Misplaced Pages

Berlin Hauptbahnhof

Article snapshot taken from Wikipedia with creative commons attribution-sharealike license. Give it a read and then ask your questions in the chat. We can research this topic together.

A train station , railroad station , or railroad depot (mainly North American terminology) and railway station (mainly UK and other Anglophone countries) is a railway facility where trains stop to load or unload passengers , freight , or both. It generally consists of at least one platform , one track , and a station building providing such ancillary services as ticket sales, waiting rooms , and baggage/freight service. Stations on a single-track line often have a passing loop to accommodate trains travelling in the opposite direction.

#591408

107-652: Berlin Hauptbahnhof ( listen ) (English: Berlin Central Station ) is the main railway station in Berlin , Germany. It came into full operation two days after a ceremonial opening on 26 May 2006. It is located on the site of the historic Lehrter Bahnhof , and on the Berlin S-Bahn suburban railway . The station is owned by DB InfraGO , a subsidiary of Deutsche Bahn AG, and is classified as

214-866: A Category 1 station, one of 21 in Germany and four in Berlin, the others being Berlin Gesundbrunnen , Berlin Südkreuz and Berlin Ostbahnhof . Lehrter Bahnhof (Lehrte Station) opened in 1871 as the terminus of the railway linking Berlin with Lehrte , near Hanover , which later became Germany's most important east–west main line. In 1882, with the completion of the Stadtbahn (City Railway, Berlin's four-track central elevated railway line, which carries both local and main line services), just north of

321-404: A bar or pub . Other station facilities may include: toilets , left-luggage , lost-and-found , departures and arrivals schedules , luggage carts, waiting rooms , taxi ranks , bus bays and even car parks . Larger or staffed stations tend to have a greater range of facilities including also a station security office. These are usually open for travellers when there is sufficient traffic over

428-406: A bypass line, used by freight trains that do not need to stop at the terminus. Some termini have a newer set of through platforms underneath (or above, or alongside) the terminal platforms on the main level. They are used by a cross-city extension of the main line, often for commuter trains , while the terminal platforms may serve long-distance services. Examples of underground through lines include

535-404: A few intermediate stations that take the form of a stub-end station, for example at some zigzags . If there is a station building , it is usually located to the side of the tracks. In the case of intermediate stations used for both passenger and freight traffic, there is a distinction between those where the station building and goods facilities are on the same side of the tracks and those in which

642-472: A few small railway stations are designated as "halts" ( Irish : stadanna , sing. stad ). In some Commonwealth countries the term "halt" is used. In Australia, with its sparse rural populations, such stopping places were common on lines that were still open for passenger traffic. In the state of Victoria , for example, a location on a railway line where a small diesel railcar or railmotor could stop on request, allowing passengers to board or alight,

749-831: A further 40 from other companies at the Grouping of 1923. Peak building periods were before the First World War (145 built) and 1928–1939 (198 built). Ten more were opened by British Rail on ex-GWR lines. The GWR also built 34 "platforms". Many such stops remain on the national railway networks in the United Kingdom, such as Penmaenmawr in North Wales , Yorton in Shropshire , and The Lakes in Warwickshire , where passengers are requested to inform

856-571: A line was dual-purpose there would often be a freight depot apart from the passenger station. This type of dual-purpose station can sometimes still be found today, though in many cases goods facilities are restricted to major stations. Many stations date from the 19th century and reflect the grandiose architecture of the time, lending prestige to the city as well as to railway operations. Countries where railways arrived later may still have such architecture, as later stations often imitated 19th-century styles. Various forms of architecture have been used in

963-407: A long enough period of time to warrant the cost. In large cities this may mean facilities available around the clock. A basic station might only have platforms, though it may still be distinguished from a halt , a stopping or halting place that may not even have platforms. Many stations, either larger or smaller, offer interchange with local transportation; this can vary from a simple bus stop across

1070-504: A member of on-board train staff if they wish to alight, or, if catching a train from the station, to make themselves clearly visible to the driver and use a hand signal as the train approaches. Most have had "Halt" removed from their names. Two publicly advertised and publicly accessible National Rail stations retain it: Coombe Junction Halt and St Keyne Wishing Well Halt . A number of other halts are still open and operational on privately owned, heritage, and preserved railways throughout

1177-507: A more northern part of Berlin, where the circle and north–south-line of the S-Bahn cross each other. In 2005 the bridging segments, which cross over the roof of the station, were lowered. This was the first time this unique method to build later office rooms was applied. The architect Meinhard von Gerkan filed a complaint against Deutsche Bahn in October 2005 after Deutsche Bahn altered

SECTION 10

#1732786994592

1284-614: A new through-station, including the cases of Berlin Hauptbahnhof , Vienna Hauptbahnhof and numerous examples throughout the first century of railroading. Stuttgart 21 is a controversial project involving the replacement of a terminus station by a through-station. An American example of a terminal with this feature is Union Station in Washington, DC , where there are bay platforms on the main concourse level to serve terminating trains and standard island platforms one level below to serve trains continuing southward. The lower tracks run in

1391-475: A remedy, small sheets were placed above the carrier to prevent further carrier dissolution. Between 1868 and 1871, a 239 kilometres (149 mi) railway was built between Hannover and Berlin via Lehrte by the Magdeburg Halberstädter railway company. Lehrter Bahnhof was constructed as the Berlin terminus. It was adjacent to Hamburger Bahnhof , just outside what was then Berlin's boundary at

1498-549: A separate alignment for the U-Bahn, in addition to a road tunnel ventilated by a 60 m (197 ft)-high tower completed in 2004. During its construction, the course of the Spree had to be diverted (1996–1998). Water leaks in the tunnels caused over one year's delay to the construction work. In 1998, the construction of the station proper began. About 1,500,000 cubic metres (53,000,000 cu ft) of material were excavated for

1605-523: A special challenge for the Egyptian engineer Hani Azer , the chief construction engineer since 2001. The main station hall is spanned by a similarly curved glass roof with a surface area of about 85 m (279 ft) by 120 m (390 ft), which was installed in February 2002. A photovoltaic system was integrated into the glass surface. The steel and glass construction was a difficult task for

1712-407: A spot at the station to board and disembark trains is called station track or house track regardless of whether it is a main line or loop line. If such track is served by a platform , the track may be called platform track. A loop line without a platform, which is used to allow a train to clear the main line at the station only, is called passing track. A track at the station without a platform which

1819-417: A station and various other features set certain types apart. The first is the level of the tracks . Stations are often sited where a road crosses the railway: unless the crossing is a level crossing , the road and railway will be at different levels. The platforms will often be raised or lowered relative to the station entrance: the station buildings may be on either level, or both. The other arrangement, where

1926-576: A station stop does not. A station stop usually does not have any tracks other than the main tracks, and may or may not have switches (points, crossovers). An intermediate station does not have any other connecting route, unlike branch-off stations , connecting stations, transfer stations and railway junctions . In a broader sense, an intermediate station is generally any station on the route between its two terminal stations . The majority of stations are, in practice, intermediate stations. They are mostly designed as through stations ; there are only

2033-405: A station track as a temporary storage of a disabled train. A "terminus" or "terminal" is a station at the end of a railway line. Trains arriving there have to end their journeys (terminate) or reverse out of the station. Depending on the layout of the station, this usually permits travellers to reach all the platforms without the need to cross any tracks – the public entrance to the station and

2140-405: A three-way junction and platforms are built on all three sides, for example Shipley and Earlestown stations. In a station, there are different types of tracks to serve different purposes. A station may also have a passing loop with a loop line that comes off the straight main line and merge back to the main line on the other end by railroad switches to allow trains to pass. A track with

2247-650: A tunnel beneath the concourse and emerge a few blocks away to cross the Potomac River into Virginia. Terminus stations in large cities are by far the biggest stations, with the largest being Grand Central Terminal in New York City. Other major cities, such as London, Boston , Paris, Istanbul , Tokyo, and Milan have more than one terminus, rather than routes straight through the city. Train journeys through such cities often require alternative transport ( metro , bus , taxi or ferry ) from one terminus to

SECTION 20

#1732786994592

2354-601: A tunnel opening located north of Hauptbahnhof station. There was also a provisional workshop for the basic maintenance and cleaning of carriages. Formerly, trains running on the U55 were F79 trains. However, due to a lack of trains on other large profile U-Bahn lines, the two U55 trains were removed and placed on the U6 in April 2017. Instead, an older D class train was renovated and placed into service until March 2020. The designation of

2461-464: Is Arbroath . Occasionally, a station serves two or more railway lines at differing levels. This may be due to the station's position at a point where two lines cross (example: Berlin Hauptbahnhof ), or may be to provide separate station capacity for two types of service, such as intercity and suburban (examples: Paris-Gare de Lyon and Philadelphia's 30th Street Station ), or for two different destinations. Stations may also be classified according to

2568-508: Is 2.2 kilometres (1.4 mi) in length, connecting the former U55 terminus at Brandenburger Tor with the rest of the U5 at Alexanderplatz. The link features three new U-Bahn stations at Rotes Rathaus , Museumsinsel and Unter den Linden . Unter Den Linden provides an interchange with line U6, replacing the former Französische Straße station, located a little further to the south on Friedrichstraße, which closed on 3 December 2020. Operations on

2675-455: Is any longer served by trains), or military base (such as Lympstone Commando ) or railway yard. The only two such "private" stopping places on the national system, where the "halt" designation is still officially used, seem to be Staff Halt (at Durnsford Road, Wimbledon) and Battersea Pier Sidings Staff Halt, both of which are solely for railway staff. In Portugal , railway stops are called halts ( Portuguese : apeadeiro ). In Ireland ,

2782-404: Is frequently, but not always, the final destination of trains arriving at the station. Especially in continental Europe, a city may have a terminus as its main railway station, and all main lines converge on it. In such cases all trains arriving at the terminus must leave in the reverse direction from that of their arrival. There are several ways in which this can be accomplished: There may also be

2889-611: Is one of the most densely packed stations. The upper platform level serves the Berlin Stadtbahn and consists of six elevated tracks on four bridge structures, served by three island platforms 10 metres (33 ft) high. The outer bridges carry one track each, while the inner bridges carry two each. The lower platform level serves the Berlin North–South mainline , and consists of eight underground tracks served by four island platforms 15 metres (49 ft 3 in) deep. To

2996-645: Is part of the mushroom concept in Berlin, in which the station forms a connecting point for converging and intersecting lines of different modes of public transport. The station's length is 430 metres (1,411 ft), though some of the platforms are 80 metres (260 ft) long. Structurally, the entire station complex is a tower station, while operationally it is a crossing station similar to all central stations. The complex consists of several independent operating points: The station building has two platform levels and three connecting and business levels. Compared to Raffles Place MRT station and Taipei main station , it

3103-514: Is the terminology typically used in the U.S. In Europe, the terms train station and railway station are both commonly used, with railroad being obsolete. In British Commonwealth usage, where railway station is the traditional term, the word station is commonly understood to mean a railway station unless otherwise specified. In the United States, the term depot is sometimes used as an alternative name for station , along with

3210-411: Is used for trains to pass the station without stopping is called through track. There may be other sidings at the station which are lower speed tracks for other purposes. A maintenance track or a maintenance siding, usually connected to a passing track, is used for parking maintenance equipment, trains not in service, autoracks or sleepers . A refuge track is a dead-end siding that is connected to

3317-751: The Chancellor of Germany Helmut Kohl , who also announced the reunification of Germany on 3 October 1990, it was decided to refurbish the area around the Bundestag into a modern government complex. As part of this effort, there were plans to extend the U5 from its western terminus at Alexanderplatz through the city centre, past the Brandenburg Gate and the Bundestag, to the new central train station, Berlin Hauptbahnhof. This Kanzlerlinie (Chancellor Line), so nicknamed because it passed through

Berlin Hauptbahnhof - Misplaced Pages Continue

3424-494: The S-Bahn , began service along two of the Stadtbahn tracks; long-distance traffic commenced in 1884 along the other two. With the expansion of Lehrter Bahnhof, it was able to take over the functions of Hamburger Bahnhof. A 300 m (984 ft) connector line was built; on 14 October 1884, traffic towards Hamburg , northeast Germany , and Scandinavia was diverted to Lehrter Bahnhof, and Hamburger Bahnhof closed. In 1886,

3531-466: The Second World War the station was severely damaged. After the war, the shell was repaired such that it could be used temporarily. During the late 1940s it became a frequent spot for Group of Soviet Occupation Forces in Germany soldiers to sexually assault passengers . However, the postwar division of Germany spelled the end for most of West Berlin 's mainline stations. On 28 August 1951

3638-629: The Shinkansen in Japan, THSR in Taiwan, TGV lines in France, and ICE lines in Germany. Stations normally have staffed ticket sales offices, automated ticket machines , or both, although on some lines tickets are sold on board the trains. Many stations include a shop or convenience store . Larger stations usually have fast-food or restaurant facilities. In some countries, stations may also have

3745-624: The Stuttgart engineering consultants Schlaich, Bergermann and Partner. The Hauptbahnhof was planned to have platforms for the cancelled Transrapid maglev train at track 8. Later on, it was replaced by normal railway tracks. The building work took place in several stages. In 1995 the construction of the Tiergarten tunnels began, and this work was finished in 2005 with the completion of the last station tunnel. The tunnels provide four tubes for long-distance and regional services and two tubes in

3852-1000: The Thameslink platforms at St Pancras in London, the Argyle and North Clyde lines of Glasgow's suburban rail network , in Antwerp in Belgium, the RER at the Gare du Nord in Paris, the Milan suburban railway service 's Passante railway , and many of the numerous S-Bahn lines at terminal stations in Germany, Austria and Switzerland, such as at Zürich Hauptbahnhof . Due to the disadvantages of terminus stations there have been multiple cases in which one or several terminus stations were replaced with

3959-525: The Tunnel Tiergarten Spreebogen . During Cyclone Kyrill , on 18 January 2007, the 8.4-metre (27 ft 7 in) long, 1.35-tonne (2,976 lb) horizontal strut 40 metres (131 ft 3 in) high, crashed from the lattice-like exterior onto a staircase, onto the southwestern part of the building, another strut was torn from the anchorage. These decorative elements had only been hung up and should only hold their own weight. As

4066-415: The "Pilzkonzept" (mushroom concept), in which a new north–south railway line intersecting the Stadtbahn was to be constructed. The name derived from the shape formed by the new line and existing lines, which vaguely resembles a mushroom. In June 1992 the federal government decided that the new station should be built on the site of Lehrter Bahnhof. While close to the centre of Berlin and government buildings,

4173-581: The 1980s, when operation of the West Berlin S-Bahn lines was transferred to the West Berlin transit authority, the BVG . Berlin 's 750th-anniversary celebration in 1987 saw the station, now under West Berlin control, renovated at a cost of about DM 10 million. Because it had largely been preserved in its original condition, it became a listed building . However, in 2002, Lehrter Stadtbahnhof

4280-626: The Berlin-Lehrte railway, and with it Lehrter Bahnhof, was nationalized and subsequently came under the control of the Prussian State Railways . Even in its early years, the line was known as one of the country's fastest: in 1872, express trains could attain a speed of 90 km/h (56 mph). 19 December 1932 marked the maiden voyage of the famous diesel-powered Fliegender Hamburger (Flying Hamburger), which whisked passengers to Hamburg at 160 km/h (99 mph). In

4387-609: The British Isles. The word is often used informally to describe national rail network stations with limited service and low usage, such as the Oxfordshire Halts on the Cotswold Line . It has also sometimes been used for stations served by public services but accessible only by persons travelling to/from an associated factory (for example IBM near Greenock and British Steel Redcar – although neither of these

Berlin Hauptbahnhof - Misplaced Pages Continue

4494-558: The Humbolthafen port on the river Spree . Its architects were Alfred Lent , Bertold Scholz , and Gottlieb Henri Lapierre . In contrast to earlier railway stations, built with brick façades, and in keeping with then-current trends, Lehrter Bahnhof was designed in the French Neo-Renaissance style. Its originally planned stone façade was replaced with glazed tiles to save money. With its magnificent architecture,

4601-536: The Stadtbahn viaduct at the northern end of Lehrter Bahnhof's concourse. This four-track station on the Stadtbahn was used mainly by suburban trains. The main purpose of the Stadtbahn was to connect central areas of Berlin with the Lehrter Bahnhof, the Schlesischer Bahnhof termini with nearby Charlottenburg , then still a separate city. It also provided an east–west railway connection across

4708-405: The arched, column-free, glass roof structure, which is supported by the two outer railway overpass structures. In the glass surface, a 2,700 square metres (29,000 sq ft) photovoltaic system with a capacity of 330 kilowatts was integrated. The hall is between 46 and 66 metres (151 and 217 ft) wide and a maximum of 16 metres (52 ft 6 in) high. It consists of three sections, with

4815-493: The area was still not heavily populated. The following year, a design competition for the project was held, which was won by the Hamburg architecture firm Gerkan, Marg and Partners . The design called for five levels. The highest level, on a bridge 10 metres (33 ft) above street level, was to have platforms for both long-distance and S-Bahn trains on the existing Stadbahn. The lowest level, 15 metres (49 ft) underground,

4922-484: The broadening from four to six tracks and the additional platforms, the total width has increased from 39 to 66 metres (128 to 217 ft) wide. The Humboldthafen Bridge spans the Humboldthafen with a span of 60 metres (197 ft). It consists of a bow with steel tubes and pre-stressed concrete beam as upper flange. The upper platform hall, which runs east–west, is 321 metres (1,053 ft) long and consists of

5029-530: The centre of Berlin. Because of steadily increasing traffic to Lehrter Stadtbahnhof and its location on a bridge crossing the north end of Lehrter Bahnhof, elaborate changes were made to the track structure in 1912 and again in 1929. On 1 December 1930, the newly electrified suburban trains were given the designation S-Bahn , making the Lehrter Stadtbahnhof an S-Bahnhof. During the War, in April 1943

5136-458: The city council suffered a major financial crisis. The city had accepted money from the German federal government for the construction work already finished, and by the terms of the agreement, the city would have had to return the money if there were no operating trains on the line. In 2004, the city and federal governments reached a compromise: the city would complete the short section of line that

5243-478: The compound forms train depot , railway depot , and railroad depot —it is used for both passenger and freight facilities. The term depot is not used in reference to vehicle maintenance facilities in the U.S., whereas it is used as such in Canada and the United Kingdom. The world's first recorded railway station, for trains drawn by horses rather than engined locomotives , began passenger service in 1807. It

5350-533: The construction of stations, from those boasting grand, intricate, Baroque - or Gothic -style edifices, to plainer utilitarian or modernist styles. Stations in Europe tended to follow British designs and were in some countries, like Italy, financed by British railway companies. Train stations built more recently often have a similar feel to airports, with a simple, abstract style. Examples of modern stations include those on newer high-speed rail networks, such as

5457-534: The cross-loading of freight and may be known as transshipment stations, where they primarily handle containers. They are also known as container stations or terminals. U55 (Berlin U-Bahn) U55 was an U-Bahn line in the German capital city of Berlin . It connected the new Berlin Hauptbahnhof , or main railway station, to an interchange with the S-Bahn at Brandenburger Tor . It had only three stations, did not connect to any other U-Bahn line, and

SECTION 50

#1732786994592

5564-434: The dedication. Reamonn and BAP performed at the station, and there were also events at the other new stations: Gesundbrunnen , Potsdamer Platz and Südkreuz . Berlin Hauptbahnhof officially went into operation on 28 May 2006. The opening ceremony was marred by an attack by a drunken 16-year-old wielding a knife , who stabbed members of the public leaving the ceremony. Forty-one people were wounded, six seriously, before

5671-472: The east are two tracks and an island platform serving U-Bahn line U5 (formerly line U55 ). Further to the east, a similar double track platform is being built as part of the S21 project. The bridges carrying the Stadtbahn are approximately 680 metres (2,231 ft) long, and span not only the station area, but also the adjacent Humboldthafen. Due to the way the Stadtbahn is aligned, they are curved, and due to

5778-421: The engineers, particularly as the glass roofs were shortened by approximately 100 metres (330 ft) to speed up construction. Over the first weekend of July 2002 the bridges and main station hall were brought into service so that traffic could be diverted onto the new alignment. The old Lehrter Stadtbahnhof S-Bahn station was closed and rapidly demolished to make way for further construction. On 9 September 2002

5885-406: The fifth track had no platform and served as a turnaround for the locomotives. At the turn of the century this track was removed to accommodate the widening of the central platform. Although the front of the building was ornate and had a grand entrance, most passengers entered and left via the east side, where horse-drawn carriages were able to stop. In 1882 the metropolitan railway, predecessor of

5992-402: The final train departed from Lehrter Bahnhof, heading for Wustermark and Nauen . On 9 July 1957 demolition began, and on 22 April 1958 the main entrance was blown up. The biggest challenge in the demolition of the station was to preserve the viaducts of the Stadtbahn, which ran directly overhead. Work was completed in the summer of 1959. On 15 May 1882, Lehrter Stadtbahnhof opened, situated on

6099-433: The frames, each weighing 1,250 t (2,755,778 lb), were lowered by steel cables at a rate of 6 m (19 ft 8 in) per hour; the remaining 20 mm (0.79 in) gap between the bow frames upon completion of the lowering process was subsequently closed. During summer 2003 a survey commissioned by Peter Strieder, Berlin 's Senator for City Development and Traffic, and Deutsche Bahn director Hartmut Mehdorn

6206-476: The goods facilities are on the opposite side of the tracks from the station building. Intermediate stations also occur on some funicular and cable car routes. A halt , in railway parlance in the Commonwealth of Nations , Ireland and Portugal , is a small station, usually unstaffed or with very few staff, and with few or no facilities. In some cases, trains stop only on request , when passengers on

6313-522: The government quarter, was originally planned since the 200km plan as a diagonal line through central Berlin, continuing to Turmstraße in Moabit , where it would link with the U9 , and on to Jungfernheide , where it would connect with the S-Bahn ring and U7 . The line was also planned to go via Tegel Airport (to be replaced by Urban Tech Republic), Scharnweberstraße towards Rathaus Reinckendorf . As this

6420-401: The layout of the platforms. Apart from single-track lines, the most basic arrangement is a pair of tracks for the two directions; there is then a basic choice of an island platform between, two separate platforms outside the tracks ( side platforms ), or a combination of the two. With more tracks, the possibilities expand. Some stations have unusual platform layouts due to space constraints of

6527-417: The less developed KTM East Coast railway line to serve rural 'kampongs' (villages), that require train services to stay connected to important nodes, but do not have a need for staff. People boarding at halts who have not bought tickets online can buy it through staff on board. In rural and remote communities across Canada and the United States, passengers wanting to board the train at such places had to flag

SECTION 60

#1732786994592

6634-481: The line as U55 indicated that it was ultimately intended to become part of the U5 line. Construction of the link to enable this commenced in April 2010, and was originally expected to be completed by 2017. Construction works suffered from continued difficulties, mainly concerning high water contents in the soil; in November 2015 the opening date was postponed, with the link finally opening on 4 December 2020. The link

6741-615: The line was extended to Alexanderplatz and it became part of line U5 . Railway station Locations at which passengers only occasionally board or leave a train, sometimes consisting of a short platform and a waiting area but sometimes indicated by no more than a sign, are variously referred to as "stops", " flag stops ", " halts ", or "provisional stopping places". The stations themselves may be at ground level, underground, or elevated. Connections may be available to intersecting rail lines or other transport modes such as buses , trams , or other rapid transit systems. Train station

6848-541: The loading and unloading of goods and may well have marshalling yards (classification yards) for the sorting of wagons. The world's first goods terminal was the 1830 Park Lane Goods Station at the South End Liverpool Docks. Built in 1830, the terminal was reached by a 1.24-mile (2 km) tunnel. As goods are increasingly moved by road, many former goods stations, as well as the goods sheds at passenger stations, have closed. Many are used purely for

6955-403: The main reception facilities being at the far end of the platforms. Sometimes the track continues for a short distance beyond the station, and terminating trains continue forward after depositing their passengers, before either proceeding to sidings or reversing to the station to pick up departing passengers. Bondi Junction , Australia and Kristiansand Station , Norway are examples. A terminus

7062-497: The middle of 2001, commissioning for 2006 was expected. Construction of the bridges for the new S-Bahn route began in 2001. These needed to span not only the entire length of the station, but also the adjacent Humboldthafen port, and are 450 m (1,480 ft) long. Because of the alignment of the S-Bahn they are curved, and each pair of tracks has a separate bridge. Bridges of this type had never been built before, and represented

7169-424: The money to the federal government. The opening of the line between Berlin Hauptbahnhof and Brandenburger Tor was delayed owing to extreme groundwater problems at the site of the latter new station. It was finally opened on 8 August 2009. With the opening of the U-Bahn station, the existing Unter den Linden S-Bahn station was renamed Brandenburger Tor (for the nearby Brandenburg Gate). The name "Unter den Linden"

7276-407: The northeastern part of the two diagonally opposite station terraces, the sculpture of Rolling Horse, erected in 2007 by Jürgen Goertz, artificially complements the building and is reminiscent to Lehrter Bahnhof and Lehrter Stadtbahnhof. There are integrated artificial elements, which can be viewed through four portholes. From the southwestern terrace, it rises the disguised chimney located underneath

7383-816: The other. For instance, in Istanbul transfers from the Sirkeci Terminal (the European terminus) and the Haydarpaşa Terminal (the Asian terminus) historically required crossing the Bosphorus via alternative means, before the Marmaray railway tunnel linking Europe and Asia was completed. Some cities, including New York, have both termini and through lines. Terminals that have competing rail lines using

7490-403: The pits, which are 90,000 m (970,000 sq ft) in total and about 20 metres (65 ft 7 in) deep. In their place, 227,000 m (8,000,000 cu ft) of concrete and 13,000 tons of steel reinforcement were installed. With 27-metre (89 ft)-long buoyancy anchors (a total of 250 kilometres (160 mi)) and 180 kilometres (110 mi) of inclined anchors, the foundation

7597-596: The platform indicate that they wish to board, or passengers on the train inform the crew that they wish to alight. These can sometimes appear with signals and sometimes without. The Great Western Railway in Great Britain began opening haltes on 12 October 1903; from 1905, the French spelling was Anglicised to "halt". These GWR halts had the most basic facilities, with platforms long enough for just one or two carriages; some had no raised platform at all, necessitating

7704-469: The provision of steps on the carriages. Halts were normally unstaffed, tickets being sold on the train. On 1 September 1904, a larger version, known on the GWR as a "platform" instead of a "halt", was introduced; these had longer platforms, and were usually staffed by a senior grade porter, who sold tickets and sometimes booked parcels or milk consignments. From 1903 to 1947 the GWR built 379 halts and inherited

7811-426: The railways to West Berlin under the control of East Germany , Lehrter Bahnhof was demolished, but Lehrter Stadtbahnhof remained as a stop on the S-Bahn. In 1987, it was extensively renovated to commemorate Berlin's 750th anniversary. After German reunification , it was decided to improve Berlin's railway network by constructing a new north–south main line , to supplement the east-west Stadtbahn. Lehrter Stadtbahnhof

7918-565: The same day, Berlin Papestraße station, which was rebuilt as the city's second-largest station, opened officially under its new name, Berlin Südkreuz (South Cross), similar to the existing Ostkreuz and Westkreuz stations. It is also on the new north–south route. Although it was intended to open a further station as Berlin-Nordkreuz (North Cross), the name Berlin-Gesundbrunnen was retained for what became Berlin's fourth biggest railway station for commuter and long-distance trains, located in

8025-419: The south-west façade were torn loose during European windstorm Kyrill . One of them, an 8.4-metre (27 ft 7 in)-long beam weighing 1.35-tonne (2,976 lb), dropped 40 metres (130 ft) onto a staircase below, and the other impacted and damaged a third beam. The station had suffered some flooding and had been evacuated due to the complete cancellation of train service in Germany. Consequently, nobody

8132-566: The station construction timeline without proper approval. The complaint was upheld in late 2006. There may therefore be further construction on the station in the future. In addition, Deutsche Bahn decided to implement a slightly different version of the "Pilzkonzept" by running intercity trains through the new Tiergarten tunnels rather than via the Stadtbahn. This move was unpopular for its effect on Berlin's two previous main stations; Bahnhof Berlin Zoologischer Garten (Zoo Station)

8239-487: The station each year. After groundwater had penetrated into the excavation pit as a result of a leak, the completion date was postponed in the spring of 1999. The incident necessitated a far-reaching change in the safety concept during the construction phase, in order to keep the groundwater lying about 3 metres (9 ft 10 in) below the ground. Under the new schedule, the station's shell should have been finished in 2003, and trial operations should have begun in 2004. In

8346-405: The station entrance and platforms are on the same level, is also common, but is perhaps rarer in urban areas , except when the station is a terminus. Stations located at level crossings can be problematic if the train blocks the roadway while it stops, causing road traffic to wait for an extended period of time. Stations also exist where the station buildings are above the tracks. An example of this

8453-477: The station frequently set up a jointly owned terminal railroad to own and operate the station and its associated tracks and switching operations. During a journey, the term station stop may be used in announcements, to differentiate halts during which passengers may alight and halts for another reasons, such as a locomotive change . While a junction or interlocking usually divides two or more lines or routes, and thus has remotely or locally operated signals ,

8560-567: The station location, or the alignment of the tracks. Examples include staggered platforms, such as at Tutbury and Hatton railway station on the Crewe–Derby line , and curved platforms, such as Cheadle Hulme railway station on the Macclesfield to Manchester Line. Stations at junctions can also have unusual shapes – a Keilbahnhof (or "wedge-shaped" station) is sited where two lines split. Triangular stations also exist where two lines form

8667-645: The station was bombed by the Polish sabotage and diversionary squad " Zagra-lin ". The Stadtbahnhof survived WWII intact, but came to lose its pre-war significance due to the division of Berlin; with Lehrter Bahnhof closed, the Stadtbahnhof served only a relatively underpopulated area near the border with East Berlin . It was the final stop in West Berlin ; the next station, Berlin Friedrichstraße ,

8774-407: The station was known as a "palace among stations". The train shed was 188 metres (617 ft) long and 38 metres (125 ft) wide. Its roof was a long barrel vault with steel supports. As was common for the period, the station was divided into an arrival side on the west, and a departure side on the east. Originally there were five tracks, four of which ended at the side and the central platform;

8881-410: The station was renamed "Berlin Hauptbahnhof – Lehrter Bahnhof". The main concourse, supported by two towers, provides roughly 44,000 m (470,000 sq ft) of commercial space. Construction of the towers began in 2005. On two separate weekends, 29 July and 13 August 2005, structural frames were installed, supporting the structure above the east–west tracks. This was built using a new technique:

8988-528: The station, a smaller interchange station called Lehrter Stadtbahnhof was opened to provide connections with the new line. This station later became part of the Berlin S-Bahn. In 1884, after the closure of nearby Hamburger Bahnhof (Hamburg Station), Lehrter Bahnhof became the terminus for trains to and from Hamburg . Following heavy damage during World War II , limited services to the main station were resumed, but then suspended in 1951. In 1957, with

9095-557: The street to underground rapid-transit urban rail stations. In many African, South American, and Asian countries, stations are also used as a place for public markets and other informal businesses. This is especially true on tourist routes or stations near tourist destinations . As well as providing services for passengers and loading facilities for goods, stations can sometimes have locomotive and rolling stock depots, usually with facilities for storing and refuelling rolling stock and carrying out minor repairs. The basic configuration of

9202-442: The train down to stop it, hence the name " flag stops " or "flag stations". Accessibility for disabled people is mandated by law in some countries. Considerations include: In the United Kingdom, rail operators will arrange alternative transport (typically a taxi ) at no extra cost to the ticket holder if the station they intend to travel to or from is inaccessible. Goods or freight stations deal exclusively or predominantly with

9309-489: The western segment 172 metres (564 ft) and the eastern 107 metres (351 ft) long. In between lies the 50 metres (164 ft) wide and 180 metres (591 ft) long north–south roof, whose barrel vaults with the main roof form a flat viaduct. Parallel to the north–south roof, the two "ironing structures" span the main roof of the platform hall and carry the north–south roof. These ironing structures contain 42,000 square metres (450,000 sq ft) of office space. On

9416-618: The world was Crown Street railway station in Liverpool, England , built in 1830, on the locomotive-hauled Liverpool to Manchester line. The station was slightly older than the still extant Liverpool Road railway station terminal in Manchester. The station was the first to incorporate a train shed . Crown Street station was demolished in 1836, as the Liverpool terminal station moved to Lime Street railway station . Crown Street station

9523-455: The youth was arrested. According to police, the youth said he could not remember his act of violence and denied it. One of the first stabbing victims was HIV -positive, leading to worries that other victims may have been infected, although this did not prove to be the case. The youth was charged with attempted murder, and was sentenced to seven years in prison for attempted manslaughter in 33 cases in 2007. On 18 January 2007, two steel beams of

9630-591: Was The Mount in Swansea , Wales, on the Oystermouth (later the Swansea and Mumbles ) Railway. The world's oldest station for engined trains was at Heighington , on the Stockton and Darlington railway in north-east England built by George Stephenson in the early 19th century, operated by locomotive Locomotion No. 1 . The station opened in 1827 and was in use until the 1970s. The building, Grade II*-listed ,

9737-416: Was a long-planned route, short tunnels exist at both Jungfernheide and Turmstraße to accommodate the new line. Plans were discarded as a tram was also planned to be extended west. For now, the line is only approved to terminate at the Hauptbahnhof, with the route to Jungfernheide and beyond to be built later. On 19 January 2000, construction began on the western end of this extension. However, around that time

9844-533: Was anchored against the buoyant pressure of groundwater (200 kilonewtons per square meter). On 9 September 1998, the foundation stone was laid symbolically by Federal Minister of Transport Wissmann, railway director Ludewig and Berlin's governing mayor Eberhard Diepgen in the then 17-metre (56 ft)-deep excavation pit. The commissioning date was in 2003. Construction costs were estimated at 800 million DM (€409 million). Over 50 million long-distance passengers and 86 million regional passengers were projected to use

9951-526: Was called a "rail motor stopping place" (RMSP). Usually situated near a level crossing , it was often designated solely by a sign beside the railway. The passenger could hail the driver to stop, and could buy a ticket from the train guard or conductor. In South Australia, such facilities were called "provisional stopping places". They were often placed on routes on which "school trains" (services conveying children from rural localities to and from school) operated. In West Malaysia , halts are commonplace along

10058-447: Was closed until December 2018 to accommodate the work needed to connect it to this new phase of the project. The complete project, merging U55 and U5 into a single line, opened on 4 December 2020. Operation of the U55 ceased on 17 March 2020 in preparation for the line's incorporation into the U5 extension. The unusual nature of U55 reflected Berlin's troubled finances. When the German government decided to move from Bonn to Berlin under

10165-531: Was conducted among Berlin residents with the intention of selecting a name for the station. Of the three possibilities listed on the survey, the majority of participants opted for Lehrter Bahnhof; nevertheless, the station remained "Berlin Hauptbahnhof – Lehrter Bahnhof", an option that was not listed. It was decided early in 2005 that the station would be renamed "Berlin Hauptbahnhof " on the date of its opening, 28 May 2006, to avoid confusing rail passengers. On

10272-721: Was considered to be the logical location for a new central station. The station is located in the Moabit district, in the Mitte constituency. To the north is Europaplatz and Invalidenstraße , and to the south is Washingtonplatz and the Spree . South of the station is the Spreebogenpark , the Bundeskanzleramt , and the Paul-Löbe-Haus. To the east is the Mitte district and the Humboldthafen. Berlin Hauptbahnhof

10379-627: Was converted to a goods station terminal. The first stations had little in the way of buildings or amenities. The first stations in the modern sense were on the Liverpool and Manchester Railway , opened in 1830. Manchester's Liverpool Road Station , the second oldest terminal station in the world, is preserved as part of the Museum of Science and Industry in Manchester . It resembles a row of Georgian houses. Early stations were sometimes built with both passenger and freight facilities, though some railway lines were goods-only or passenger-only, and if

10486-488: Was demolished to make way for the new central station, despite its listed status. The argument was that Bellevue and Hackescher Markt stations were architecturally similar. Hackescher Markt, in former East Berlin , had been restored in 1994–1996, after German reunification . Soon after the fall of the Berlin Wall in 1989, city planners began work on a transport plan for reunified Berlin. One element of this became

10593-414: Was downgraded to a regional railway station, and the number of mainline services to Berlin Ostbahnhof (East Station) was drastically reduced. On 26 May 2006, the station was ceremonially opened by Chancellor Angela Merkel , who arrived together with transport minister Wolfgang Tiefensee in a specially chartered Intercity Express from Leipzig . A "Symphony of Light" was performed immediately following

10700-746: Was in East Berlin , although it served as a stop on the West Berlin S- and U-Bahn systems; these parts of the station were sealed off and inaccessible to East Berliners. The S-Bahn, like the mainlines leading to West Berlin , was run by the East German railway, the Deutsche Reichsbahn . The 1961 construction of the Berlin Wall further isolated the station, and led to a boycott of the S-Bahn in West Berlin that lasted until

10807-519: Was in bad condition, but was restored in 1984 as an inn. The inn closed in 2017; in 2024 there were plans to renovate the derelict station in time for the 200th anniversary of the opening of the railway line. The two-storey Mount Clare station in Baltimore , Maryland , United States, which survives as a museum, first saw passenger service as the terminus of the horse-drawn Baltimore and Ohio Railroad on 22 May 1830. The oldest terminal station in

10914-554: Was injured and the station was cleared for reopening the following day. The beams had not been welded or bolted in place but laid down like shelves in a bookcase. In the next days extra lugs were welded to the remaining beams to secure them in place and the station declared stormproof on 23 January. The Berlin U-Bahn line U55 opened in August 2009, connecting Hauptbahnhof with the Brandenburger Tor station . In December 2020

11021-412: Was largely complete between Berlin Hauptbahnhof and Unter den Linden S-Bahn station (renamed "Brandenburger Tor" in 2009) and run it as a single-track shuttle with a single train, without any signaling. Although transit planners projected that such a shuttle would not attract a significant ridership, the city determined that the cost of building and operating the line would be less than the cost of returning

11128-513: Was operated as a shuttle line using a single train. The line was constructed as part of an extension of the U5 that was subsequently postponed due to financial difficulties. As much of the work on this disconnected section of the extension had been completed, it was decided to complete the section and open it as a separate line in 2009. In 2010, construction began on the intervening section connecting Brandenburger Tor to Alexanderplatz; on 4 June 2018, U55

11235-436: Was signed between Perleberger Straße and Spreebogen, between the federal government and the railway in the total amount of €700 million. The federal share amounted to €500 million. Any additional cost increases were supposed to be broken down according to a defined key. New York-based Tishman Speyer Properties was commissioned by Bahn AG to develop the station. Execution planning and construction supervision were carried out by

11342-448: Was then given to a new station further east at the junction with Friedrichstraße , where the U5 intersects the U6 . The train ran every 10 minutes and, due to the low demand, there was no night service. Because the U55 was not physically connected to the rest of the U-Bahn system, any trains being delivered to the new line had to be taken by low loaders on the street and set on track through

11449-472: Was to have platforms served by new tunnels to Potsdamer Platz under the Spree and the Tiergarten , forming a new north–south line running to the northern part of the S-Bahn ring around central Berlin. Platforms for the planned extension to U-Bahn line 5 were also included. The planning approval for the station and the north–south connection was made on 12 September 1995. In 1997, a financing agreement

#591408