Misplaced Pages

Lungmen Nuclear Power Plant

Article snapshot taken from Wikipedia with creative commons attribution-sharealike license. Give it a read and then ask your questions in the chat. We can research this topic together.

The Lungmen Nuclear Power Plant ( Chinese : 龍門核能發電廠 ; pinyin : Lóngmén Hénéng Fādiànchǎng ), formerly known as Gongliao and commonly as the Fourth Nuclear Power Plant ( Chinese : 核四 ; pinyin : Hésì ; lit. 'Nuke 4'), is an unfinished nuclear power plant in New Taipei City , Taiwan. It consists of two ABWRs each of 1,300  MWe net. It is owned by Taiwan Power Company (Taipower).

#882117

49-494: It was intended to be the first of these advanced Generation III reactors built outside Japan . The preceding four reactors in Japan were completed in four to five years. However, Taipower did not award the contract to a single architect/engineering firm; instead, they split the procurement among multiple vendors, complicating project management and increasing costs. In 2000, the project was canceled due to political opposition when it

98-408: A nuclear renaissance suggesting that Gen III+ designs should solve three key problems: safety, cost and buildability. Construction costs of US$ 1,000/kW were forecast, a level that would make nuclear competitive with gas, and construction times of four years or less were expected. However, these estimates proved over-optimistic. A notable improvement of Gen III+ systems over second-generation designs

147-528: A 200-tonne core catcher in the VVER reactor as the first large piece of equipment in the reactor building of Rooppur 1 , describing it as "a unique protection system". In 2017, Rosatom has started commercial operations of the NVNPP-2 Unit 1 VVER-1200 reactor in central Russia, marking the world's first full start-up of a generation III+ reactor. The first Generation III reactors were built in Japan, in

196-684: A local referendum gathered 50,000 signatures by March 2013, but the proposed referendum was rejected by the Executive Yuan Referendum Review Committee  [ zh ] in May 2013, ruling the issue was of national importance, and could not be decided by local referendum. She launched another local referendum in June 2013 in opposition to the KMT-authored Lee referendum. Meanwhile, Lu filed suit in 2014 in

245-733: A national referendum could be held; Taipower estimated the three-year cost of sealing Unit 1 as less than NT$ 2 billion. In September 2014 Taiwan Power Co. submitted its plan to the Atomic Energy Council (AEC) to mothball Unit 1 and halt construction on Unit 2 of the No. 4 nuclear power plant for three years, beginning in 2015. The plan, written in accordance with the April 2014 government directive to halt construction, underwent several revisions until its final submission in January 2015;

294-515: A nuclear power plant after decades of no construction activity on a legacy construction project. The Fourth Nuclear Power Plant was first proposed in 1978, and Taipower selected the ABWR in 1996 after a competitive bidding process. The reactor is designed by General Electric , but is supported by Hitachi , Shimizu Corporation , Toshiba , and other American, Taiwanese, and other Chinese and international companies. The application to start construction

343-566: A popular poll, which favored lowering the threshold of participation and opposed continued construction. The proposed Kao referendum was rejected by the Executive Yuan Referendum Review Committee in August 2014, citing the language as confusing and contradictory, since the reason given for the referendum is in opposition to nuclear power, while the referendum itself asks to start a nuclear reactor, despite

392-423: A rated thermal power of 3,926 MW (1.340 × 10 BTU/h); the core is composed of 872 GE14 fuel assemblies , and water is circulated using ten reactor internal pumps at a rate of 52.2 × 10 kg/h (1.15 × 10 lb/h), generating 7.637 × 10 kg/h (1.684 × 10 lb/h) of steam at full power. A Generation III nuclear reactor has a 72-hour capability of passive cooling to prevent damage to its core should

441-487: A vote to place the Lee referendum on the national ballot. This led to a scuffle when KMT legislators attempted to break through the barricade, and the Lee referendum was not voted on. In the following legislative session, protesters called on the government to withdraw the Lee referendum, and it was subsequently withdrawn. Annette Lu used the local referendum process to debate the plant's fate as early as 2012. Her petition for

490-613: A whole are safer than older reactors. Edwin Lyman , a senior staff scientist at the Union of Concerned Scientists , has challenged specific cost-saving design choices made for two Generation III reactors, both the AP1000 and ESBWR . Lyman, John Ma (a senior structural engineer at the NRC), and Arnold Gundersen (an anti-nuclear consultant) are concerned about what they perceive as weaknesses in

539-848: Is arbitrary, few Gen III reactors have reached the commercial stage as of 2022. The Generation IV International Forum calls Gen IV reactors "revolutionary designs". These are concepts for which no concrete prognoses for realization existed at the time. The improvements in reactor technology in third generation reactors are intended to result in a longer operational life (designed for 60 years of operation, extendable to 100+ years of operation prior to complete overhaul and reactor pressure vessel replacement) compared with currently used Generation II reactors (designed for 40 years of operation, extendable to 60+ years of operation prior to complete overhaul and pressure vessel replacement). The core damage frequencies for these reactors are designed to be lower than for Generation II reactors – 60 core damage events for

SECTION 10

#1732791817883

588-683: Is believed this experience provided knowledge that will give better results in future units. The first two units built, Kashiwazaki Kariwa 6 & 7 fared much better than the following two, Hamaoka 5 and Shika 2. Generation III reactors Generation III reactors , or Gen III reactors , are a class of nuclear reactors designed to succeed Generation II reactors, incorporating evolutionary improvements in design. These include improved fuel technology , higher thermal efficiency , significantly enhanced safety systems (including passive nuclear safety ), and standardized designs intended to reduce maintenance and capital costs. They are promoted by

637-488: Is the incorporation in some designs of passive safety features that do not require active controls or operator intervention but instead rely on gravity or natural convection to mitigate the impact of abnormal events. Generation III+ reactors incorporate extra safety features to avoid the kind of disaster suffered at Fukushima in 2011. Generation III+ designs, passive safety, also known as passive cooling, requires no sustained operator action or electronic feedback to shut down

686-624: The EPR as the only new reactor design under consideration in the United States that "...appears to have the potential to be significantly safer and more secure against attack than today's reactors." There have also been issues in fabricating the precision parts necessary to maintain safe operation of these reactors, with cost overruns, broken parts, and extremely fine steel tolerances causing issues with new reactors under construction in France at

735-763: The European Pressurized Reactor (EPR) and 3 core damage events for the Economic Simplified Boiling Water Reactor (ESBWR) per 100 million reactor-years are significantly lower than the 1,000 core damage events per 100 million reactor-years for BWR/4 Generation II reactors. The third generation EPR reactor was also designed to use uranium more efficiently than older Generation II reactors, using approximately 17% less per unit of electricity generated than these older reactor technologies. An independent analysis conducted by environmental scientist Barry Brook on

784-658: The Executive Yuan of the Republic of China ( Taiwan ) which is responsible for atomic safety, development and regulations. It also conducts research and development into atomic technologies. It is affiliated with IAEA by special agreements to safeguard the peaceful development of the nuclear energy by the Republic of China government. The agency was created in 1955 as the Atomic Energy Council by

833-510: The Flamanville Nuclear Power Plant . Atomic Energy Council 25°0′11.37″N 121°31′35.51″E  /  25.0031583°N 121.5265306°E  / 25.0031583; 121.5265306 The Nuclear Safety Commission ( NSC ; Chinese : 核能安全委員會 ; pinyin : Xíngzhèng Yuàn Yuánzǐnéng Wěiyuánhuì ; Pe̍h-ōe-jī : Hêng-chèng Īⁿ Goân-chú-lêng Úi-oân-hōe ) is an independent government agency of

882-542: The Fukushima Daiichi nuclear disaster . By obtaining the signatures of a certain percentage of registered voters, or by legislative action, a referendum may be referred to the national ballot for voter action. However, due to the politically sensitive nature of the Fourth Nuclear Plant issue, legislatively-referred and voter-referred referendums had failed to enter the national ballot. Because of

931-546: The Generation IV International Forum (GIF). The first Generation III reactors to begin operation were Kashiwazaki 6 and 7 advanced boiling water reactors (ABWRs) in 1996 and 1997. From 2012, both have been shut down due to a less permissive political environment in the wake of the Fukushima nuclear accident . Due to the prolonged period of stagnation in the construction of new reactors and

980-879: The Taishan Nuclear Power Station (first grid connection on 2018-06-29) and a Westinghouse AP1000 reactor at the Sanmen Nuclear Power Station (first grid connection on 2018-06-30) in China. In the United States, reactor designs are certified by the Nuclear Regulatory Commission (NRC). As of August 2020 , the commission has approved seven new designs, and is considering one more design as well as renewal of an expired certification. Proponents of nuclear power and some who have historically been critical have acknowledged that third generation reactors as

1029-571: The AEC approved Taipower's final plan in February, and it will take effect in July 2015 and run through 2017. Of the 126 systems which passed safety testing, 80 will remain in operation, 14 require periodic testing to ensure they can support their safety functions and 32 will be kept in low-humidity storage. It was estimated the cost of maintaining the mothballed reactor is 1.3 billion NT Dollars per year. With

SECTION 20

#1732791817883

1078-471: The Executive Yuan. Since then, it has assisted industry in developing nuclear power for commercial use and allowed universities to conduct research into atomic energy. On 27 September 2023, the agency is renamed to Nuclear Safety Commission . The agency is still primarily responsible for the supervision of nuclear power plants, nuclear facilities, and radiation workplaces. It also strictly implement

1127-597: The Kao referendum was formulated to require positive action: "Do you agree to allow Taiwan Power Co to insert fuel rods into the Fourth Nuclear Power Plant in New Taipei City for a test run" so poor voter turnout would result in referendum defeat, and thus create binding opposition to starting the plant. In April 2014, the government decided to halt construction. The first reactor was sealed after

1176-551: The Taipei High Administrative Court over the Executive Yuan's rejection of the earlier referendum. The court's decision is expected in August 2014. Taipower applied for the initial fuel loading of Unit 1 on December 31, 2013. A competing referendum was launched in 2012 by National Taiwan University professor Kao Cheng-yan , initially as a local referendum and then a national one in July 2014, once sufficient signatures had been gathered. The language of

1225-494: The completion of safety checks, and construction of the second reactor was halted. A final decision on whether to proceed with construction would be subject to another referendum. The ruling KMT stated the purpose of a new referendum was to have the people decide the plant's fate while weighing the consequences of not bringing a major power source on-line. Electricity prices are estimated to rise by 14–40%, and electricity rationing could be imposed as early as 2021. Completely cancelling

1274-494: The construction site, prompting calls to halt construction again. In 2011 the Taiwan Atomic Energy Council (AEC) criticized Taipower's management of the project. Taipower was fined by the AEC twice, in 2008 and 2011, for completing design changes without first obtaining approval from the plant's designer, General Electric. Taipower later stated the changes were executed to stay on schedule, and approval

1323-418: The continued (albeit declining) popularity of Generation II/II+ designs in new construction, relatively few third generation reactors have been built. The older Gen II reactors comprise the vast majority of current nuclear reactors. Gen III reactors are so-called advanced light-water reactors (LWRs). Gen III+ reactors are labeled as "evolutionary designs". Though the distinction between Gen II and III reactors

1372-579: The controversy over the plant, in February 2013 the Kuomintang (KMT)-led government proposed that a referendum should be issued, which would allow the people of the country to decide the fate of the plant. The proposed referendum was sponsored by 32 KMT lawmakers led by Lee Ching-hua and asked "Do you agree that the construction of the Fourth Nuclear Power Plant should be halted and that it not become operational?" Referendums must have good voter turnout (greater than 50% of registered voters must participate in

1421-573: The form of advanced boiling water reactors . On 5 August 2016, a Generation III+ VVER-1200 /392M reactor became operational (first grid connection) at Novovoronezh Nuclear Power Plant II in Russia, which was the first operational Generation III+ reactor. Several other Generation III+ reactors are under late-stage construction in Europe, China, India, and the United States. The next Generation III+ reactors to come online were an AREVA EPR reactor at

1470-580: The formal entry into mothball status on July 1, Unit 1 is required to resubmit the application for initial fuel loading. In September 2015 GE started International Court of Arbitration proceedings over withheld payments. In 2018, Taipower started shipping unused fuel rods back to the US . Taipower is required to remove all fuel rods from the plant by 2020. The ruling Democratic Progressive Party plans to shut down all nuclear plants in Taiwan by 2025. The removal of

1519-552: The fuel rods may mean that the plant's construction will never be restarted. Taipower stated it would take at least six years to start commercial operations at Unit 1 due to fuel removal, obsolescence of components in the ABWR NSSS, and startup testing. In December 2021, the proposal of the re-construction of the plant was rejected, further ensuring that the construction would not be restarted in near future. Lungmen Nuclear Power Plant consists of two identical ABWR units, each with

Lungmen Nuclear Power Plant - Misplaced Pages Continue

1568-484: The fuel to the United States. In December 2021, the proposal to continue construction of Unit 2 was narrowly rejected in a referendum . Given that Tsai Ing Wen of the ruling DPP opposes nuclear power and wishes to complete a nuclear phaseout by 2025 (one year after the 2024 Taiwanese presidential election ), it is unlikely that construction will ever restart even though it is technologically feasible in principle and not without precedent to finish construction of

1617-521: The greater efficiency and therefore lower material needs of Gen III reactors, corroborates this finding. Gen III+ reactor designs are an evolutionary development of Gen III reactors, offering improvements in safety over Gen III reactor designs. Manufacturers began development of Gen III+ systems in the 1990s by building on the operating experience of the American, Japanese, and Western European light-water reactor . The nuclear industry began to promote

1666-444: The plant face a total blackout after an emergency shut down. If core overheating and meltdown became unavoidable, these reactors have core catchers that will trap the molten fuel and stop the nuclear reaction (although Lungmen, as other ABWR does not have a core catcher but rely on passive cooling of the corium). Finally, a tight containment ensures that no evacuation zone is required around a Generation III nuclear power plant. The ABWR

1715-471: The plant safely in the event of an emergency. Many of the Generation III+ nuclear reactors have a core catcher . If the fuel cladding and reactor vessel systems and associated piping become molten, corium will fall into a core catcher which holds the molten material and has the ability to cool it. This, in turn protects the final barrier, the containment building . As an example, Rosatom installed

1764-483: The plant would force Taipower to book the construction budget as a total loss and force it into insolvency. Meanwhile, also in April 2014, the opposition DPP planned to introduce special legislation to bypass the provisions of the Referendum Act, allowing a simple majority vote (with no threshold of participation) to decide the plant's fate. Premier Jiang Yi-huah cited the prior 2000 precedent when construction

1813-508: The plant's foundation as potential issues. President Chen Shui-bian was elected along with other Democratic Progressive Party (DPP) legislators in March 2000 on an anti-nuclear platform which included stopping plant construction. DPP legislators called for a halt to the project in April 2000, which led to the suspension of construction in October 2000 by Premier Chang Chun-hsiung when it

1862-404: The referendum gathering more than 120,000 signatures. Undaunted, supporters of the Kao referendum vowed in October 2014 to initiate another referendum. That same month, Unit 1 completed the required safety tests before the start of operations. 126 systems were tested including cooling, shutdown, containment, control and power generation. Minister of Economic Affairs Chang Chia-juch said, "Passing

1911-424: The referendum vote), and a majority of participating voters must vote yes in order for the referendum to become binding, meaning that poor voter turnout would ensure referendum defeat (and in the case of the Lee referendum, continued construction). The opposition DPP claimed that getting better than 50% voter turnout in a non-Presidential election year was too difficult, and barricaded the legislative chamber to prevent

1960-479: The rigorous review illustrates the high standards of care invested in the design and construction of the facility." Past polls in Taiwan have showed more support for nuclear power among educated than uneducated people. The China Times poll taken in 2000 showed 60% support among those with higher degrees, and only 40% among those with only primary education. The Ministry of Economic Affairs proposed in August 2014 that further construction be halted for three years until

2009-459: The steel containment vessel and the concrete shield building around the AP1000 in that its containment vessel does not have sufficient safety margins in the event of a direct airplane strike. Other engineers do not agree with these concerns, and claim the containment building is more than sufficient in safety margins and factors of safety . The Union of Concerned Scientists in 2008 referred to

Lungmen Nuclear Power Plant - Misplaced Pages Continue

2058-455: The turbines and the generators, and other contractors for the rest, making the project difficult to manage. Construction has been delayed by legal, regulatory and political obstacles. The delays in schedule also have increased the cost of the project, due to the inflation of the costs of raw materials. The 921 earthquake in 1999 prompted three legislators to inspect construction progress; they cited rusty rebar and potential seawater seepage into

2107-455: Was approximately 10–30% complete but restarted in February 2001. A national referendum was proposed in 2014 to decide if construction of the plant should continue, but the referendum was rejected from the ballot for contradictory and confusing language. Taipower submitted a plan to mothball Unit 1, which was by then complete, and freeze construction of Unit 2, starting in 2015. In 2018, Taipower started removing unused fuel from Unit 1 and returned

2156-476: Was approximately 10–30% complete, only to restart the following year. Contractors were idled for 111 days (from 27 October 2000 to 14 February 2001), which caused a 576-day delay towards commercial operation. Taipower constructed a wharf in 2003 to accommodate delivery of heavy components, such as the reactor vessel. The wharf was beset with construction delays and may have contributed to local beach erosion , prompting further protests. Each reactor vessel delivery

2205-462: Was designed to a 0.3G earthquake acceleration standard with the Lungmen units seismic hardening increased to 0.4G. Some custom made power plants have lower reliability in the first few years of operation. Some parts may prove unsuitable and need replacement or modifications may be necessary. ABWR uses standardized parts to avoid this, but the 3rd and 4th units displayed low reliability (45% - 70%). It

2254-399: Was greeted with activist protests and construction delays resulted in the vessels being stored longer than expected, with Unit 1's reactor vessel not installed until 2005. Design of the plant was carried out by Stone & Webster (S&W), but Taipower canceled its contract with S&W in 2007, leading to protracted litigation from 2007 to 2011. In 2010, aboriginal artifacts were found at

2303-469: Was interrupted by executive order which was later ruled unconstitutional as the reason why he rejected the proposed special legislation. The Executive Yuan stated the plant could start operations if the referendum on halting construction was not held, assuming safety tests were passed first. Former DPP chairman Lin Yi-hsiung went on a hunger strike for two weeks to oppose continued construction, reflecting

2352-459: Was later obtained from GE for 97% of the changes. The temporary cancellation by the Government and other project management difficulties caused significant delays, pushing the price tag of the plant to more than US$ 7.5 billion by 2009. As of 2014, the total price tag was close to US$ 10 billion, or NT$ 300 billion. Environmental groups called for a national referendum in April 2011, following

2401-419: Was submitted on October 16, 1997, and after the license was granted on March 17, 1999, construction of the plant began in 1999 and was expected to be completed in 2004. The preceding four ABWR units in Japan were completed in four to five years each. Taipower, however, did not award the contract to a single architect/engineer, but hired General Electric to build the reactors, Mitsubishi Heavy Industries to supply

#882117