Misplaced Pages

Kapiti Line

Article snapshot taken from Wikipedia with creative commons attribution-sharealike license. Give it a read and then ask your questions in the chat. We can research this topic together.
#617382

95-425: Metlink's Kapiti Line is the electrified southern portion of the North Island Main Trunk railway between New Zealand 's capital city, Wellington , and Waikanae on the Kāpiti Coast , operated by Transdev Wellington on behalf of Greater Wellington Regional Council . Trains run frequently every day, with stops at 16 stations. Until 20 February 2011 it was known as the Paraparaumu Line. The Kapiti Line

190-402: A (nearly) continuous conductor running along the track that usually takes one of two forms: an overhead line , suspended from poles or towers along the track or from structure or tunnel ceilings, or a third rail mounted at track level and contacted by a sliding " pickup shoe ". Both overhead wire and third-rail systems usually use the running rails as the return conductor, but some systems use

285-573: A higher total efficiency. Electricity for electric rail systems can also come from renewable energy , nuclear power , or other low-carbon sources, which do not emit pollution or emissions. Electric locomotives may easily be constructed with greater power output than most diesel locomotives. For passenger operation it is possible to provide enough power with diesel engines (see e.g. ' ICE TD ') but, at higher speeds, this proves costly and impractical. Therefore, almost all high speed trains are electric. The high power of electric locomotives also gives them

380-467: A historical concern for double-stack rail transport regarding clearances with overhead lines but it is no longer universally true as of 2022 , with both Indian Railways and China Railway regularly operating electric double-stack cargo trains under overhead lines. Railway electrification has constantly increased in the past decades, and as of 2022, electrified tracks account for nearly one-third of total tracks globally. Railway electrification

475-497: A new freight loop at Plimmerton or an improved loop at Porirua (2021/2022; $ 11.09 million); and Plimmerton will get a high capacity train turn-back facility as a terminal station (2021; $ 12.8 million). Power supply upgrades will allow more long (8 car) trains (2020; $ 10.1 million). The single-track section above the coast between Pukerua Bay and Paekakariki (known as the North–South Junction ) may also be double tracked through

570-537: A number of European countries, India, Saudi Arabia, eastern Japan, countries that used to be part of the Soviet Union, on high-speed lines in much of Western Europe (including countries that still run conventional railways under DC but not in countries using 16.7   Hz, see above). Most systems like this operate at 25   kV, although 12.5   kV sections exist in the United States, and 20   kV

665-653: A peat swamp, remained single track. Extension of double track from Mackays Crossing to a junction south of the Waikanae River bridge was completed in February 2011 to coincide with the extension of electrification to Waikanae. The North–South Junction section north of the South Junction (north of the former Muri Station, at the top of the Pukerua Saddle) and with five short single-track tunnels to

760-457: A power grid that is delivered to a locomotive, and within the locomotive, transformed and rectified to a lower DC voltage in preparation for use by traction motors. These motors may either be DC motors which directly use the DC or they may be three-phase AC motors which require further conversion of the DC to variable frequency three-phase AC (using power electronics). Thus both systems are faced with

855-498: A relative lack of flexibility (since electric trains need third rails or overhead wires), and a vulnerability to power interruptions. Electro-diesel locomotives and electro-diesel multiple units mitigate these problems somewhat as they are capable of running on diesel power during an outage or on non-electrified routes. Different regions may use different supply voltages and frequencies, complicating through service and requiring greater complexity of locomotive power. There used to be

950-481: A separate fourth rail for this purpose. In comparison to the principal alternative, the diesel engine , electric railways offer substantially better energy efficiency , lower emissions , and lower operating costs. Electric locomotives are also usually quieter, more powerful, and more responsive and reliable than diesel. They have no local emissions, an important advantage in tunnels and urban areas. Some electric traction systems provide regenerative braking that turns

1045-400: A single long double track tunnel (replacing five short tunnels) or replaced by a less steep deviation; although the proposal in 2007 was to daylight only the northernmost (No. 7) tunnel which is through rock, and have double track north from there. Further extension of the electrification 15 kilometres (9.3 mi) north from Waikanae to Ōtaki remains a possibility. The two over bridges of

SECTION 10

#1732802246618

1140-418: A third rail. The key advantage of the four-rail system is that neither running rail carries any current. This scheme was introduced because of the problems of return currents, intended to be carried by the earthed (grounded) running rail, flowing through the iron tunnel linings instead. This can cause electrolytic damage and even arcing if the tunnel segments are not electrically bonded together. The problem

1235-411: Is derived by using resistors which ensures that stray earth currents are kept to manageable levels. Power-only rails can be mounted on strongly insulating ceramic chairs to minimise current leak, but this is not possible for running rails, which have to be seated on stronger metal chairs to carry the weight of trains. However, elastomeric rubber pads placed between the rails and chairs can now solve part of

1330-451: Is effected by one contact shoe each that slide on top of each one of the running rails . This and all other rubber-tyred metros that have a 1,435 mm ( 4 ft  8 + 1 ⁄ 2  in ) standard gauge track between the roll ways operate in the same manner. Railways and electrical utilities use AC as opposed to DC for the same reason: to use transformers , which require AC, to produce higher voltages. The higher

1425-526: Is electrified, companies often find that they need to continue use of diesel trains even if sections are electrified. The increasing demand for container traffic, which is more efficient when utilizing the double-stack car , also has network effect issues with existing electrifications due to insufficient clearance of overhead electrical lines for these trains, but electrification can be built or modified to have sufficient clearance, at additional cost. A problem specifically related to electrified lines are gaps in

1520-486: Is limited and losses are significantly higher. However, the higher voltages used in many AC electrification systems reduce transmission losses over longer distances, allowing for fewer substations or more powerful locomotives to be used. Also, the energy used to blow air to cool transformers, power electronics (including rectifiers), and other conversion hardware must be accounted for. Standard AC electrification systems use much higher voltages than standard DC systems. One of

1615-513: Is located at Queen Elizabeth Park on the lower North Island of New Zealand , near the overbridge at McKay's Crossing between Paekākāriki and Paraparaumu . Trams have been in operation on a line through the park since 1965. The museum is 45 km (28 mi) from Wellington . The Trams owned by the museum date back to the 1920s and 1930s and were used on the Wellington tramway system between 1878 and 1964, transporting commuters around

1710-778: Is no longer exactly one-third of the grid frequency. This solved overheating problems with the rotary converters used to generate some of this power from the grid supply. In the US , the New York, New Haven, and Hartford Railroad , the Pennsylvania Railroad and the Philadelphia and Reading Railway adopted 11   kV 25   Hz single-phase AC. Parts of the original electrified network still operate at 25   Hz, with voltage boosted to 12   kV, while others were converted to 12.5 or 25   kV 60   Hz. In

1805-447: Is sufficient traffic, the reduced track and especially the lower engine maintenance and running costs exceed the costs of this maintenance significantly. Newly electrified lines often show a "sparks effect", whereby electrification in passenger rail systems leads to significant jumps in patronage / revenue. The reasons may include electric trains being seen as more modern and attractive to ride, faster, quieter and smoother service, and

1900-410: Is that the power-wasting resistors used in DC locomotives for speed control were not needed in an AC locomotive: multiple taps on the transformer can supply a range of voltages. Separate low-voltage transformer windings supply lighting and the motors driving auxiliary machinery. More recently, the development of very high power semiconductors has caused the classic DC motor to be largely replaced with

1995-894: Is the countrywide system. 3   kV DC is used in Belgium, Italy, Spain, Poland, Slovakia, Slovenia, South Africa, Chile, the northern portion of the Czech Republic, the former republics of the Soviet Union , and in the Netherlands on a few kilometers between Maastricht and Belgium. It was formerly used by the Milwaukee Road from Harlowton, Montana , to Seattle, across the Continental Divide and including extensive branch and loop lines in Montana, and by

SECTION 20

#1732802246618

2090-580: Is the development of powering trains and locomotives using electricity instead of diesel or steam power . The history of railway electrification dates back to the late 19th century when the first electric tramways were introduced in cities like Berlin , London , and New York City . In 1881, the first permanent railway electrification in the world was the Gross-Lichterfelde Tramway in Berlin , Germany. Overhead line electrification

2185-420: Is typically generated in large and relatively efficient generating stations , transmitted to the railway network and distributed to the trains. Some electric railways have their own dedicated generating stations and transmission lines , but most purchase power from an electric utility . The railway usually provides its own distribution lines, switches, and transformers . Power is supplied to moving trains with

2280-838: Is used on some narrow-gauge lines in Japan. On "French system" HSLs, the overhead line and a "sleeper" feeder line each carry 25   kV in relation to the rails, but in opposite phase so they are at 50   kV from each other; autotransformers equalize the tension at regular intervals. Various railway electrification systems in the late nineteenth and twentieth centuries utilised three-phase , rather than single-phase electric power delivery due to ease of design of both power supply and locomotives. These systems could either use standard network frequency and three power cables, or reduced frequency, which allowed for return-phase line to be third rail, rather than an additional overhead wire. The majority of modern electrification systems take AC energy from

2375-656: The Delaware, Lackawanna and Western Railroad (now New Jersey Transit , converted to 25   kV   AC) in the United States, and the Kolkata suburban railway (Bardhaman Main Line) in India, before it was converted to 25   kV 50   Hz. DC voltages between 600   V and 750   V are used by most tramways and trolleybus networks, as well as some metro systems as the traction motors accept this voltage without

2470-711: The HSL-Zuid and Betuwelijn , and 3,000   V south of Maastricht . In Portugal, it is used in the Cascais Line and in Denmark on the suburban S-train system (1650   V DC). In the United Kingdom, 1,500   V   DC was used in 1954 for the Woodhead trans-Pennine route (now closed); the system used regenerative braking , allowing for transfer of energy between climbing and descending trains on

2565-701: The Innovia ART system. While part of the SkyTrain network, the Canada Line does not use this system and instead uses more traditional motors attached to the wheels and third-rail electrification. A few lines of the Paris Métro in France operate on a four-rail power system. The trains move on rubber tyres which roll on a pair of narrow roll ways made of steel and, in some places, of concrete . Since

2660-636: The Southern Railway serving Coulsdon North and Sutton railway station . The lines were electrified at 6.7   kV 25   Hz. It was announced in 1926 that all lines were to be converted to DC third rail and the last overhead-powered electric service ran in September 1929. AC power is used at 60   Hz in North America (excluding the aforementioned 25   Hz network), western Japan, South Korea and Taiwan; and at 50   Hz in

2755-461: The United States , the New York, New Haven and Hartford Railroad was one of the first major railways to be electrified. Railway electrification continued to expand throughout the 20th century, with technological improvements and the development of high-speed trains and commuters . Today, many countries have extensive electrified railway networks with 375 000  km of standard lines in

2850-465: The double tracking of the single track line between Mackays Crossing (between Paekakariki and Paraparaumu) as far as the rail underbridge and river bridge south of Waikanae. The $ 90 million project started in December 2008, and was completed in 2011, with the first commuter trains to Waikanae on 20 February. Completion of the project was delayed to 2011 to minimise commuter disruption by working in

2945-754: The EDs by 1981 and the EWs by 1988. From 2010 the introduction of the Matangi EMUs provided extra passenger capacity, and enabled the remaining DM/D EMUs to be withdrawn in 2012. A second batch of Matangi EMUs was then ordered to replace the EM/ET EMUs (rather than reconditioning them). A proposal to extend the electrification to Waikanae was approved by the Greater Wellington Regional Council on 8 May 2007. This project included

Kapiti Line - Misplaced Pages Continue

3040-651: The Kapiti Line from mid-2011. Paraparaumu and Waikanae stations were upgraded at a cost of more than $ 1 million each. Upgrading Waikanae station rather than moving it south of Elizabeth Street or providing a road underpass was criticised locally, as frequent closing of the Elizabeth Street level crossing south of the station (which connected to State Highway through the town) could increase traffic congestion in Waikanae. However this has since been alleviated by

3135-717: The Netherlands, New Zealand ( Wellington ), Singapore (on the North East MRT line ), the United States ( Chicago area on the Metra Electric district and the South Shore Line interurban line and Link light rail in Seattle , Washington). In Slovakia, there are two narrow-gauge lines in the High Tatras (one a cog railway ). In the Netherlands it is used on the main system, alongside 25   kV on

3230-564: The North Junction (at the northern portal of No 13 tunnel) before Paekakariki and along the coast below the steep and unstable Paekakariki Escarpment remains as a single track. From electrification in 1940 until the 1980s, the majority of commuter services on the line were operated by DM/D electric multiple units , with some carriage trains hauled by ED and EW electric locomotives , particularly at peak periods. ED and EW locomotives also hauled freight trains over this section until

3325-618: The North and South junctions and the need with "tablet" working to continuously man five stations with 3 or 4 tablet porters at each station (3 tablet porters at Porirua, Paremata and Pukerua Bay; and 4 tablet porters at Tawa Flat and Plimmerton); so requiring 19 men for traffic working instead of 8 with CTC (and also 11 staff houses). CTC working applied between Paekakariki and Plimmerton on 25 February, Plimmerton and Paremata on 30 June and Tawa to Porirua on 4 December 1940; giving full traffic control from Wellington to Paekakariki (as Wellington to Tawa

3420-610: The Peka Peka to Otaki expressway which opened in 2022 were designed to allow for a future double track line. A group known as "Save Kapiti" is actively campaigning for the extension. The Otaki Community Board also supports the extension of electrification. Provision has been made during road earthworks north of Waikanae for a future crossing loop between Peka Peka and Ōtaki . In 2012 the Greater Wellington Regional Council investigated extension of

3515-633: The Pukerua Bay saddle were later double-tracked. As part of the Plimmerton to Paekakariki duplication, a Westinghouse three-wire (two feed and one return) Centralised Train Control (CTC) system was installed in 1940; to control trains from Wellington. It was the first CTC system in New Zealand and the first outside the United States of America. This avoided the need for two new signal boxes at

3610-745: The UK, the London, Brighton and South Coast Railway pioneered overhead electrification of its suburban lines in London, London Bridge to Victoria being opened to traffic on 1   December 1909. Victoria to Crystal Palace via Balham and West Norwood opened in May 1911. Peckham Rye to West Norwood opened in June 1912. Further extensions were not made owing to the First World War. Two lines opened in 1925 under

3705-494: The ability to pull freight at higher speed over gradients; in mixed traffic conditions this increases capacity when the time between trains can be decreased. The higher power of electric locomotives and an electrification can also be a cheaper alternative to a new and less steep railway if train weights are to be increased on a system. On the other hand, electrification may not be suitable for lines with low frequency of traffic, because lower running cost of trains may be outweighed by

3800-516: The advantages of raising the voltage is that, to transmit certain level of power, lower current is necessary ( P = V × I ). Lowering the current reduces the ohmic losses and allows for less bulky, lighter overhead line equipment and more spacing between traction substations, while maintaining power capacity of the system. On the other hand, the higher voltage requires larger isolation gaps, requiring some elements of infrastructure to be larger. The standard-frequency AC system may introduce imbalance to

3895-665: The benefits. The detailed analysis for Raumati (which was a "viability benchmark" for other new stations) said that the modelled peak-hour patronage needed to be about 300 new passengers to justify a new station, and that most Raumati users would have switched from Paraparaumu Station. Network extensions beyond the current Metlink rail operation limits would be by "shuttles or non-electrified services" running to Wellington. Proposed infrastructure upgrades include sleeper replacement in tunnels, stabilisation of high-risk slopes and renewal of one bridge with timber elements. To cater for freight trains with more frequent passenger trains, there will be

Kapiti Line - Misplaced Pages Continue

3990-535: The body and chassis of a New Plymouth Birney tram which is on long-term loan to the Whanganui Tramways Trust, plus a small collection of diesel buses and trolley buses from Wellington and New Plymouth . The museum previously owned ex-Brisbane "Dreadnought" tram No.133 (gifted to the Whanganui Tramways Trust in 2017) and the body and chassis only of ex-Wanganui tram No.8, also gifted to the Whanganui Tramways Trust. From 1969 to 1974, Saul Goldsmith

4085-464: The catch points and two cross-overs of the siding were lifted, and Mackays Crossing became the point where the double-track section north ended. Further duplication was delayed in the 1940s but continued in the 1950s with the completion of the Tawa to Porirua section on 15 December 1957. Double track from Porirua to Mana was opened on 7 November 1960. Harbour reclamation allowed mostly straight track with

4180-553: The city. The museum maintains nearly 2 km (1.2 mi) of 4-foot (1219mm) gauge track in Queen Elizabeth Park, as well a fleet of trams from the closed Wellington system , several of which are currently operational with further examples in storage or undergoing restoration. The museum also owns an ex-Brisbane tram No.236 which is leased to the Tramway Historical Society of Christchurch,

4275-410: The distance they could transmit power. However, in the early 20th century, alternating current (AC) power systems were developed, which allowed for more efficient power transmission over longer distances. In the 1920s and 1930s, many countries worldwide began to electrify their railways. In Europe, Switzerland , Sweden , France , and Italy were among the early adopters of railway electrification. In

4370-566: The electrification with Matangi trains north of Waikanae to Ōtaki (estimated cost $ 30 million for the Ōtaki project) and north of Upper Hutt to a new station at Timberlea. In March 2014, the GWRC said that electrification to Ōtaki was estimated to cost $ 115 million to $ 135 million and was too costly for the number of new passengers it would attract (approximately 250 new passengers). Because the trip would take over an hour, new trains with toilets would be required. As an alternative to electrification, it

4465-448: The electrification. Electric vehicles, especially locomotives, lose power when traversing gaps in the supply, such as phase change gaps in overhead systems, and gaps over points in third rail systems. These become a nuisance if the locomotive stops with its collector on a dead gap, in which case there is no power to restart. This is less of a problem in trains consisting of two or more multiple units coupled together, since in that case if

4560-404: The end of funding. Most electrification systems use overhead wires, but third rail is an option up to 1,500   V. Third rail systems almost exclusively use DC distribution. The use of AC is usually not feasible due to the dimensions of a third rail being physically very large compared with the skin depth that AC penetrates to 0.3 millimetres or 0.012 inches in a steel rail. This effect makes

4655-591: The experiment was curtailed. In 1970 the Ural Electromechanical Institute of Railway Engineers carried out calculations for railway electrification at 12 kV DC , showing that the equivalent loss levels for a 25 kV AC system could be achieved with DC voltage between 11 and 16   kV. In the 1980s and 1990s 12 kV DC was being tested on the October Railway near Leningrad (now Petersburg ). The experiments ended in 1995 due to

4750-500: The fact that electrification often goes hand in hand with a general infrastructure and rolling stock overhaul / replacement, which leads to better service quality (in a way that theoretically could also be achieved by doing similar upgrades yet without electrification). Whatever the causes of the sparks effect, it is well established for numerous routes that have electrified over decades. This also applies when bus routes with diesel buses are replaced by trolleybuses. The overhead wires make

4845-489: The floors of the tunnels between Pukerua Bay and Paekakariki were lowered in 1967 and DA diesel locomotives could be used into Wellington. In 1948 the traffic over the 24 mile (38.5 km) Wellington to Paekakariki section averaged 30 passenger trains, 18 goods trains and 13 light engines (ED class) daily, with 67 daily crossings; opinion was that train delays were less frequent and of shorter duration with CTC than with Tyers Tablet control in 1937. The average tons per train

SECTION 50

#1732802246618

4940-1012: The general power grid. This is especially useful in mountainous areas where heavily loaded trains must descend long grades. Central station electricity can often be generated with higher efficiency than a mobile engine/generator. While the efficiency of power plant generation and diesel locomotive generation are roughly the same in the nominal regime, diesel motors decrease in efficiency in non-nominal regimes at low power while if an electric power plant needs to generate less power it will shut down its least efficient generators, thereby increasing efficiency. The electric train can save energy (as compared to diesel) by regenerative braking and by not needing to consume energy by idling as diesel locomotives do when stopped or coasting. However, electric rolling stock may run cooling blowers when stopped or coasting, thus consuming energy. Large fossil fuel power stations operate at high efficiency, and can be used for district heating or to produce district cooling , leading to

5035-411: The high cost of the electrification infrastructure. Therefore, most long-distance lines in developing or sparsely populated countries are not electrified due to relatively low frequency of trains. Network effects are a large factor with electrification. When converting lines to electric, the connections with other lines must be considered. Some electrifications have subsequently been removed because of

5130-532: The lead up to the local authority elections of 2019, candidate for Mayor of the Kāpiti Coast District, Gwynn Compton, started a petition to extend electrification to Ōtaki. During the 2020 general election the National Party announced that National would extend the electric commuter rail service to Ōtaki and fast-track a four-lane expressway from Ōtaki to Levin. A business case for extending

5225-549: The line are two "cross-tie" substations at Ngauranga and Tawa, which provide a switching function but don't have transformers or rectifiers. Public road-rail crossings have warning lights and barriers, and some are now fitted with automatically locking pedestrian gates to prevent use while alarms are operating. In 2021 upgrading of the Plimmerton railway station started, to be completed by 2023. Some trains will then turn around at Plimmerton rather than Porirua thus increasing

5320-477: The line between Wellington and Tawa through Johnsonville. The deviation required the construction of two significant tunnels between Kaiwharawhara and Tawa . It opened as a single track line to freight on 24 July 1935 and as a double track line to passengers on 19 June 1937. The Wellington to Johnsonville section was retained as the Johnsonville Line . Electrification from Wellington to Paekakariki

5415-530: The line further to Levin has been pushed for by transport minister Michael Wood in 2022, adding an extra 35 km to the line, going past Ōtaki and possibly including Te Horo and Manakau . Railway electrification system Railway electrification is the use of electric power for the propulsion of rail transport . Electric railways use either electric locomotives (hauling passengers or freight in separate cars), electric multiple units ( passenger cars with their own motors) or both. Electricity

5510-579: The line no longer following the curves of the shoreline bays north of Porirua; the previous 200m radius curves had a speed limit of 50 km/h. A new station at Paremata was required, and a new Paremata Inlet bridge. The Mana to Plimmerton section and bridge was opened on 16 October 1961. In conjunction with the extension of electrification to Paraparaumu in March 1983, double-track was extended from Paekakariki to Mackays Crossing on 5 December 1983. The section between Mackays Crossing and Paraparaumu, built across

5605-497: The losses (saving 2   GWh per year per 100   route-km; equalling about €150,000 p.a.). The line chosen is one of the lines, totalling 6000   km, that are in need of renewal. In the 1960s the Soviets experimented with boosting the overhead voltage from 3 to 6   kV. DC rolling stock was equipped with ignitron -based converters to lower the supply voltage to 3   kV. The converters turned out to be unreliable and

5700-422: The maximum power that can be transmitted, also can be responsible for electrochemical corrosion due to stray DC currents. Electric trains need not carry the weight of prime movers , transmission and fuel. This is partly offset by the weight of electrical equipment. Regenerative braking returns power to the electrification system so that it may be used elsewhere, by other trains on the same system or returned to

5795-402: The need for overhead wires between those stations. Maintenance costs of the lines may be increased by electrification, but many systems claim lower costs due to reduced wear-and-tear on the track from lighter rolling stock. There are some additional maintenance costs associated with the electrical equipment around the track, such as power sub-stations and the catenary wire itself, but, if there

SECTION 60

#1732802246618

5890-520: The number of trains that the line could carry, duplication and electrification of the line along with other improvements, such as curve easements, was planned and progressed in stages. The first section to bed double-tracked (from Wellington to Tawa Flat (now Tawa) was the Tawa Flat deviation . it bypassed the steep (1 in 36 to 40) grades from Wellington to Ngaio on the Johnsonville Line . The sections from Tawa to Porirua and subsequently from Porirua to

5985-551: The opening of the Kāpiti Expressway which has moved the main road west and out of the centre of Waikanae itself. Ten traction substations along the line take electricity from Wellington Electricity or Electra's 11,000-volt distribution network and transform and rectify it to 1500-volt direct current for the overhead traction lines. The substations are located at Wellington, Kaiwharawhara, Glenside, Paremata, Mana, Pukerua Bay, Paekakariki, Raumati, Lindale and Waikanae. Also along

6080-399: The peak capacity of the line by reducing the number of passengers on trains to Waikanae . For accidents on the single-track section between Pukerua Bay and Paekakariki see North–South Junction . Proposals for new stations at Raumati South , between Mackays Crossing and Paraparaumu , and Lindale , north of Paraparaumu near Otaihanga , were on hold, to be reconsidered after 2010, as it

6175-505: The phase separation between the electrified sections powered from different phases, whereas high voltage would make the transmission more efficient. UIC conducted a case study for the conversion of the Bordeaux-Hendaye railway line (France), currently electrified at 1.5   kV DC, to 9   kV DC and found that the conversion would allow to use less bulky overhead wires (saving €20 million per 100   route-km) and lower

6270-508: The problem by insulating the running rails from the current return should there be a leakage through the running rails. The Expo and Millennium Line of the Vancouver SkyTrain use side-contact fourth-rail systems for their 650 V DC supply. Both are located to the side of the train, as the space between the running rails is occupied by an aluminum plate, as part of stator of the linear induction propulsion system used on

6365-435: The quiet end-of-year holiday period, according to ONTRACK programme director David Gordon. The project involved 50 workers and 20 machines installing 600 traction poles in eight or nine metre deep holes, and laying 30 km of rail and 30,000 sleepers. The project allows commuter services from Waikanae every 15 minutes at peak travel times but more commonly every 30 minutes. The new Matangi electric multiple units were used on

6460-465: The resistance per unit length unacceptably high compared with the use of DC. Third rail is more compact than overhead wires and can be used in smaller-diameter tunnels, an important factor for subway systems. The London Underground in England is one of few networks that uses a four-rail system. The additional rail carries the electrical return that, on third-rail and overhead networks, is provided by

6555-570: The revenue obtained for freight and passenger traffic. Different systems are used for urban and intercity areas; some electric locomotives can switch to different supply voltages to allow flexibility in operation. Six of the most commonly used voltages have been selected for European and international standardisation. Some of these are independent of the contact system used, so that, for example, 750   V   DC may be used with either third rail or overhead lines. There are many other voltage systems used for railway electrification systems around

6650-498: The running rails. On the London Underground, a top-contact third rail is beside the track, energized at +420 V DC , and a top-contact fourth rail is located centrally between the running rails at −210 V DC , which combine to provide a traction voltage of 630 V DC . The same system was used for Milan 's earliest underground line, Milan Metro 's line 1 , whose more recent lines use an overhead catenary or

6745-467: The same task: converting and transporting high-voltage AC from the power grid to low-voltage DC in the locomotive. The difference between AC and DC electrification systems lies in where the AC is converted to DC: at the substation or on the train. Energy efficiency and infrastructure costs determine which of these is used on a network, although this is often fixed due to pre-existing electrification systems. Both

6840-543: The service "visible" even in no bus is running and the existence of the infrastructure gives some long-term expectations of the line being in operation. Due to the height restriction imposed by the overhead wires, double-stacked container trains have been traditionally difficult and rare to operate under electrified lines. However, this limitation is being overcome by railways in India, China and African countries by laying new tracks with increased catenary height. Wellington Tramway Museum The Wellington Tramway Museum

6935-569: The steep approaches to the tunnel. The system was also used for suburban electrification in East London and Manchester , now converted to 25   kV   AC. It is now only used for the Tyne and Wear Metro . In India, 1,500   V DC was the first electrification system launched in 1925 in Mumbai area. Between 2012 and 2016, the electrification was converted to 25   kV 50   Hz, which

7030-443: The supply grid, requiring careful planning and design (as at each substation power is drawn from two out of three phases). The low-frequency AC system may be powered by separate generation and distribution network or a network of converter substations, adding the expense, also low-frequency transformers, used both at the substations and on the rolling stock, are particularly bulky and heavy. The DC system, apart from being limited as to

7125-694: The three-phase induction motor fed by a variable frequency drive , a special inverter that varies both frequency and voltage to control motor speed. These drives can run equally well on DC or AC of any frequency, and many modern electric locomotives are designed to handle different supply voltages and frequencies to simplify cross-border operation. Five European countries – Germany, Austria, Switzerland, Norway and Sweden – have standardized on 15   kV 16 + 2 ⁄ 3   Hz (the 50   Hz mains frequency divided by three) single-phase AC. On 16 October 1995, Germany, Austria and Switzerland changed from 16 + 2 ⁄ 3   Hz to 16.7   Hz which

7220-575: The through traffic to non-electrified lines. If through traffic is to have any benefit, time-consuming engine switches must occur to make such connections or expensive dual mode engines must be used. This is mostly an issue for long-distance trips, but many lines come to be dominated by through traffic from long-haul freight trains (usually running coal, ore, or containers to or from ports). In theory, these trains could enjoy dramatic savings through electrification, but it can be too costly to extend electrification to isolated areas, and unless an entire network

7315-466: The train stops with one collector in a dead gap, another multiple unit can push or pull the disconnected unit until it can again draw power. The same applies to the kind of push-pull trains which have a locomotive at each end. Power gaps can be overcome in single-collector trains by on-board batteries or motor-flywheel-generator systems. In 2014, progress is being made in the use of large capacitors to power electric vehicles between stations, and so avoid

7410-713: The train's kinetic energy back into electricity and returns it to the supply system to be used by other trains or the general utility grid. While diesel locomotives burn petroleum products, electricity can be generated from diverse sources, including renewable energy . Historically, concerns of resource independence have played a role in the decision to electrify railway lines. The landlocked Swiss confederation which almost completely lacks oil or coal deposits but has plentiful hydropower electrified its network in part in reaction to supply issues during both World Wars. Disadvantages of electric traction include: high capital costs that may be uneconomic on lightly trafficked routes,

7505-413: The transmission and conversion of electric energy involve losses: ohmic losses in wires and power electronics, magnetic field losses in transformers and smoothing reactors (inductors). Power conversion for a DC system takes place mainly in a railway substation where large, heavy, and more efficient hardware can be used as compared to an AC system where conversion takes place aboard the locomotive where space

7600-470: The tyres do not conduct the return current, the two guide bars provided outside the running ' roll ways ' become, in a sense, a third and fourth rail which each provide 750 V DC , so at least electrically it is a four-rail system. Each wheel set of a powered bogie carries one traction motor . A side sliding (side running) contact shoe picks up the current from the vertical face of each guide bar. The return of each traction motor, as well as each wagon ,

7695-432: The voltage, the lower the current for the same power (because power is current multiplied by voltage), and power loss is proportional to the current squared. The lower current reduces line loss, thus allowing higher power to be delivered. As alternating current is used with high voltages. Inside the locomotive, a transformer steps the voltage down for use by the traction motors and auxiliary loads. An early advantage of AC

7790-405: The weight of an on-board transformer. Increasing availability of high-voltage semiconductors may allow the use of higher and more efficient DC voltages that heretofore have only been practical with AC. The use of medium-voltage DC electrification (MVDC) would solve some of the issues associated with standard-frequency AC electrification systems, especially possible supply grid load imbalance and

7885-532: The world, and the list of railway electrification systems covers both standard voltage and non-standard voltage systems. The permissible range of voltages allowed for the standardised voltages is as stated in standards BS   EN   50163 and IEC   60850. These take into account the number of trains drawing current and their distance from the substation. 1,500   V DC is used in Japan, Indonesia, Hong Kong (parts), Ireland, Australia (parts), France (also using 25 kV 50 Hz AC ) ,

7980-534: The world, including China , India , Japan , France , Germany , and the United Kingdom . Electrification is seen as a more sustainable and environmentally friendly alternative to diesel or steam power and is an important part of many countries' transportation infrastructure. Electrification systems are classified by three main parameters: Selection of an electrification system is based on economics of energy supply, maintenance, and capital cost compared to

8075-680: Was 474 tons per train northward and 473 southward, with passenger trains just over 560 tons in aggregate. From 1982, the new EM/ET electric multiple units were delivered. They had been ordered to replace the wooden carriage trains hauled by electric locomotives on commuter services and largely displaced the DM/D units on the Paraparaumu Line. By the 1980s, the ED and EW electric locomotives were not required for either freight trains or for commuter trains. They were retired due to age and lack of use,

8170-517: Was claimed that there were problems affecting a station at Raumati (the provision of access to SH 1 and park-and-ride facilities) and an unstable hillside behind the line. The 2013 Review and Draft 2014 Review of the Wellington Regional Public Transport Plan confirmed that building additional stations on the Kapiti Line at Raumati and Lindale was no longer recommended, with the cost of new stations outweighing

8265-484: Was completed on 24 July 1940, avoiding the smoke nuisance in the new deviation's lengthy second tunnel, and providing extra tractive effort on the Paekakariki Hill between Pukerua Bay and Paekakariki. Paekakariki became a major station where long-distance trains swapped from steam (later diesel ) to electric motive power and became the northern terminus of the commuter line for many years. Electrification

8360-436: Was constructed by the Wellington and Manawatu Railway Company (W&MR) as part of its line between Wellington and Longburn , south of Palmerston North . It was built by a group of Wellington businessmen frustrated with the indecision of the government about the construction of a west coast route out of Wellington. Construction of the line began in September 1882 and followed a circuitous, steep route via Johnsonville . It

8455-649: Was double-tracked). From 14 June 1943 a siding for the US Marines' camp at Mackays Crossing with a crossing loop and tablet station was opened; near where the Wellington Tramway Museum is now located. With duplication of the track from Paekakariki to Mackays Crossing and automatic signalling from Paekakariki to Paraparaumu, Mackays Crossing was relay worked from the Paekakariki South signal box from December 1943. But on 25 March 1946

8550-437: Was exacerbated because the return current also had a tendency to flow through nearby iron pipes forming the water and gas mains. Some of these, particularly Victorian mains that predated London's underground railways, were not constructed to carry currents and had no adequate electrical bonding between pipe segments. The four-rail system solves the problem. Although the supply has an artificially created earth point, this connection

8645-404: Was extended to Paraparaumu on 7 May 1983 and to Waikanae on 20 February 2011. The W&MR constructed the line as a single-track railway with crossing loops at principal stations to allow opposing trains to pass. In the 1920s the need for extra train services on the line was recognised, both to increase the tonnage of goods trains and to allow more frequent suburban passenger services. To increase

8740-553: Was first applied successfully by Frank Sprague in Richmond, Virginia in 1887-1888, and led to the electrification of hundreds of additional street railway systems by the early 1890s. The first electrification of a mainline railway was the Baltimore and Ohio Railroad's Baltimore Belt Line in the United States in 1895–96. The early electrification of railways used direct current (DC) power systems, which were limited in terms of

8835-607: Was opened to Plimmerton in October 1885 and completed on 3 November 1886. The final spike was driven just north of Paraparaumu, at Otaihanga . The government acquired the Wellington and Manawatu Railway Company on the 7 December 1908 and incorporated it into its national network as the southern portion of the North Island Main Trunk line. In 1928, work began on a deviation to avoid the difficult section of

8930-527: Was president of the Tramway Museum. The museum is open every Saturday and Sunday from 11am to 4.30pm (last tram 4pm), and on public holidays except for Christmas Day. After Christmas the museum opens daily from Boxing Day (26 December) to Wellington Anniversary Day in late January. The museum also opens with restricted hours throughout some school holidays, these dates being advertised on the museum's website. During open hours tram rides are available in

9025-541: Was suggested that diesel multiple units could be used on services north of Waikanae. This could be a "final nail in the coffin" for the under-threat Capital Connection service from Wellington to Palmerston North, which also stops at Ōtaki. During the 2017 general election , the Green Party proposed extending electrification to Ōtaki as an alternative to the Northern Corridor extension from Pekapeka. In

#617382