A tidal barrage is a dam -like structure used to capture the energy from masses of water moving in and out of a bay or river due to tidal forces.

#433566

36-602: The Mersey Barrage is a proposed scheme for building a tidal barrage across the Mersey Estuary , between Liverpool and the Wirral Peninsula , England. The River Mersey is considered to be a suitable source of marine renewable energy in the United Kingdom, because of its strong current and tidal range of up to 10 m (33 ft), the second highest in the United Kingdom. A Department of

72-457: A barrage across a bay or river that is subject to tidal flow. Turbines installed in the barrage wall generate power as water flows in and out of the estuary basin, bay, or river. These systems are similar to a hydro dam that produces static head or pressure head (a height of water pressure). When the water level outside of the basin or lagoon changes relative to the water level inside, the turbines are able to produce power. The basic elements of

108-503: A barrage are caissons , embankments, sluices , turbines , and ship locks . Sluices, turbines, and ship locks are housed in caissons (very large concrete blocks). Embankments seal a basin where it is not sealed by caissons. The sluice gates applicable to tidal power are the flap gate, vertical rising gate, radial gate, and rising sector. Only a few such plants exist. The first was the Rance Tidal Power Station , on

144-546: A barrage as part of his 2017 election campaign. The 2018 study indicated that economics were more favourable than previously, but still fell short by 20%. In February 2020, following a year-long feasibility study, a tidal power proposal for the River Mersey was granted £2.5   million in funding to further develop the plan. In December 2022, the Liverpool City Region mayor announced an agreement between

180-487: A barrage is dependent on the volume of water. The potential energy contained in a volume of water is: where: The factor half is due to the fact, that as the basin flows empty through the turbines, the hydraulic head over the dam reduces. The maximum head is only available at the moment of low water, assuming the high water level is still present in the basin. Assumptions: Mass of the sea water = volume of sea water × density of sea water Potential energy content of

216-587: A small fraction of fish only. Research in sonic guidance of fish is ongoing. The Open-Centre turbine reduces this problem allowing fish to pass through the open centre of the turbine. Recently a run of the river type turbine has been developed in France. This is a very large slow rotating Kaplan-type turbine mounted on an angle. Testing for fish mortality has indicated fish mortality figures to be less than 5%. This concept also seems very suitable for adaption to marine current/tidal turbines. The energy available from

252-439: A tidal barrage allows water to flow into a bay or river during high tide , and releases the water during low tide . This is done by measuring the tidal flow and controlling the sluice gates at key times of the tidal cycle. Turbines are placed at these sluices to capture the energy as the water flows in and out. Tidal barrages are among the oldest methods of tidal power generation, with tide mills being developed as early as

288-478: A very low running cost. As a result, a tidal power scheme may not produce returns for many years, and investors may be reluctant to participate in such projects. It reportedly took around 20 years to recoup the $ 100m costs of building the Rance Tidal Power Plant. As of 2024 , it has been operating for 60 years with the cost of tidal power lower than nuclear or solar, so it has more than paid back

324-403: Is in effect a dam being placed across estuarine systems. As people have become more aware of environmental issues, they have opposed barrages because of the adverse effects associated with changing a large ecosystem that is habitat for many varieties of species. The basin is filled through the sluices until high tide. Then the sluice gates are closed. (At this stage there may be "Pumping" to raise

360-549: The Cheshire Wildlife Trust are monitoring the progress of the proposals, and the potential impact on existing habitat and wildlife within the estuary. Following a similar scheme with the Rance Tidal Power Station in Brittany , some marine fauna initially suffered, but a new equilibrium was achieved after ten   years. Tidal barrage Instead of damming water on one side like a conventional dam ,

396-971: The Rance river , in France, which has been operating since 1966 and generates 240MW. A larger 254MW plant began operation at Sihwa Lake , Korea, in 2011. Smaller plants include the Annapolis Royal Generating Station on the Bay of Fundy , and another across a tiny inlet in Kislaya Guba , Russia . A number of proposals have been considered for a barrage across the River Severn , from Brean Down in England to Lavernock Point near Cardiff in Wales . Barrage systems are dependent on high civil infrastructure costs associated with what

SECTION 10

#1732772559434

432-703: The City Region and K-water of South Korea , who built and operates the Sihwa Lake Tidal Power Station , to carry out "reciprocal visits and information sharing". The Mersey Tidal Power Project was launched as "a scoping project" in March 2024. The projected power output is not stated but it is suggested that the scheme will be able to "power a million homes". The tidal barrage plan was put to public consultation in September 2024, starting

468-558: The Environment and UKAEA report in 1984 identified a site between New Brighton and Brocklebank Dock for a Mersey barrage. A 2006 study by Peel Holdings and the North West Development Agency identified the River Mersey as having considerable potential for tidal power. A pilot project, using a water wheel to harness tidal power, was considered at Bootle docks. At the same time, a tidal barrage plan

504-407: The abandoned space, which caused a shift in diversity. Also as a result of the construction, sandbanks disappeared, the beach of St. Servan was badly damaged and high-speed currents have developed near sluices, which are water channels controlled by gates. Turbidity (the amount of matter in suspension in the water) decreases as a result of smaller volume of water being exchanged between the basin and

540-562: The available power varies with the square of the tidal range, a barrage is best placed in a location with very high-amplitude tides. Suitable locations are found in Russia, the US, Canada, Australia, Korea, and the UK. Amplitudes of up to 17 m (56 ft) occur for example in the Bay of Fundy , where tidal resonance amplifies the tidal range. Tidal barrage power schemes have a high capital cost and

576-464: The construction costs. Governments may be able to finance tidal barrage power, but many are unwilling to do so also due to the lag time before investment return and the high irreversible commitment. For example, the energy policy of the United Kingdom recognizes the role of tidal energy and expresses the need for local councils to understand the broader national goals of renewable energy in approving tidal projects. The UK government itself appreciates

612-484: The cost of the extra length of barrage. There are some favourable geographies, however, which are well suited to this type of scheme. Tidal pools are independent enclosing barrages built on high level tidal estuary land that trap the high water and release it to generate power, single pool, around 3.3 W/m . Two lagoons operating at different time intervals can guarantee continuous power output, around 4.5 W/m . Enhanced pumped storage tidal series of lagoons raises

648-414: The dual basin type. With two basins, one is filled at high tide and the other is emptied at low tide. Turbines are placed between the basins. Two-basin schemes offer advantages over normal schemes in that generation time can be adjusted with high flexibility and it is also possible to generate almost continuously. In normal estuarine situations, however, two-basin schemes are very expensive to construct due to

684-498: The ecosystem. "Tidal Lagoons" do not suffer from this problem. Estuaries often have high volume of sediments moving through them, from the rivers to the sea. The introduction of a barrage into an estuary may result in sediment accumulation within the barrage, affecting the ecosystem and also the operation of the barrage. Fish may move through sluices safely, but when these are closed, fish will seek out turbines and attempt to swim through them. Also, some fish will be unable to escape

720-609: The environment. The main environmental impact of turbines is their impact on fish. If the turbines are moving slowly enough, such as low velocities of 25–50 rpm, fish kill is minimalized and silt and other nutrients are able to flow through the structures. For example, a 20 kW tidal turbine prototype built in the St. Lawrence Seaway in 1983 reported no fish kills. Tidal fences block off channels, which makes it difficult for fish and wildlife to migrate through those channels. In order to reduce fish kill, fences could be engineered so that

756-516: The formal planning process. A Mersey barrage has been predicted to be capable of producing between 1.0 and 1.5   terawatt-hours of electricity per year (0.11 to 0.17 GW), which is equivalent to two-thirds of Liverpool 's 2017 electricity requirement. One design has proposed that cross-river public transport infrastructure is included in the construction. The estuary is designated as an internationally important protected area, for wading birds, ducks and fish. The Lancashire Wildlife Trust and

SECTION 20

#1732772559434

792-408: The grid to increase the water level in the basin at high tide (for ebb generation). Much of this energy is returned during generation, because power output is strongly related to the head. If water is raised 2 ft (61 cm) by pumping on a high tide of 10 ft (3 m), this will have been raised by 12 ft (3.7 m) at low tide. Another form of energy barrage configuration is that of

828-425: The level further). The turbine gates are kept closed until the sea level falls, in order to create sufficient head across the barrage. The gates are opened so that the turbines generate until the head is again low. Then the sluices are opened, turbines disconnected and the basin is filled again. The cycle repeats with the tides. Ebb generation (also known as outflow generation) takes its name because generation occurs as

864-456: The mouths of estuaries pose similar environmental threats as large dams. The construction of large tidal plants alters the flow of saltwater in and out of estuaries, which changes the hydrology and salinity and could possibly harm marine mammals that use the estuaries as their habitat. The La Rance plant, off the Brittany coast of northern France, was the first and largest tidal barrage plant in

900-454: The sea. This lets light from the Sun penetrate the water further, improving conditions for the phytoplankton . The changes propagate up the food chain , causing a general change in the ecosystem . Tidal fences and turbines, if constructed properly, pose less environmental threats than tidal barrages. Tidal fences and turbines, like tidal stream generators , rely entirely on the kinetic motion of

936-645: The sixth century. In the 1960s the 1.7 megawatt Kislaya Guba Tidal Power Station in Kislaya Guba , Russia , was built. Around the same time, the 240 MW la Rance Tidal Power Station was built in Brittany , France, opened in November 1966. La Rance was the largest tidal barrage in world for 45 years, until the 254 MW Sihwa Lake Tidal Power Station was commissioned in South Korea in 2011. However, there are few other examples worldwide. The barrage method of extracting tidal energy involves building

972-426: The spaces between the caisson wall and the rotor foil are large enough to allow fish to pass through. Larger marine mammals such as seals or dolphins can be protected from the turbines by fences or a sonar sensor auto-braking system that automatically shuts the turbines down when marine mammals are detected. As a result of less water exchange with the sea, the average salinity inside the basin decreases, also affecting

1008-777: The technical viability and siting options available, but has failed to provide meaningful incentives to move these goals forward. Kislaya Guba Kislaya Guba (meaning sour bay in Russian ) is a fjord on the Kola Peninsula near Murmansk , Russia . The fjord is connected to the Barents Sea to the north and is primarily known as the site of the experimental tidal power project, Kislaya Guba Tidal Power Station . 69°22′34″N 33°04′33″E  /  69.37611°N 33.07583°E  / 69.37611; 33.07583 This Murmansk Oblast location article

1044-409: The tidal currents and do not use dams or barrages to block channels or estuarine mouths. Unlike barrages, tidal fences do not interrupt fish migration or alter hydrology , thus these options offer energy generating capacity without dire environmental impacts. Tidal fences and turbines can have varying environmental impacts depending on whether or not fences and turbines are constructed with regard to

1080-410: The tide changes tidal direction. The basin is filled through the turbines, which generate at tide flood. This is generally much less efficient than ebb generation, because the volume contained in the upper half of the basin (which is where ebb generation operates) is greater than the volume of the lower half (filled first during flood generation). Therefore, the available level difference – important for

1116-400: The turbine power produced – between the basin side and the sea side of the barrage, reduces more quickly than it would in ebb generation. Rivers flowing into the basin may further reduce the energy potential, instead of enhancing it as in ebb generation. Of course this is not a problem with the "lagoon" model, without river inflow.. Turbines are able to be powered in reverse by excess energy in

Mersey Barrage - Misplaced Pages Continue

1152-500: The water in the basin at high tide = ½ × area × density × gravitational acceleration × tidal range squared Now we have 2 high tides and 2 low tides every day. At low tide the potential energy is zero. Therefore, the total energy potential per day = Energy for a single high tide × 2 Therefore, the mean power generation potential = Energy generation potential / time in 1 day Assuming the power conversion efficiency to be 30%: The daily-average power generated = 104 MW * 30% Because

1188-559: The water level higher than the high tide, and uses intermittent renewables for pumping, around 7.5 W/m . i.e. 10 × 10 km delivers 750 MW constant output 24/7. These independent barrages do not block the flow of the river. The placement of a barrage into an estuary has a considerable effect on the water inside the basin and on the ecosystem. Many governments have been reluctant in recent times to grant approval for tidal barrages. Through research conducted on tidal plants, it has been found that tidal barrages constructed at

1224-434: The water speed near a turbine and will be sucked through. Even with the most fish-friendly turbine design, fish mortality per pass is approximately 15% (from pressure drop, contact with blades, cavitation , etc.). Alternative passage technologies ( fish ladders , fish lifts, fish escalators etc.) have so far failed to solve this problem for tidal barrages, either offering extremely expensive solutions, or ones which are used by

1260-528: The world. It is also the only site where a full-scale evaluation of the ecological impact of a tidal power system, operating for 20 years, has been made. French researchers found that the isolation of the estuary during the construction phases of the tidal barrage was detrimental to flora and fauna, however; after ten years, there has been a "variable degree of biological adjustment to the new environmental conditions." Some species lost their habitat due to La Rance's construction, but other species colonized

1296-573: Was evaluated, capable of generating 700   MW. A barrage scheme was abandoned in 2011, following a study by Peel Energy and the North West Development Agency . This proposal involved constructing a barrage between Dingle on the Liverpool bank and New Ferry on the Wirral bank. Although the study provided valuable insight, the preferred scheme was abandoned due to the expected lack of medium-term profitability. Steve Rotheram revived plans for