The Rio Vista Bridge (officially the Helen Madere Memorial Bridge ) is a continuous truss span with a vertical-lift bridge in the middle which carries California State Route 12 across the Sacramento River at Rio Vista, California . The present bridge was completed in 1960 and is one of several moveable bridges spanning rivers in the Sacramento–San Joaquin River Delta . It is named after Helen Madere, who served as vice-mayor of Rio Vista. As of 2013 the bridge carries approximately 21,000 cars per day.
36-561: The original bridge spanning the Sacramento River was built in 1918 and opened in January 1919 at a cost of US$ 260,000 (equivalent to $ 4,570,000 in 2023). From west to east, the 1919 bridge consisted of a 70-foot (21 m) concrete tied arch , the 343-foot (105 m) Strauss double-leaf bascule , three 120-foot (37 m) concrete tied arches and 1,670-foot (510 m) timber A-frame trestle spans. The 1919 bridge
72-426: A chord tying the arch ends rather than by the ground or the bridge foundations. This strengthened chord may be the deck structure itself or consist of separate, independent tie-rods. Thrusts downwards on a tied-arch bridge deck are translated, as tension, by vertical ties between the deck and the arch, tending to flatten it and thereby to push its tips outward into the abutments, like for other arch bridges. However, in
108-474: A cost of US$ 730,000 (equivalent to $ 12,350,000 in 2023), and traffic was diverted from the timber trestles onto the steel trusses with a crossover. The US Corps of Engineers authorized replacement of the remaining portion of the bridge on 2 February 1950, with contracts awarded for US$ 960,000 (equivalent to $ 9,890,000 in 2023) to Lord and Bishop for the substructure and US$ 2,410,000 (equivalent to $ 24,820,000 in 2023) to Judson Pacific Murphy for
144-658: A permanent 370-short-ton (340 t) replacement span (which included a 36-foot (11 m) cantilevered section to replace damage in the adjacent truss span) in June 1967 and removed both the wreckage from the original bridge and the temporary span at the same time. In 1998, the Rio Vista Bridge was officially designated the Helen Madere Memorial Bridge after Helen Madere, a former vice-mayor of Rio Vista who served as that city's representative to
180-529: A single span, two tied-arches are placed in parallel alongside the deck, so the deck lies in between the arches. Axial tied-arch or single tied-arch bridges have at most one tied-arch per span that is usually centered in the middle of the bridge deck. An example for this is Hoge Brug in Maastricht. Since it has hinged hangers it might also classify as a Nielsen bridge who held a patent on tied-arch bridges with hinged hangers from 1926. Some designs tilt
216-769: A tied-arch or bowstring bridge, these movements are restrained not by the abutments but by the strengthened chord, which ties these tips together, taking the thrusts as tension, rather like the string of a bow that is being flattened. Therefore, the design is also called a bowstring-arch or bowstring-girder bridge . The elimination of horizontal forces at the abutments allows tied-arch bridges to be constructed with less robust foundations; thus they can be situated atop elevated piers or in areas of unstable soil . In addition, since they do not depend on horizontal compression forces for their integrity, tied-arch bridges can be prefabricated offsite, and subsequently floated, hauled or lifted into place. Notable bridges of this type include
252-536: A tied-arch; however, the bowstring truss behaves as truss , not an arch . The visual distinction is a tied-arch bridge will not have substantial diagonal members between the vertical members. In a 1978 advisory issued by the Federal Highway Administration (FHWA), the FHWA noted that tied-arch bridges are susceptible to problems caused by poor welds at the connection between the arch rib and
288-414: Is provided by a 167-horsepower (125 kW) diesel generator set. The main lift span can be raised to its full height in less than 90 seconds, although the total operating cycle can disrupt road traffic for 8–25 minutes. Clearance under the raised lift is 135 feet (41 m) to the highest anticipated water level, and the navigation channel is 270 feet (82 m) wide between the timber fenders protecting
324-655: Is the Fremont Bridge in Portland, Oregon which is the second-longest tied-arch bridge in the world and also classifies as a through arch bridge . The Chaotianmen Bridge in Chongqing is a tied-arch, through arch and a truss arch bridge . Contrarily, the Hart Bridge uses a cantilevered trussed arch, it is self-anchored , but its arch is non-tied. In particular the bridge deck is suspended, but does not tie
360-604: The Fremont Bridge in Portland, Oregon and the first "computer-designed" bridge of this type, the Fort Pitt Bridge in Pittsburgh, Pennsylvania . Both the tied-arch bridge and the self-anchored suspension bridge place only vertical loads on the anchorage, and so are suitable where large horizontal forces are difficult to anchor. Some tied-arch bridges only tie a segment of the main arch directly and prolong
396-504: The Solano Transportation Authority . The legislative act also cited her instrumental role in improving driver safety on California State Route 12. The bridge was raised to allow marine traffic to pass on July 7, 2012, and became stuck in that position for several hours due to a mechanical failure. On August 9, 2018, the bridge again became stuck open for ten hours, until work crews were able to manually lower
SECTION 10
#1732783484222432-492: The 1945 steel truss spans was built to avoid interference with substructure construction, and after the new lift portion was built, another crossover was built to reroute road traffic from the 1919 bascule to the 1960 bridge. Once the new bridge was complete, removal of the old structure was completed by July 1960. On 15 January 1967, the Italian freighter Ilice missed the raised draw while underway in heavy fog and crashed into
468-468: The 2012 study concluded a fixed high-level bridge or a tunnel are the preferred alternatives to allow passage of both ship and road traffic, calling it "the single most important investment that can be made to improve SR-12." The City of Rio Vista dropped its support for the north (Airport Road) alternative alignment in 2012. Caltrans is undertaking a two-part preservation project for the bridge. The first part of this work, which involves cleaning and painting
504-689: The City of Rio Vista, the Solano Transportation Authority, and Caltrans have all studied potential replacements for the Helen Madere Bridge. Two goals were first, to remove the drawbridge or at least reduce the necessity of raising the bridge and second, to expand the existing roadway from two lanes to four. The first study was performed from 1991 through 1994 at the request of the City of Rio Vista, which proposed eight alternatives for crossings at, north of and south of
540-475: The Rio Vista bridge won an American Institute of Steel Construction class IV (movable bridges) prize bridge award in 1960. The main lift span weighs 750 short tons (680 t), with an equal amount in counterweights, so the lift mechanism operates 1,500 short tons (1,400 t) using two 30-horsepower (22 kW) electric motors, one in each tower. In the event of electrical failure, backup electrical power
576-692: The arch ends. Tied arch bridges may consist of successively lined up tied arches in places where a single span is not sufficient. An example for this is the Godavari Arch Bridge in Rajahmundry, India. It has four separate supports on each pier and carries the South Central Railway Line of India. It was designed for 250 km/h rail services. Like for multi-span continuous beam bridges the tying chord continually spans over all piers. The arches feet coincide (fuse) at
612-413: The arches outward or inward with respect to the axis running along the bridge deck. In analogy to twin bridges , two tied arch bridges erected side by side to increase traffic capacity, but structurally independent, may be referred to by tied arch twin bridges . Each in return may use a single- or multi-span, discrete or continuous tied-arch design. A bowstring truss bridge is similar in appearance to
648-413: The arches. Contrarily each abutment on the riverbanks supports a single arch end only, in the middle of the deck. The tying chord(s) consist of a composite deck structure. Four post tensioned coil steel cables, two to each side of the walking deck, are locked in place by orthogonally run steel beams every 7.5 meters. The hangers are joined to each of these beams between each cable pair. Since the beams extend
684-418: The bridge just east of the draw, destroying an entire 144-foot (44 m), 400-short-ton (360 t)) truss span. No one was injured in the crash, although two youths who were stopped on the bridge while the freighter passed were tossed into the river and were subsequently rescued. Once Ilice was freed from the wreckage, she proceeded upriver to Sacramento to take on its scheduled load of rice. The remnants of
720-625: The bridge overlapped the planning process for the Sacramento Deep Water Ship Channel . When plans for the Deep Water Channel were complete, the eastern truss section of the new bridge were already complete, and the Channel rerouted ship traffic from its then-current course near the western bank (through the 1919 bascule) to a point 575 feet (175 m) east. A new crossover from the 1919 bascule bridge to
756-463: The bridge piers. A good visual indication are shared supports at the piers. Dynamic loads are distributed between spans. This type may be combined with the shouldered tied-arch design discussed above. An example for this is Dashengguan Bridge in Nanjing, China. Its two main arches are shouldered by short auxiliary arches. It is both, a (rigid) tied-arch and a cantilevered trussed arch design. Because
SECTION 20
#1732783484222792-429: The bridge, is expected to complete in winter 2020 at a cost of $ 37.1 million. After the bridge has been repainted, the mechanical and electrical systems will be upgraded, starting in spring 2022, at an anticipated cost to range between $ 11.9 and $ 19.2 million. Tied-arch bridge A tied-arch bridge is an arch bridge in which the outward-directed horizontal forces of the arch(es) are borne as tension by
828-404: The construction site, where they were raised into place by a 100-short-ton (91 t) capacity barge crane. The sheaves at the top of each tower were lifted in place during high tides in order to reach the necessary height. The 1960 superstructure replacing the 1919 bascule bridge includes the four truss spans west of the main lift span and one truss span east of the main lift. The construction of
864-413: The current SR-12 alignment. Fixed high-level bridges of various designs would require longer approaches to accommodate the required height with reasonable road grades, and resulted in the proposed alternative crossings north and south of the existing SR-12 alignment. Both a mid-level moveable bridge (with approximately 50 feet (15 m) of clearance with the draw down) and tunnel crossings were proposed for
900-415: The destroyed span were cut free from the bridge and dropped into the water. A temporary repair consisting of a steel trestle and two 72-foot (22 m) steel girders was erected after three weeks, with a ferry carrying traffic across the river while the temporary span was erected. The Marine Boss crane barge, built for the heavy girder lifts during the construction of the 1967 San Mateo Bridge , erected
936-517: The draw. Marine traffic has the right-of-way, and the nearest detour around the bridge requires an additional 80 miles (130 km) of driving. It was unable to be raised again until August 16, blocking marine shipments of rice and cement to the Port of West Sacramento. Caltrans made plans to manually raise and test the draw section after determining the motor gear box had failed, but warned motorists that repairs would take up to thirty days to complete, as
972-411: The existing alignment, with the mid-level bridge being named the preferred alternative in 1992. In 2010, the Solano Transportation Authority expanded on the 1991–94 studies by carefully considering a subset of the proposed alternative crossings, with the tunnel at the existing SR-12 alignment now becoming the preferred alternative. Rio Vista businesses along the existing SR-12 alignment urged no change to
1008-631: The gearbox would need to be rebuilt in Alabama. The bridge was raised by hand, closing to road traffic overnight every few days to allow marine traffic to pass. Repairs to the bridge were completed on September 14. The bridge opened 200 times for ship traffic during peak months in 2004 (nearly seven times per day); peak queues reached 200 vehicles extending 0.75 miles (1.21 km) and caused travel delays of up to 30 minutes. With ship traffic projected to increase to require as many as 400 openings by 2035, and traffic on State Route 12 also projected to increase,
1044-428: The route, worried that moving SR-12 traffic could result in business closures. One of the proposed measures to raise funds would have imposed a toll on the existing bridge, and was met with similar resistance. Caltrans performed a 2012 study for the entire SR-12 corridor, which concluded the cost of a replacement high-level bridge would be close to US$ 1,000,000,000 (equivalent to $ 1,327,100,000 in 2023). Ultimately,
1080-467: The strengthened chord to tie to the top ends of auxiliary (half-)arches . The latter usually support the deck from below and join their bottom feet to those of the main arch(es). The supporting piers at this point may be slender, because the outward-directed horizontal forces of main and auxiliary arch ends counterbalance. The whole structure is self-anchored . Like the simple case it exclusively places vertical loads on all ground-bound supports. An example
1116-496: The superstructure, with an additional US$ 124,000 (equivalent to $ 1,280,000 in 2023) contract to Pacific Murphy for the concrete slab approach spans. The substructure was constructed from 4 April 1957 through 30 October 1958, and consists of the concrete piers and pilings. The first part of the superstructure erected was the east tower, which began on 4 December 1958. The superstructure was assembled in prefabricated segments at Pacific Murphy's Richmond yard and barged upstream to
Rio Vista Bridge - Misplaced Pages Continue
1152-444: The tie girders, and at the connection between the arch and vertical ties. In addition, problems with electroslag welds , while not isolated to tied-arch bridges, resulted in costly, time-consuming and inconveniencing repairs. The structure as a whole was described as nonredundant : failure of either of the two tie girders would result in failure of the entire structure. Weeks 533 Too Many Requests If you report this error to
1188-417: The tower piers. With the lift down, vertical clearance is only 18 feet (5.5 m). Less than thirty years after being completed, the eastern timber trestles of the 1919 bridge were in poor condition, and construction of replacement steel trusses began in 1943. Construction of the 1,300-foot (400 m) eastern steel truss section, consisting of seven 180-foot (55 m) truss spans, was completed in 1945 at
1224-477: The traffic runs through the structural envelope, it is also a through arch bridge. Guandu Bridge in New Taipei, Taiwan is a non-trussed example with three main arches augmented by two auxiliary arch segments at the bridge portals. The Infinity Bridge uses two arches of different height and span length that both bifurcate before their apex. Above its single, middle-displaced river pier the deck lies between
1260-474: The width of the post-tensioned concrete deck, the tensing cable pairs remain visible. A close-up of the river pier shows that the structural dead load is tied per span: The larger arch span uses thicker tensing cables and the reflex segments are not suspended from, but supported by steel beams, essentially completing the arches at the river pier. However, for dynamic and non-uniform loads the visually defining arch continuations must not be neglected. Usually, for
1296-419: Was replaced during seventeen years of piecewise construction. The finished 1943–1960 bridge consists of thirteen steel Warren truss spans (with one of those being the 306-foot (93 m) vertical-lift chorded Warren truss main span) carried on twelve piers. Total bridge length is 2,890 feet (880 m), including 441 feet (134 m) of concrete slab approach spans on the west end of the bridge. Upon completion,
#221778