63-654: Download coordinates as: The Namma Metro ( English: Our metro ), also known as Bangalore Metro, is the rapid transit system serving the city of Bangalore in India. Out of the operational 68 metro stations of Namma Metro as of November 2024, there are 59 elevated stations, eight underground stations and one at-grade station. The first section (on the Purple Line) of the Namma Metro system opened on 20 October 2011 between Baiyappanahalli and M.G Road . The system
126-479: A headway varying between 3–15 minutes. The trains initially began with three coaches but later grew to six coaches as ridership increased. Power is supplied by 750 V direct current through third rail . As of March 2024, the metro system had an average daily ridership of about 636,000 passengers. On August 14 2024, the ridership was 9.17 lakh, the highest recorded so far in the history of Namma Metro. The State Town Planning Department had recommended looking into
189-562: A mass rapid transit project, i.e. a metro for Bengaluru city, back in 1977. A high-level Committee had also agreed that a metro study was warranted and a team from Southern Railway (SR) was commissioned to do this in 1981. The Southern Railway team recommended a two-corridor metro, 80 km (50 mi) in length, in addition to commuter rail lines and a ring railway. In 1993, the State of Karnataka established another committee to look into mass rapid transit. This committee had again recommended
252-624: A regular metro line with fewer halts would be built instead of a high speed rail, thus travel time between city to airport would be less. As early as in February 2012, the Central Government had also requested BMRC to start work on the airport link during Phase 2 itself. Following this, in September 2016, suggestions were invited from public to choose any one of nine possible extension routes from existing and proposed metro lines to
315-434: A result, there were several postponements. The difficult geological conditions below ground with a mix of soft soil, high groundwater levels, hard granite and large boulders was a major impediment for tunnel boring. A major delay was due to a broken cutter head of TBM Godavari for which spares had to be ordered from Italy. Phase 1, containing two lines aggregating 42.3 km (26.3 mi) was completed and services opened to
378-443: A road-cum-rail flyover, road widening and allied works. Construction of the 7.5 km elevated section of a new pink line between Kalena Agrahara and Tavarekere (previously Swagat Road Cross) stations, estimated to cost ₹575.52 crore (US$ 81 million) began post tendering in February 2018. The tender includes the construction of the elevated viaduct, 5 stations and car depot line to Kothanur depot. BMRC initially floated tenders for
441-949: A separate compensation of Rs 10 lakh for each of the deaths from the Chief Ministers' Relief Fund. Phase 2 originally involved extending four reaches of the two lines in all directions and two new lines (Yellow Line and Pink Line). The ORR-East Line was later included as Phase 2A followed by the Airport Line (as a continuation of the ORR-East Line) as Phase 2B. The line was later named the Blue Line . Construction of Phase 2A has been divided into two (elevated section) packages. Construction of Phase 2B has been divided into three (elevated section) packages. Airport stations have not been included with tenders as they will likely be built by BIAL. A 124 km (77 mi) Phase 3
504-668: A signal and telecommunication workshop at Podanur , Coimbatore . It has three EMU car sheds in Chennai at Avadi , Tambaram , Velachery and MEMU sheds at Kollam and Palakkad . Southern Railway maintains trip sheds at Basin Bridge , Egmore , Tondiarpet and Jolarpettai . Southern Railway operated ticket printing presses at Royapuram , Thiruvananthapuram and Tiruchirappalli , but these have been phased out due to digitization . Southern Railways uses both ICF coaches and LHB coaches for its trains. ICF coaches manufactured by
567-492: Is a rapid transit system serving the city of Bengaluru , the capital city of the state of Karnataka , India . It is the second-longest operational metro network in India with an operational length of 76.95 kilometers, just behind Delhi Metro . Upon its inauguration in 2011, it became the first underground metro system in South India . Namma Metro has a mix of underground, at grade , and elevated stations. Out of
630-491: Is estimated at 7.7 lakhs. Construction of the airport line is expected to begin by October 2021. In January 2023, there was an accident when a reinforcement cage of the under-construction metro pier fell on a woman software engineer, Tejaswini Sulakhe and her son Vihan in HBR Layout, which led to their eventual death. BMRCL announced a financial assistance of ₹ 20 lakh. Chief Minister Basavaraj Bommai also announced
693-527: Is estimated to cost ₹247.41 crore while the east extension (15.5 km) was awarded for ₹1,300 crore (US$ 180 million). Construction of the yellow line, a new line from Rashtreeya Vidyalaya Road to Bommasandra in 3 packages began post awarding of tenders in November 2017. The first package (6.418 km / 3.988 mi) was a stretch from Bommasandra to Hosa Road station, including depot entry line to Hebbagodi depot and five Metro stations. The second package
SECTION 10
#1732780014462756-566: Is headed by the General Manager, assisted by an Additional General Manager. Southern Railway is headquartered in Chennai and is divided into six divisions namely Chennai , Tiruchirappalli , Madurai , Palakkad , Salem and Thiruvananthapuram . The zone operates both passenger and freight trains. Various classes of passenger trains including Vande Bharat Express , Shatabdi Express and Tejas Express are operated by Southern Railways. Freight operations include container traffic from
819-464: Is identified by a specific color. The system uses rolling stock of standard gauge and has a combination of elevated, underground and at-grade lines. The metro is operational from about 05:00 to 23:00 hours with trains operating at a frequency of 5 to 15 minutes. The Purple Line connects Challaghatta in the west and Whitefield (Kadugodi) in the east, while the Green Line connects Madavara in
882-458: Is mostly underground (13.79 km or 8.57 mi), but also has a 6.98 km (4.34 mi) elevated section and a 0.48 km (0.30 mi) at-grade section. There are 18 stations on the line, of which 12 are underground and six are elevated. Unlike Phase 1, all stations being built in Phase 2 will have bus bays and/or parking facilities. Karnataka Industrial Areas Development Board (KIADB)
945-612: Is one of the eighteen zones of Indian Railways . It is headquartered at Chennai and operates across the states of Tamil Nadu , Kerala , Andhra Pradesh and the union territory of Puducherry . The origin of the Southern Railway can be traced back to the Madras Railway formed in 1845. Southern Railway was created on 14 April 1951 by merging three state railways, namely, the Madras and Southern Mahratta Railway ,
1008-673: Is operated by the Bangalore Metro Rail Corporation Limited (BMRCL). On 25 March 2023, a new section of the Purple Line from Krishnarajapura to Whitefield (Kadugodi) (13.71 km) with 12 new stations was inaugurated by the Prime Minister , Narendra Modi . After the inauguration, the Purple Line was complete and the Namma Metro became the second longest metro system in India (76.95 km) after Delhi Metro . Each line of Namma Metro
1071-506: Is responsible for acquiring land for Phase 2. It was estimated that 102.02 hectares (252.1 acres) of land would be required for Phase 2 (including Phase 2A). By April 2017, BMRCL had already spent ₹5000 crore on land acquisition. Construction work began on the south extension of the Green Line from Yelachenahalli to Silk Institute (6.29 km or 3.91 mi) and the west extension of the Purple Line from Mysore Road to Kengeri (8.81 km or 5.47 mi) by October 2016. Construction work on
1134-440: Is set to escalate about 5 per cent every year with increasing cost of inputs. The Union government will share that part of cost escalation due to increase in central levies, while the State and BMRCL will have to bear any other escalation. The total project cost for Phase 2 is estimated to reach at least ₹30,000 crore (US$ 4.2 billion) at the start of construction itself. In October 2018, Deputy Chief Minister G Parameshwara stated that
1197-629: Is the commuter rail system in the city of Chennai , operated by the Southern Railways. The system operates four lines with a track length of 1,174.21 km (729.62 mi), of which 509.71 km (316.72 mi) are dedicated dual tracks for EMUs. Nilgiri Mountain Railway is a 1,000 mm ( 3 ft 3 + 3 ⁄ 8 in ) metre gauge railway in Nilgiris district connecting Mettupalayam and Udagamandalam . It
1260-427: Is underground and about 33.48 kilometres (20.80 mi) is elevated. There are 40 stations in Phase 1, of which seven stations are underground, one is at grade and 32 are elevated. The first phase of the project was initially budgeted at ₹6,395 crore (US$ 875 million). With route extensions and cost escalation, this was later revised to ₹11,609 crores (US$ 1.6 billion). There were many delays during construction and as
1323-1233: The Integral Coach Factory in Chennai have been used predominantly for over sixty years since the formation of the zone in 1951. The ICF coaches are slowly being replaced by newer LHB rakes which provide better passenger comfort and safety. Following are the list of railway lines operational. Defunct railway lines include Kundala Valley Railways , Kochin Tramways , Madras Tramways , Tiruchendur Light Railway, Dharmapuri and Krishnagiri famine light railways, Kodaikanal Light Railway. Southern Railways operates 41 sets of express trains and 97 sets of superfast trains. The superfast trains include: Vande Bharat Express (8), Shatabdi Express (2), Garib Rath Express (2), Duronto Express (1), Jan Shatabdi Express (4), Sampark Kranti Express (1), Anuvrat Express (1), Humsafar Express (1), Tejas Express (1), Uday Express (1), Antyodaya Express (2) and Double Decker Express (1). Apart from this, it operates various Passenger trains , DEMU , EMU services, Chennai Suburban and
SECTION 20
#17327800144621386-609: The Madras and Southern Mahratta Railway . In 1944, all the railway companies operating in British India were taken over by the Government. Post Independence , various re-grouping proposals were studied as there were 42 different railway systems. In December 1950, the Central Advisory Committee for Railways approved the plan for Indian Railways into six zonal systems and the Southern Railway zone
1449-633: The South Indian Railway Company , and the Mysore State Railway and became the first railway zone created in newly formed India. Southern Railway maintains about 5,081 km (3,157 mi) of railway lines and operates 727 railway stations . It has the distinction of operating the first railway line in India , which opened for traffic from Redhills to Chindadripettai in Madras on 12 September 1836. The history of
1512-603: The 68 operational metro stations of Namma Metro as of November 2024, there are 59 elevated stations, eight underground stations and one at-grade station. The system runs on standard-gauge tracks. Bengaluru Metro Rail Corporation Limited (BMRCL), a joint venture of the Government of India and the State Government of Karnataka , is the agency for building, operating and expanding the Namma Metro network. Services operate daily between 05:00 and 24:00 running with
1575-481: The Central Government. Phase 2 was cleared by the expenditure finance committee (EFC) in August 2013. The Union Cabinet finally announced that it had approved plans for Phase 2 on 30 January 2014. The estimated total cost for Phase 2 was around ₹26,405 crore (US$ 3.7 billion) at 2011-12 price levels. The State Government would contribute ₹9,000 crore (US$ 1.3 billion). The project cost of ₹26,405 at 2011–12 price levels
1638-648: The Green Line will be extended from Yelachenahalli to Silk Institute (previously named Anjanapura) along Kanakapura Road, and he north end from Nagasandra to Madavara (previously named BIEC) on Tumkur Road (NH-4). The east end of the Purple Line will be extended from Baiyappanahalli to Whitefield and the west end from Mysore Road to Kengeri (later extended to Challaghatta). A new, 18.82 km (11.69 mi) long, fully elevated line from RV Road to Bommasandra will be constructed, passing through Electronic City . The second new line will be 21.25 km (13.20 mi) from Kalena Agrahara (previously Gottigere) to Nagawara. The line
1701-563: The March–June period, 2019. One of the firms ( L&T ) won two bids. The total awarded tunneling tenders for the underground sections was ₹5,925.95 crores (appx US$ 812 million). Pre-tunneling construction work and piling for stations began in May 2019 by L&T. Tunnel boring using TBMs began in July 2020 by L&T. Tunnel boring work by the other two contractors (viz. Afcons & ITD-Cem)
1764-671: The Nagawara-Ramakrishna Hegde Nagar-Jakkur-Yelahanka route to the airport. On 10 January 2019, the State Cabinet approved a change in alignment for the proposed metro line to the airport. The new line would begin at Krishnarajapura (K.R. Pura) and be aligned along the northern part of ORR (Outer Ring Road), passing Nagawara, Hebbal, and Jakkur before heading towards the airport along Ballari road. The line would be 39.8 km (24.7 mi) long, about 8 km (5.0 mi) longer than
1827-536: The Nilgiri Mountain Railway. There are about 727 stations on the Southern railway network including 486 non suburban stations, 74 suburban stations and 166 halt stations. The major and highest revenue earning stations are Chennai Central , Chennai Egmore , Coimbatore Junction , Thiruvananthapuram Central , Tambaram , , Ernakulam Junction and Madurai Junction . Chennai Suburban Railway
1890-450: The Pink line from Nagawara directly north) were eliminated. An alternate route proceeding north till RK Hegde nagar and then turning west to Jakkur was then explored. However, even this had an obstacle as a high-pressure petroleum pipeline was passing through the originally proposed route. Bangalore Development Minister K. J. George announced on 12 May 2017 that the government had finalized
1953-460: The Purple line) commenced operations on 30 April 2016, providing connectivity between the east and west of the city. The second underground section, along with southern reaches (viz. Reach 4,4A) was opened on 18 June 2017. Once the east and west reaches were inter-connected with opening of the underground section of the purple line, ridership surged hugely. After the north–south underground section
List of Namma Metro stations - Misplaced Pages Continue
2016-605: The Southern Railway can be traced back to the Madras Railway . In 1832, the proposal to construct the first railway line in India at Madras was made by the British . In 1835, the railway track was constructed between Little Mount and Chintadripet in Madras and became operational in 1837. The Madras Railway was established later in 1845 and the construction on the first main line between Madras and Arcot started in 1853, which became operational in 1856. In 1908, Madras Railway merged with Southern Mahratta Railway to form
2079-576: The Southern railway network. Southern Railway utilizes various classes of electric and diesel locomotives to haul the trains. Steam locomotives are used by the Nilgiri Mountain Railway . The zone has three electric locomotive sheds and four diesel locomotive sheds. Southern Railway maintains wagon and locomotive workshops at Perambur, Chennai and Ponmalai, Tiruchirapalli , engineering workshop at Arakkonam , carriage maintenance workshops at Basin Bridge and Egmore and
2142-430: The airport. The proposed extension routes had an average length of 30 km (19 mi), and cost estimates ranged between ₹4,500 crore and ₹7,000 crore. A 25.9 km (16.1 mi) extension from Nagawara via Kannur and Bagaluru was the shortest, while the 35.4 km (22.0 mi) extension from Yeshwanthpur via Yelahanka, Kannur and Bagaluru was the longest of the proposed routes. BMRC received 1,300 responses from
2205-441: The city center which were the first metro tunnels built in South India . Construction of underground sections in Phase 1 commenced in late 2012. The delay was due to cancellation of the initial tenders called in early 2008 as the entire DPR had to be revised and bids received were too high. A second round of tendering was done in late 2009 with the gigantic Majestic inter-change station as a separate package. Bids were awarded for
2268-407: The construction of the 13.9 km underground section in four packages during June 2017. However, the tenders were cancelled as all the bids received were far too high (higher by nearly 70%) at Rs.8553.45 crores (US$ 1.28 billion) when compared to BMRC's estimated total of Rs 5047.56 crores (about US$ 760 million). The second round of tendering resulted in tenders being awarded to three firms during
2331-437: The cost of Phase 2 would be around ₹32,000 crore (US$ 4.5 billion). Phase 2 spans a length of 72.095–13.79 km (44.798–8.569 mi) underground, 0.48 km (0.30 mi) at grade and 57.825 km (35.931 mi) elevated, and adds 62 stations to the network, of which 12 are underground. Phase 2 includes extension of the two Phase 1 lines in both directions, as well as construction of two new lines. The south end of
2394-638: The cross was to be at the Central Railway Station in Bengaluru, completely underground. The economic rate-of-return was forecast at 22.3%. The financial forecast assumes a government subsidy for interest payments and some depreciation, i.e. fare revenue will cover somewhat more than direct operating costs. The Government accepted this option. BMRTL ceased to exist and was replaced by Bengaluru Metro Rail Corporation Ltd (BMRCL). Delhi Metro Rail Corporation Limited (DMRC) prepared and submitted
2457-471: The detailed project for the first phase of Namma Metro in May 2003. The DPR was for a 33 km (21 mi) network with 32 stations for Phase 1 of the project, using standard gauge . The project was approved by the Union Cabinet on 25 April 2006. The foundation stone for construction of Phase 1 was laid by then Prime Minister Dr. Manmohan Singh on 24 June 2006. Navayuga Engineering Company Limited
2520-561: The lowest bidder for all packages. However, the tenders were quashed due to cash flow problems and bankruptcy proceedings by the firm. A second round of tendering was done in December 2019 and bids were received by multiple firms in March 2020. There are two packages. The first package included 2.84 km of ramps for a flyover at Central Silk board junction in addition to 9.859 km of viaduct with six elevated stations. The second package
2583-693: The north and Silk Institute in the south. The network is currently being expanded with the addition of new lines and extensions to existing lines (see below for the complete list of stations). (ಕೆ. ಆರ್. ಪುರ) The list below includes operational and under-construction stations. Grey Line ** Grey Line (TBC) — Sri Balagangadharanatha Swamiji Stn., Hosahalli (Int) . KHB Colony . Vinayaka Nagara . Sumanahalli Cross (Int) . Sunkadakatte . Herohalli . Byadarahalli . Forest Gate . Kadabagere Namma Metro Under construction (3) Under planning (3) [REDACTED] Namma Metro ( transl. Our Metro ), also known as Bengaluru Metro ,
List of Namma Metro stations - Misplaced Pages Continue
2646-444: The ports, coal bound to the thermal power stations, oil and petroleum products from refineries, cement and food grains. Most of the lines inside ports, thermal stations, manufacturing industries and owned by the respective companies and the zone provides a link connecting to its network along with the wagons and locomotives. The zone has a larger proportion of passenger traffic compared to freight. There are about 727 stations on
2709-692: The project on BOT basis. However, the project hadn't taken off. In 2003, the Government of Karnataka commissioned the Delhi Metro Rail Corporation (DMRC), which had successfully developed the Delhi Metro , to carry out a detailed preparation study for a metro in Bengaluru, to be done emulating the technical and financial aspects of the approach used in Delhi. The study recommended a 2-line metro, 60 km (37.3 mi) and 50 km (31 mi) in length, cross shaped. The middle of
2772-532: The public on 19 June 2017. The final cost for Phase 1 was ₹14,405 crores. The State Government accorded approval for preparation of the detailed project report (DPR) for Phase 2 by DMRC on 4 January 2011. The high power committee (HPC) gave in-principle clearance to proceed with Phase 2 in July 2011. Karnataka government gave in-principle approval to Phase 2 of the Namma Metro project on 3 January 2012. However, there were delays in DPR preparation and hence approval from
2835-423: The public on 20 October 2011. There was an overwhelming response by the public at commencement of operations. As per BMRCL sources, within the first 3 days of operations 169,019 people rode the metro. At the end of the 4th day, about 200,000 passengers had already commuted on Namma Metro. Namma Metro's first 12-day cumulative revenue was ₹1 crore (US$ 100,000). The northern section of Green Line (Reach 3, 3A, 3B)
2898-504: The public. A 25.9 km (16.1 mi) extension of the Kalena Agrahara (previously Gottigere) – Nagawara line via Kannur and Bagaluru to the airport emerged as the most popular choice. Since Bengaluru International Airport Limited (BIAL) forbade underground construction from the southern side of the airport (due to security as it would have to pass beneath the airport's second runway), the shortest route options (i.e. extending
2961-511: The route previously proposed. It is estimated to cost ₹10,584 crore (US$ 1.5 billion) almost twice as much as the previous route's estimate of ₹5,950 crore (US$ 830 million). The Union Cabinet cleared two much awaited lines of the Bengaluru Metro's Phase 2A and 2B on 20 April 2021. Phase 2A and Phase 2B lines total a distance of 58.19 km and were approved at a cost of Rs.14,788 crore. The projected ridership on both these lines in 2026
3024-580: The same metro project put forward by SR in 1983 and the same circular railway. The state created Bangalore Mass Rapid Transit Ltd (BMRTL) in 1994, with terms of reference to seek a public/private partnership for a mass rapid transit project. The government immediately introduced a special city cess dedicated to the anticipated mass rapid transit project. BMRTL commissioned a feasibility study which came up with an elevated, LRT-based, 300 km (190 mi) long network on 6 routes. A private consortium led by United Breweries Group undertook further development of
3087-632: The state government, another new corridor spanning 35 km from Hebbal to Sarjapura was announced (to be taken up as Phase 3B). The Chief Minister stated that the Detailed Project Report (DPR) would be prepared for the proposed corridor, estimated to cost around ₹15,000 crores. The two corridors announced previously were estimated to cost ₹13,500 crores. On 16 August 2024, the Union Cabinet approved Phase 3, which will add two lines and 31 stations, with an estimated cost of ₹15,611 crores. Southern Railway zone Southern Railway ( SR )
3150-543: The total route length for Phase 1 became 42.3 km (26.3 mi). The objective was to connect the metro to the Outer Ring Road at northern and southern ends, and also cover the industrial areas of Peenya in the north-west, thereby providing better connectivity and increasing ridership. In October 2008, the Government of Karnataka approved this extension, which would cost an additional ₹1,763 crore (US$ 250 million). Both lines in Phase 1 have tunnel sections in
3213-430: The tunnel sections in 2011 and construction began in 2012. The tunnels bored with tunnel boring machines (TBMs), located approximately 60 feet (18 m) below ground level, have a diameter of 5.5 metres (18 ft 1 in) and are 5 metres (16 ft 5 in) apart. The TBMs were nicknamed Helen , Margarita , Kaveri , Krishna and Godavari. Tunnel boring of underground section UG1 (on east–west corridor)
SECTION 50
#17327800144623276-410: The west extension of Purple Line was awarded in two packages for ₹660 crore, while the Green Line south extension was awarded in a single package for ₹508.86 crore. Construction work for the north extension of the Green Line (from Nagasandra to Madavara) and the east extension of the Purple Line (from Baiyyappanahalli to Whitefield) began in July 2017. The 3.031 km (1.883 mi) north extension
3339-526: Was awarded the first contract to construct Reach 1 of the east–west corridor in 2006. Civil construction on the first section (Reach-1) of the Purple Line between Baiyyappanahalli and Mahatma Gandhi Road , commenced on 15 April 2007. DPRs for a northern extension (from Yeshwanthapura to Nagasandra ) and a southern extension (from Rashtreeya Vidyalaya Road to Yelachenahalli ) was submitted in October 2007 and June 2008 respectively. With these extensions,
3402-510: Was commenced in 2021. In September 2016, the government announced that a new 18 km (11 mi) line connecting Silk Board with K.R. Pura would be included in Phase 2 as Phase 2A of the project. The line would be along the eastern half of Outer Ring Road and is proposed to have 13 stations – Silk Board, HSR Layout, Agara, Ibbalur, Bellandur, Kadubeesanahalli, Kodibisanahalli, Marathahalli, ISRO, Doddanekundi, DRDO Sports Complex, Sarasvathi Nagara (previously Mahadevapura) and K.R. Pura. The cost
3465-419: Was completed on 17 March 2014. Track works and 3rd rail electrification works were completed on the 4.8 km (3.0 mi) east–west tunnel of the Purple line between Cubbon Park and Magadi Road and Bangalore Metro Rail Corporation Ltd (BMRCL) began trials on 23 November 2015. The entire stretch of the Purple Line was opened on 29 April 2016. Tunnel boring of underground section UG2 (on north–south corridor)
3528-539: Was completed on 23 September 2016. The tunneling faced a major delay when the cutter head of TBM Godavari was broken and spares had to be awaited. Trial runs on the 4.0 km (2.5 mi) east–west tunnel of the Green line between Sampige Road and National College were commenced on 31 March 2017. The entire stretch of Green Line was opened on 19 June 2017, thus completing Phase 1 of the project. After missing deadlines, Namma Metro's first section (Reach-1) finally opened to
3591-471: Was created on 14 April 1951 by merging three state railways, namely, the Madras and Southern Mahratta Railway , the South Indian Railway Company , and the Mysore State Railway . Southern Railway zone covers the states of Tamil Nadu , Kerala , Puducherry and a small portion of Andhra Pradesh . Andaman and Nicobar will form part of the zone once the proposed new railway line between Port Blair and Diglipur becomes operational. The Southern Railway
3654-499: Was estimated to be ₹4202 crores. BMRCL prepared the detailed project report for the proposed line and submitted the DPR to the state government on 28 October 2016. Phase 2A was approved by the State Cabinet on 1 March 2017. The ORR Metro line (Blue line) will have interchange stations with the extended Purple Line at K.R. Pura and with the proposed R V Road – Bommasandra line (Yellow Line) at Silk Board. Tenders for ORR Metro line (east) were called in February 2018 and IL&FS emerged
3717-416: Was for 8.377 km viaduct with seven elevated stations, 1.097 km depot line and a 0.30 km pocket track. There had been a proposal to build a 33 km (21 mi) high speed rail line from MG Road to Kempegowda International Airport (KIA), at a cost of ₹5,767 crore (US$ 810 million). This was to be executed by an independent SPV, but later it was decided that BMRC would manage this project and
3780-417: Was for a 6.38 km (3.96 mi) stretch from Hosa Road to Bommanahalli (previously HSR Layout). Both packages were awarded for ₹1,750 crore (US$ 250 million) to Thailand-based ITD Cementation India. The third package was for a stretch from RV Road to Bommanahalli (previously HSR Layout), 6.34 km long elevated section and five stations, for ₹797.29 crores (US$ 110 million) and includes the construction of
3843-407: Was initially proposed in May 2016. Certain significant sections that were proposed for Phase 3 were included in Phase 2 as Phase 2A and Phase 2B. On 7 March 2020 it was announced that two corridors totaling 44.65 km would be built as fully elevated lines under PPP mode (Kempapura-Jayaprakash Nagara 4th Ph (along ORR-West) and Hosahalli-Kadabagere). On 4 March 2022, during a budget speech by
SECTION 60
#17327800144623906-408: Was initially scheduled to be opened by the end of 2012. However, it was delayed and finally opened on 1 March 2014. BMRCL MD Pradeep Singh Kharola stated that about 25,000 passengers travelled on the line on the opening day. In the first month of operations, 7.62 lakh people used the line, at an average of 24,605 daily, generating revenues of ₹1.5 crore (US$ 210,000). The first underground section (on
3969-406: Was opened (simultaneously with the elevated reach 4,4A in the south), the network provided connectivity in all four directions with interchange between the lines and this further increased ridership. Ridership kept increasing and was around 4,50,000 daily (September 2019). Phase 1 comprises two lines spanning a length of 42.30 kilometres (26.28 mi), of which about 8.82 kilometres (5.48 mi)
#461538