretical maximum DC power output. In other countries, the manufacturer states the surface and the efficiency. However, Canada, Japan, Spain, and the United States often specify using the converted lower nominal power output in MW AC ,

7740-497: Was a provision that required utilities to purchase electricity generated from qualifying independent power producers at rates not to exceed their avoided cost. Avoided costs were designed to reflect the cost that a utility would incur to provide that same electrical generation . Different interpretations of PURPA prevailed in the 1980s: some utilities and state utility commissions interpreted avoided costs narrowly to mean avoided fuel costs, while others chose to define "avoided costs" as

7830-412: Was included. While Germany's StrEG was insufficient to encourage costlier technologies such as photovoltaics , it proved relatively effective at encouraging lower-cost technologies like wind, leading to the deployment of 4,400 MW of new wind capacity between 1991 and 1999, which represented approximately one-third of total global wind capacity by 1999. An additional challenge that StrEG addressed

7920-555: Was installed in the Alqueva Dam reservoir, Portugal, enabling solar power and hydroelectric energy to be combined. Separately, a German engineering firm committed to integrating an offshore floating solar farm with an offshore wind farm to use ocean space more efficiently. The projects involve " hybridization ", in which different renewable energy technologies are combined in one site. The first successful test in January 2024 of

8010-654: Was proposed by Tasmanian Greens Senator Christine Milne but was not enacted. By mid-2011, Feed-in tariff in NSW and the ACT had been closed to new generators as the installed capacity cap had been reached. In NSW, both the Feed-in tariff and the cap were cut due to the overly generous original settings. The new conservative Victorian government replaced the original Feed-in tariff with a less generous transitional Feed-in tariff of 25 cents per kilowatt-hour for any power generated excess to

8100-588: Was the right to connect to the grid. The StrEG guaranteed renewable electricity producers grid access. Similar percentage-based feed-in laws were adopted in Spain and Denmark in the 1990s. Germany's feed-in law underwent a major restructuring in 2000 to become the Renewable Energy Sources Act (2000) ( German : Erneuerbare-Energien-Gesetz or EEG ). The title is an act on granting priority to renewable energy sources. In its new form,

#512487