Misplaced Pages

Joralemon Street Tunnel

Article snapshot taken from Wikipedia with creative commons attribution-sharealike license. Give it a read and then ask your questions in the chat. We can research this topic together.
#27972

117-803: The Joralemon Street Tunnel ( / dʒ ə ˈ r æ l ɛ m ə n / , ju- RAL -e-mun ), originally the Brooklyn–Battery Tunnel , is a pair of tubes carrying the IRT Lexington Avenue Line ( 4 and ​ 5 trains) of the New York City Subway under the East River between Bowling Green Park in Manhattan and Brooklyn Heights in Brooklyn , New York City . The Joralemon Street Tunnel

234-402: A continuous flight augering (CFA) pile, is formed by drilling into the ground with a hollow stemmed continuous flight auger to the required depth or degree of resistance. No casing is required. A cement grout mix is then pumped down the stem of the auger. While the cement grout is pumped, the auger is slowly withdrawn, conveying the soil upward along the flights. A shaft of fluid cement grout

351-612: A receiver was appointed to oversee the completion of the tunnel. By that July, the city's Public Service Commission ordered that additional shifts of workers be hired for the Joralemon project so that test trains could start running through the tunnels within three months. The first test train, carrying officials, reporters, and construction engineers, ran through the Joralemon Street Tunnel to Brooklyn at 12:40 p.m. on November 27, 1907. The Joralemon Street Tunnel and

468-478: A 65-story skyscraper. The MTA mandated that the developers pay for station improvements at Grand Central to allow for the building's construction. In 2015, SL Green, the developer, gave $ 220 million toward the building's construction, of which two-thirds of the money would be used for station redesign; this marked the largest private investment to date to the New York City Subway system. As part of

585-402: A Continuous Flight Auger rig but using smaller, more lightweight equipment. This piling method is fast, cost-effective and suitable for the majority of ground types. In drilled pier foundations, the piers can be connected with grade beams on which the structure sits, sometimes with heavy column loads bearing directly on the piers. In some residential construction, the piers are extended above

702-430: A continuous barrier in the ground. The main application of sheet piles is in retaining walls and cofferdams erected to enable permanent works to proceed. Normally, vibrating hammer, t-crane and crawle drilling are used to establish sheet piles. Soldier piles, also known as king piles or Berlin walls, are constructed of steel H sections spaced about 2 to 3 m apart and are driven or drilled prior to excavation. As

819-417: A displacement pile (like Olivier piles ) may provide the cost efficiency of an augercast pile and minimal environmental impact. In ground containing obstructions or cobbles and boulders, augercast piles are less suitable as refusal above the design pile tip elevation may be encountered. Small Sectional Flight Auger piling rigs can also be used for piled raft foundations. These produce the same type of pile as

936-420: A failure of the foundation system. Vibrated stone columns are a ground improvement technique where columns of coarse aggregate are placed in soils with poor drainage or bearing capacity to improve the soils. Specific to marine structures, hospital piles (also known as gallow piles) are built to provide temporary support to marine structure components during refurbishment works. For example, when removing

1053-412: A large hollow steel pile, of some 4 m in diameter with approximately 50mm thick walls, some 25 m deep into the seabed, through a 0.5 m layer of larger stone and gravel to minimize erosion around the pile. A transition piece (complete with pre-installed features such as boat-landing arrangement, cathodic protection , cable ducts for sub-marine cables, turbine tower flange, etc.) is attached to

1170-515: A long time below the groundwater level. In 1648, the Royal Palace of Amsterdam was constructed on 13,659 timber piles that still survive today since they were below groundwater level. Timber that is to be used above the water table can be protected from decay and insects by numerous forms of wood preservation using pressure treatment ( alkaline copper quaternary (ACQ), chromated copper arsenate (CCA), creosote , etc.). Splicing timber piles

1287-701: A low bid to retain control of underground rapid transit for himself and his construction company. Contract 2, giving a lease of 35 years, was executed between the commission and the Rapid Transit Construction Company on September 11, 1902. Construction on the Manhattan side began on March 4, 1903, and on the Brooklyn side on July 10, 1903. While the RTC had allocated $ 2 million to the tubes' construction (equivalent to $ 54 million in 2023),

SECTION 10

#1732772645028

1404-492: A maximum gradient of 3.1 percent. The lowest points on the tubes are about 91 to 95 feet (28 to 29 m) below the mean high water level of the East River. About 700 feet (210 m) of the tunnel in Brooklyn is above the water level of the river. While the Manhattan end of the tunnels was constructed through solid rock, the Brooklyn end was constructed through sandy ground. The steelwork for Contract 2 tunnels, including

1521-608: A new exit was provided at Reade Street and Lafayette Street and a new passageway under Reade Street was built connecting to the Chambers Street station on the BMT Nassau Street Line. At the center of the enlarged platforms, a new overhead passage was built, providing more direct access to the Municipal Building . The platform extensions allowed the old platform extensions at the southern end of

1638-432: A rate of 5 to 12 feet (1.5 to 3.7 m) per day. All of the headings were driven within a pressurized environment. After the headings had been driven approximately 100 feet (30 m), two thick brick walls were constructed at each end, creating air locks . An upper lock gave workers access to the heading, while a lower lock allowed spoils to be extracted from the excavation and through the shafts on either side. The work

1755-615: A river pontoon, the brow will be attached to hospital pile to support it. They are normal piles, usually with a chain or hook attachment. Piled walls can be drivene or bored. They provide special advantages where available working space dictates and open cut excavation not feasible. Both methods offer technically effective and offer a cost efficient temporary or permanent means of retaining the sides of bulk excavations even in water bearing strata. When used in permanent works, these walls can be designed to resist vertical loads in addition lateral load from retaining soil. Construction of both methods

1872-453: A straight-shaft pile. These piles are suited for expansive soils which are often subjected to seasonal moisture variations, or for loose or soft strata. They are used in normal ground condition also where economics are favorable. Under reamed piles foundation is used for the following soils:- 1. Under reamed piles are used in black cotton soil: This type of soil expands when it comes in contact with water and contraction occurs when water

1989-462: A tripod rig to install piles is one of the more traditional ways of forming piles. Although unit costs are generally higher than with most other forms of piling, it has several advantages which have ensured its continued use through to the present day. The tripod system is easy and inexpensive to bring to site, making it ideal for jobs with a small number of piles. Sheet piling is a form of driven piling using thin interlocking sheets of steel to obtain

2106-496: Is a barrier built under ground using a mix of bentonite and water to prevent the flow of groundwater. A trench that would collapse due to the hydraulic pressure in the surrounding soil does not collapse as the slurry balances the hydraulic pressure. These are essentially variations of in situ reinforcements in the form of piles (as mentioned above), blocks or larger volumes. Cement, lime/quick lime, flyash, sludge and/or other binders (sometimes called stabilizer) are mixed into

2223-412: Is also not possible to extend the wall beyond the bottom of the excavation, and dewatering is often required. Screw piles , also called helical piers and screw foundations , have been used as foundations since the mid 19th century in screw-pile lighthouses . Screw piles are galvanized iron pipe with helical fins that are turned into the ground by machines to the required depth. The screw distributes

2340-463: Is formed to ground level. Reinforcement can be installed. Recent innovations in addition to stringent quality control allows reinforcing cages to be placed up to the full length of a pile when required. Augercast piles cause minimal disturbance and are often used for noise-sensitive and environmentally-sensitive sites. Augercast piles are not generally suited for use in contaminated soils, because of expensive waste disposal costs. In cases such as these,

2457-414: Is often used when the sides of the borehole are likely to slough off before concrete is poured. For end-bearing piles, drilling continues until the borehole has extended a sufficient depth (socketing) into a sufficiently strong layer. Depending on site geology, this can be a rock layer , or hardpan, or other dense, strong layers. Both the diameter of the pile and the depth of the pile are highly specific to

SECTION 20

#1732772645028

2574-575: Is one of the lines of the A Division of the New York City Subway , stretching from Lower Manhattan north to 125th Street in East Harlem . The line is served by the 4 , ​ 5 , ​ 6 , and <6> trains. The line was constructed in two main portions by the Interborough Rapid Transit Company (IRT), a private operator. The first portion, from City Hall north to 42nd Street,

2691-426: Is removed. So that cracks appear in the construction done on such clay. An under reamed pile is used in the base to remove this defect. 2. Under reamed piles are used in low bearing capacity Outdated soil (filled soil) 3.Under reamed piles are used in sandy soil when water table is high. 4. Under reamed piles are used, Where lifting forces appear at the base of foundation. An augercast pile, often known as

2808-426: Is still quite common and is the easiest of all the piling materials to splice. The normal method for splicing is by driving the leader pile first, driving a steel tube (normally 60–100 cm long, with an internal diameter no smaller than the minimum toe diameter) half its length onto the end of the leader pile. The follower pile is then simply slotted into the other end of the tube and driving continues. The steel tube

2925-409: Is the same as for foundation bearing piles. Contiguous walls are constructed with small gaps between adjacent piles. The spacing of the piles can be varied to provide suitable bending stiffness. Secant pile walls are constructed such that space is left between alternate 'female' piles for the subsequent construction of 'male' piles. Construction of 'male' piles involves boring through the concrete in

3042-432: The 14th Street–Union Square station killed five riders and injured 215 others in the worst accident on the system since the 1928 Times Square derailment . As a result of the crash, new safety protocols were put in place and there was a partial implementation of automation of the New York City Subway . The Metropolitan Transportation Authority announced in 2024 that it would begin installing 5G cellular equipment on

3159-517: The 42nd Street Shuttle . The system would be changed from looking like a "Z" system (as seen on a map) to an H-shaped system. One trunk would run via the new Lexington Avenue Line down Park Avenue, and the other trunk would run via the new Seventh Avenue Line up Broadway. It was predicted that the subway extension would lead to the growth of the Upper East Side and the Bronx . The rest of

3276-816: The Brooklyn Rapid Transit Company , via a subsidiary; and the City of New York. For decades, the Lexington Avenue Line was the only line in Manhattan that directly served the Upper East Side and East Midtown ; this four-track line is the most used rapid transit line in the United States. Its average of 1.3 million daily riders is more than the total riderships of the transit systems of Chicago (772,900 weekday passengers), Boston (569,200 weekday passengers), and San Francisco (452,600 weekday passengers). The line spurred

3393-649: The City Hall and Worth Street stations were both very close to the Brooklyn Bridge–City Hall station's Brooklyn Bridge and Duane Street exits, respectively, so both were abandoned. Finally, South Ferry is within walking distance of Bowling Green , and is right next to the corresponding station on the Broadway–Seventh Avenue line . Services that use the Lexington Avenue Line are colored forest green. The following services use part or all of

3510-582: The Dual Contracts on February 27, 1912, and construction was soon halted on Section 6. The construction of this line, in conjunction with the construction of the Broadway–Seventh Avenue Line , would change the operations of the IRT system. Instead of having trains go via Park Avenue, turning onto 42nd Street, before finally turning onto Broadway, there would be two trunk lines connected by

3627-628: The East River , connecting the New York City boroughs of Manhattan in the west and Brooklyn in the east. Completed in 1908 for the Interborough Rapid Transit Company (IRT), it was the first subway tunnel between the two boroughs, and was built as part of Contract 2 of the first New York City Subway line . The tubes extend between South Ferry in Lower Manhattan and Joralemon Street in Brooklyn Heights , Brooklyn, with

Joralemon Street Tunnel - Misplaced Pages Continue

3744-624: The Horns Rev wind farm in the North Sea west of Denmark utilizes 80 large monopiles of 4 metres diameter sunk 25 meters deep into the seabed, while the Lynn and Inner Dowsing Wind Farm off the coast of England went online in 2008 with over 100 turbines, each mounted on a 4.7-metre-diameter monopile foundation in ocean depths up to 18 metres. The typical construction process for a wind turbine subsea monopile foundation in sand includes driving

3861-529: The IRT 42nd Street Shuttle was formed along the old connection between the sides. Due to the shape of the system, it was referred to as the "H system". The first section of the IRT Pelham Line also opened to Third Avenue–138th Street on August 1, 1918. The cost of the extension from Grand Central was $ 58 million. The construction and opening of the Lexington Avenue Line north of Grand Central resulted in

3978-429: The New York City Subway at Grand Central–42nd Street . The improvements include an underground connection between Grand Central Terminal and One Vanderbilt; new mezzanines and exits for the subway station; and three new stairways to each of the Lexington Avenue Line platforms. This would directly result in additional capacity for the subway station, with 4,000 to 6,000 more subway passengers per hour being able to use

4095-436: The first IRT line in 1900. A 1902 explosion during construction seriously damaged properties just above the line. The part of the line from City Hall to just south of 42nd Street was part of the original IRT line, opened on October 27, 1904. A 0.3 miles (0.48 km) extension to Fulton Street opened at 12:01 a.m. on January 16, 1905. Only the northbound platform opened at this time. The next station, Wall Street ,

4212-404: The mean high water level of the East River, with a maximum gradient of 3.1 percent. During the tunnel's construction, a house at 58 Joralemon Street in Brooklyn was converted into a ventilation building and emergency exit. The Joralemon Street Tunnel was the first underwater subway tunnel connecting Manhattan and Brooklyn. It was built by the IRT as part of Contract 2, which the IRT signed with

4329-646: The 'female' piles hole in order to key 'male' piles between. The male pile is the one where steel reinforcement cages are installed, though in some cases the female piles are also reinforced. Secant piled walls can either be true hard/hard, hard/intermediate (firm), or hard/soft, depending on design requirements. Hard refers to structural concrete and firm or soft is usually a weaker grout mix containing bentonite. All types of wall can be constructed as free standing cantilevers , or may be propped if space and sub-structure design permit. Where party wall agreements allow, ground anchors can be used as tie backs. A slurry wall

4446-717: The Borough Hall station opened to the public on January 9, 1908, with ceremonies, firecrackers, and a musical performance on the steps of Brooklyn Borough Hall . Initially, the tunnel was served by express trains along both the West Side (now the Broadway–Seventh Avenue Line to Van Cortlandt Park–242nd Street ) and East Side (now the Lenox Avenue Line ). The express trains, running to Atlantic Avenue, had their northern terminus at 242nd Street or West Farms ( 180th Street ). Lenox local trains to 145th Street served

4563-505: The Broadway Line station. Two high speed escalators were added to connect the local and express platforms. Two additional high speed escalators were built to connect the local platforms with the new mezzanine. As part of the plan, the local platforms were extended to accommodate 10-car trains. In addition, new entrances and booths were added to the 59th Street ends of the northbound and southbound sides. The project cost $ 6.5 million and

4680-561: The East Side, increased crowding is expected on the Lexington Avenue Line, underscoring the need for the Second Avenue Subway. Crowding on the line is so bad that riders are routinely stranded on the platform, having to wait for multiple trains to pass before being able to board. Trains on the line are at over 100% of capacity. In June and July 2017, The New York Times found that during an average weekday, 10% to 15% of

4797-559: The Financial District. Construction started in 2007, and on January 1, 2017, the first phase, between Lexington Avenue–63rd Street and 96th Street opened. Within a few months of the line's opening, crowding on the Lexington Avenue Line stations on the Upper East Side was somewhat reduced. East Side Access , completed in 2023, brought Long Island Rail Road service into Grand Central. With more people coming onto

Joralemon Street Tunnel - Misplaced Pages Continue

4914-598: The IRT and the BRT. As part of the Dual Contracts, the IRT extended the Lexington Avenue Line north of Grand Central–42nd Street , dividing the original IRT line into an H-shaped system. The "H" system opened in 1918, and all Joralemon Street Tunnel services were sent via the Lexington Avenue Line. The following year, the Clark Street Tunnel opened north of the Joralemon Street Tunnel, providing service from

5031-550: The Joralemon Street Tubes, was manufactured by the American Bridge Company . The tubes are lined with "rings" 22 inches (560 mm) wide, each of which is made of "plates" that form a perfect circle. Each ring has a minimum thickness of 1.125 inches (28.6 mm) and has flanges that are 7 to 7.5 inches (180 to 190 mm) deep. The rings within the rocky sections, and within the segments of

5148-571: The Lexington Avenue Line north of the Grand Central–42nd Street station in mid-2025. The Second Avenue Elevated fully closed on June 13, 1942. Because of the elevated line's closure, as well as a corresponding increase in the East Side population, crowding on the Lexington Avenue Line increased. The Manhattan section of the Third Avenue Elevated , the only other elevated line in the area, closed on May 13, 1955, and

5265-612: The New York Tunnel Company had allowed the quicksand above the tubes to settle, although the contractor denied responsibility. The two sections of the northern tube were holed-through on December 15, 1906, followed by the southern tube on March 1, 1907. Starting in mid-1907, some 1,957 feet (596 m) of the north tube and 962 feet (293 m) of the south tube were reconstructed, with the lower half of each cast-iron ring being replaced with an elliptical section. The New York Tunnel Company became insolvent that May, and

5382-622: The Rapid Transit Commission (RTC). It called for a subway line from New York City Hall in lower Manhattan to the Upper West Side , where two branches would lead north into the Bronx . A plan was formally adopted in 1897. The Rapid Transit Subway Construction Company (RTSCC), organized by John B. McDonald and funded by August Belmont Jr. , signed Contract 1 with the RTC in February 1900, in which it would construct

5499-619: The Rapid Transit Commission in 1902. Construction commenced in 1903 and the tubes were completed by 1907, despite various construction accidents and engineering errors that required part of the tunnel to be rebuilt. The first train ran through the Joralemon Street Tunnel in November 1907, and the tunnel opened for passenger service on January 9, 1908. It was listed on the National Register of Historic Places in 2006. The Joralemon Street Tunnel, consisting of two parallel tubes, crosses

5616-473: The beginning of Metro-North Railroad 's Park Avenue tunnel in Grand Central Terminal forces the Lexington Avenue Line to shift slightly eastward to Lexington Avenue ; its Grand Central–42nd Street station is located on the diagonal between Park and Lexington. Just south of Grand Central, a single non-revenue track connects the IRT 42nd Street Shuttle to the southbound local track; this

5733-509: The binders and refilling them in the desired area. The technique can also be used on lightly contaminated masses as a means of binding contaminants, as opposed to excavating them and transporting to landfill or processing. As the name implies, timber piles are made of wood . Historically, timber has been a plentiful, locally available resource in many areas. Today, timber piles are still more affordable than concrete or steel. Compared to other types of piles (steel or concrete), and depending on

5850-493: The construction of expensive apartments along Park Avenue, Madison Avenue, and Lexington Avenue. In 1928, the New York City Board of Transportation proposed to extend platforms at all stations between Brooklyn Bridge and Grand Central, except for 33rd Street. On April 13, 1948, the platform extensions to accommodate ten-car trains at 23rd Street , 28th Street , and 33rd Street were opened for use. In 1949,

5967-532: The construction of the parallel Second Avenue Subway , which opened in 2017, to relieve congestion on the Lexington Avenue line. Four stations along this line have been abandoned. When platforms were lengthened to fit ten cars, it was deemed most beneficial to close these stations and open new entrances for adjacent stations. The 18th Street station was abandoned because of the proximity to both 14th Street–Union Square and 23rd Street . In addition,

SECTION 50

#1732772645028

6084-470: The dilapidated state of the subway at the time, the Guardian Angels , founded by Curtis Sliwa , began operations on February 13, 1979, by conducting unarmed night patrols on the 4 train in an effort to discourage crime. These patrols later expanded to other parts of the subway and to other city neighborhoods. On August 28, 1991, an accident involving a 4 train on the express track just north of

6201-403: The doors of all eight cars of trains to open on the platform. Work was still underway at two of the other three stations part of the contract, Wall Street and Fulton Street, while work at Bowling Green was already completed. The entire platform-lengthening project was substantially completed by November 1965. Because the Lexington Avenue Line during the 1970s was known to frequent muggers due to

6318-539: The driven depth required was too long for a single pile; today, splicing is common with steel piles, though concrete piles can be spliced with mechanical and other means. Driving piles, as opposed to drilling shafts, is advantageous because the soil displaced by driving the piles compresses the surrounding soil, causing greater friction against the sides of the piles, thus increasing their load-bearing capacity . Driven piles are also considered to be "tested" for weight-bearing ability because of their method of installation; thus

6435-412: The driven pile, and the sand and water are removed from the centre of the pile and replaced with concrete . An additional layer of even larger stone, up to 0.5 m diameter, is applied to the surface of the seabed for longer-term erosion protection. Also called caissons , drilled shafts , drilled piers , cast-in-drilled-hole piles (CIDH piles) or cast-in-situ piles, a borehole is drilled into

6552-458: The excavation proceeds, horizontal timber sheeting (lagging) is inserted behind the H pile flanges. The horizontal earth pressures are concentrated on the soldier piles because of their relative rigidity compared to the lagging. Soil movement and subsidence is minimized by installing the lagging immediately after excavation to avoid soil loss. Lagging can be constructed by timber, precast concrete, shotcrete and steel plates depending on spacing of

6669-402: The express trains and BMT trains to Queens . Even before the express platforms were added, this station was the busiest on the line. Construction for the express station began on August 10, 1959. The two express platforms were 14 feet (4.3 m) wide and 525 feet (160 m) long. Along with the new express platforms, a new mezzanine was built above it to connect it to the local station, and

6786-516: The extension north of 42nd Street was to continue it south through Irving Place and into what is now the BMT Broadway Line at Ninth Street and Broadway . Contracts awarded on July 21, 1911, included Section 6 between 26th Street and 40th Street ; at the time, the IRT had withdrawn from the talks, and the Brooklyn Rapid Transit Company (BRT) was to operate on Lexington Avenue. The IRT submitted an offer for what became its portion of

6903-447: The grade beams, while heavier elements bear directly on the pile cap. A monopile foundation utilizes a single, generally large-diameter, foundation structural element to support all the loads (weight, wind, etc.) of a large above-surface structure. A large number of monopile foundations have been utilized in recent years for economically constructing fixed-bottom offshore wind farms in shallow-water subsea locations. For example,

7020-399: The ground at the building site . There are many reasons that a geotechnical engineer would recommend a deep foundation over a shallow foundation, such as for a skyscraper . Some of the common reasons are very large design loads, a poor soil at shallow depth, or site constraints like property lines . There are different terms used to describe different types of deep foundations including

7137-513: The ground conditions, loading conditions, and nature of the project. Pile depths may vary substantially across a project if the bearing layer is not level. Drilled piles can be tested using a variety of methods to verify the pile integrity during installation. Under-reamed piles have mechanically formed enlarged bases that are as much as 6 m in diameter. The form is that of an inverted cone and can only be formed in stable soils or rocks. The larger base diameter allows greater bearing capacity than

SECTION 60

#1732772645028

7254-413: The ground is continuously frozen , adfreeze piles are used as the primary structural foundation method. Adfreeze piles derive their strength from the bond of the frozen ground around them to the surface of the pile. Adfreeze pile foundations are particularly sensitive in conditions which cause the permafrost to melt. If a building is constructed improperly then it can melt the ground below, resulting in

7371-432: The ground level, and wood beams bearing on the piers are used to support the structure. This type of foundation results in a crawl space underneath the building in which wiring and duct work can be laid during construction or re-modelling. In jet piling high pressure water is used to set piles. High pressure water cuts through soil with a high-pressure jet flow and allows the pile to be fitted. One advantage of Jet Piling:

7488-479: The ground using a pile driver . Driven piles are constructed of wood, reinforced concrete, or steel. Wooden piles are made from the trunks of tall trees. Concrete piles are available in square, octagonal, and round cross-sections (like Franki piles ). They are reinforced with rebar and are often prestressed . Steel piles are either pipe piles or some sort of beam section (like an H-pile). Historically, wood piles used splices to join multiple segments end-to-end when

7605-438: The ground, then concrete (and often some sort of reinforcing) is placed into the borehole to form the pile. Rotary boring techniques allow larger diameter piles than any other piling method and permit pile construction through particularly dense or hard strata. Construction methods depend on the geology of the site; in particular, whether boring is to be undertaken in 'dry' ground conditions or through water-saturated strata. Casing

7722-442: The height may be as short as half the diameter. Clays and muds are easy to penetrate but provide poor holding capacity, so the height may be as much as eight times the diameter. The open nature of gravel means that water would flow through the ground during installation, causing 'piping' flow (where water boils up through weaker paths through the soil). Therefore, suction piles cannot be used in gravel seabeds. In high latitudes where

7839-404: The latter half of the 20th century, several derailments occurred in the Joralemon Street Tunnel. A Brooklyn-bound train derailed during the morning rush hour of January 1, 1965, blocking service for half a day, although no one was harmed. During the evening rush hour of March 17, 1984, another train derailed with 1,500 passengers while traveling over a track that was being repaired, but again, no one

7956-472: The line's signal system and interlockings were modernized. Work on the reconstruction of the Brooklyn Bridge station started on May 18, 1959, and continued without interruption until it was completed on September 1, 1962. Prior to the rebuild, the station's local platform could only accommodate four cars, resulting in delays. The uptown platform's extension opened at this time (the downtown platform

8073-568: The line, north to 125th Street, opened on July 17, 1918. However, until the evening of August 1, 1918, it ran as a shuttle on the local tracks only, terminating at 42nd Street and at 167th Street on the IRT Jerome Avenue Line (where the connection from the elevated IRT Ninth Avenue Line merged). On August 1, service patterns were changed, and the Lexington Avenue Line became a through route. The IRT Broadway–Seventh Avenue Line also switched from shuttle operation at that time, and

8190-480: The line. Both of these elevated lines were supposed to be replaced by a subway line under Second Avenue. However, it was not completed due to a lack of funds. With the city's economic and budgetary recovery in the 1990s, there was a revival of efforts to complete construction of the Second Avenue Subway . Once fully built, the line will run from 125th Street and Lexington Avenue to Hanover Square in

8307-588: The line: The Lexington Avenue Line begins in lower Manhattan at the inner loop of the abandoned South Ferry station. North of the station is a merge with the tracks of the Joralemon Street Tunnel from Brooklyn , which become the express tracks. These run north under Broadway and Park Row to Centre Street. At the south end of Centre Street, directly under New York City Hall , is the City Hall Loop and its abandoned station, which

8424-457: The load to the soil and is sized accordingly. Suction piles are used underwater to secure floating platforms. Tubular piles are driven into the seabed (or more commonly dropped a few metres into a soft seabed) and then a pump sucks water out at the top of the tubular, pulling the pile further down. The proportions of the pile (diameter to height) are dependent upon the soil type. Sand is difficult to penetrate but provides good holding capacity, so

8541-618: The lower level by southbound trains. This is because Lexington Avenue is too narrow to have a four-across layout. North of this, the line crosses under the Harlem River into the Bronx via the four-track Lexington Avenue Tunnel, where the line splits into the IRT Jerome Avenue Line on the western two tracks ( 4 and ​ 5 trains) and the IRT Pelham Line on the eastern two tracks ( 6 and <6> ​ trains). Construction started on

8658-545: The motto of the Pile Driving Contractors' Association is "A Driven Pile...Is a Tested Pile!". Foundations relying on driven piles often have groups of piles connected by a pile cap (a large concrete block into which the heads of the piles are embedded) to distribute loads that are greater than one pile can bear. Pile caps and isolated piles are typically connected with grade beams to tie the foundation elements together; lighter structural elements bear on

8775-603: The newly extended Broadway–Seventh Avenue Line to the IRT's Brooklyn line. Another tunnel, the Montague Street Tunnel , was built north of the Joralemon Street Tunnel as part of the Dual Contracts, opening in 1920 as part of the BRT system. Also in 1920, the Eastern Parkway Line was extended east of Atlantic Avenue; the Joralemon Street Tunnel services, which had previously served all stops on the Eastern Parkway Line, became express services. In

8892-473: The pile (which is analogous to a pole), the pier (which is analogous to a column ), drilled shafts, and caissons . Piles are generally driven into the ground in situ ; other deep foundations are typically put in place using excavation and drilling. The naming conventions may vary between engineering disciplines and firms. Deep foundations can be made out of timber , steel , reinforced concrete or prestressed concrete . Prefabricated piles are driven into

9009-463: The platform extensions, and, as such, the station was renamed Brooklyn Bridge–Worth Street. In late 1959, contracts were awarded to extend the platforms at Bowling Green, Wall Street, Fulton Street, Canal Street, Spring Street, Bleecker Street, Astor Place, Grand Central, 86th Street and 125th Street to 525 feet (160 m) to accommodate ten-car trains. At the same time, work to modernize the signals and interlockings between Wall Street and 86th Street

9126-408: The project was estimated to cost $ 10 million (equivalent to $ 272 million in 2023) by November 1903. Construction shafts were dug at South Ferry and Joralemon Street. Six tunneling shields were driven: two proceeding east from Manhattan and two each proceeding west and east from Brooklyn. The tunneling shields were each 16.95 feet (5 m) in diameter and 9.5 feet (2.9 m) long, and were pushed at

9243-470: The radial arm would lift and orient a plate into position. Three workers would bolt the plates to the already assembled lining, while a fourth would operate the device. Afterward, a compressed-air grouting machine would squeeze grout into small holes within the lining, filling the spaces between the rock and the cast-iron rings. The holes in the lining were then plugged. Some of the cast-iron plates were cracked while they were placed, but Parsons maintained that

9360-482: The route of the tunnel curving at either bank of the river. The primary engineer for the tunnel was William Barclay Parsons , who designed most of the early IRT system, while Clifford Milburn Holland served as the assistant engineer. The New York Tunnel Company was the primary contractor. When completed, it was known as the Brooklyn–Battery Tunnel, a name subsequently used for a vehicular tunnel slightly to

9477-429: The soil to increase bearing capacity. The result is not as solid as concrete, but should be seen as an improvement of the bearing capacity of the original soil. The technique is most often applied on clays or organic soils like peat . The mixing can be carried out by pumping the binder into the soil whilst mixing it with a device normally mounted on an excavator or by excavating the masses, mixing them separately with

9594-421: The soldier piles and the type of soils. Soldier piles are most suitable in conditions where well constructed walls will not result in subsidence such as over-consolidated clays, soils above the water table if they have some cohesion, and free draining soils which can be effectively dewatered, like sands. Unsuitable soils include soft clays and weak running soils that allow large movements such as loose sands. It

9711-446: The source/type of timber, timber piles may not be suitable for heavier loads. A main consideration regarding timber piles is that they should be protected from rotting above groundwater level. Timber will last for a long time below the groundwater level. For timber to rot, two elements are needed: water and oxygen. Below the groundwater level, dissolved oxygen is lacking even though there is ample water. Hence, timber tends to last for

9828-420: The south. Each tube is approximately 6,550 feet (2,000 m) long, with the sections under the river being 4,500 feet (1,400 m) long. The tunnels have an outside diameter of 16.67 feet (5.1 m) and an inside diameter of 15.5 feet (4.7 m). The centers of the tubes were placed about 28 feet (8.5 m) apart, except under Joralemon Street, where that distance is 26 feet (7.9 m). Both tubes have

9945-534: The southbound platforms at Astor Place, Bleecker Street, Spring Street, Canal Street, and Worth Street were extended. In 1957, the New York City Transit Authority started work on a $ 138 million modernization program for the Lexington Avenue Line to improve and speed up service. As part of the project, platforms on the line were extended, express platforms were built at 59th Street, additional entrances were constructed at some stations, and

10062-632: The station construction, 40% of the basement of the Grand Hyatt New York would be destroyed in order to make room for the expansion of the subway mezzanine, as well as two new subway entrances in the One Vanderbilt building itself. The new building would also coincide with the MTA 's East Side Access project, and station improvements due to One Vanderbilt's construction would provide extra capacity for over 65,000 new passengers going into

10179-435: The station, allowing for one additional express train per hour. These improvements would cost over $ 200 million. Pilings A deep foundation is a type of foundation that transfers building loads to the earth farther down from the surface than a shallow foundation does to a subsurface layer or a range of depths. A pile or piling is a vertical structural element of a deep foundation, driven or drilled deep into

10296-498: The station, which were used for express service, to be abandoned. These platform extensions had necessitated the use of gap fillers. This project cost $ 6 million, and allowed 6 trains to be lengthened to nine cars, and allowed express trains to open all doors at the station (previously the doors only opened in eight of the ten cars). Upon its completion, the Worth Street station to the north was closed due to its close proximity to

10413-635: The subway and maintain a 50-year operating lease from the opening of the line. Belmont incorporated the IRT in April 1902 to operate the subway. A subway under the southernmost section of Broadway between the Battery and City Hall was not included in Contract 1. Several days after Contract 1 was signed, the Board of Rapid Transit Railroad Commissioners instructed Parsons to evaluate the feasibility of extending

10530-485: The subway south to South Ferry and then to Brooklyn. On January 24, 1901, the Board adopted a route that would extend the subway from City Hall to the Long Island Rail Road (LIRR)'s Flatbush Avenue terminal station (now known as Atlantic Terminal) in Brooklyn, via a tunnel under the East River, then running under Joralemon Street, Fulton Street , and Flatbush Avenue in Brooklyn to Atlantic Terminal. It

10647-564: The system's busiest routes. The tunnel reopened within the week. The tunnels were more extensively repaired during 2016 and 2017 for $ 75 million. The MTA announced in 2024 that it would begin installing 5G cellular equipment in the Joralemon Street Tunnel. IRT Lexington Avenue Line The IRT Lexington Avenue Line (also known as the IRT East Side Line and the IRT Lexington–Fourth Avenue Line )

10764-498: The trains scheduled to run through Grand Central–42nd Street were canceled. This meant that during peak periods, up to 13 trains per hour could be canceled, resulting in 1,000 passengers being displaced for every canceled train. Train frequencies were also erratic, with higher frequencies on some days than on others. On May 27, 2015, the New York City Council approved plans for a developer to build One Vanderbilt ,

10881-448: The tubes into fixed blocks ; only one train at a time could occupy each block. Trains traveled through the tunnel at up to 60 miles per hour (97 km/h), requiring blocks of up to 2,400 feet (730 m). The placement of each signal was determined by the grade of each tube. Trains could run through either tube in both directions if the other tube was closed for maintenance. The signal apparatuses were powered by batteries at either end of

10998-462: The tubes were safe. The excavations caused shifting of sandy soil, which damaged some buildings in Brooklyn along the tunnel's route, including the house of the Brooklyn borough president. In June 1904, the RTC said the city was not responsible for repairs to the houses, although contractors were digging another shaft to relieve air pressure in the excavation. The shafts at Garden Place and at Henry Street were sealed, and new shafts at Furman Street on

11115-405: The tunnel above mean high water, generally weigh less than those placed within sandy ground or underneath the riverbed. After the rings were placed, they were covered with concrete, and bench walls with cable ducts were placed aside each tube. Piping and drainage systems were also installed. Pilings were sunk for additional reinforcement. When the tubes opened, there were 18 signals, which divided

11232-628: The tunnel during late nights. In Brooklyn, service proceeded beneath Joralemon, Fulton, and Willoughby Streets, originally terminating at Atlantic Avenue. The opening of the Joralemon Street Tunnel, as well as the completion of the Williamsburg Bridge and Manhattan Bridge to the north, relieved traffic from the Brooklyn Bridge and from East River ferries, which previously had provided the only passenger service between Manhattan and Brooklyn. The Dual Contracts were formalized in early 1913, specifying new lines or expansions to be built by

11349-493: The tunnel to cave-in at the Battery, though no one died. A cave-in occurred in one of the tubes in August 1906, and two months later, another blast killed one worker. Another issue was the need to create a new ventilation shaft on the Brooklyn side after the construction shaft was sealed; the IRT unsuccessfully attempted to take property on Hicks and Furman Streets. By 1907, the IRT had bought a house at 58 Joralemon Street to serve as

11466-619: The tunnel. The Manhattan end of the tunnel is the Bowling Green station of the IRT Lexington Avenue Line . North of Bowling Green, the subway runs under Broadway to connect to the original subway line. The Brooklyn end is at Joralemon and Clinton Streets in Brooklyn, where a cut-and-cover tunnel connects to the Borough Hall station of the IRT Eastern Parkway Line . Two construction shafts were built for

11583-479: The tunnel: one in Manhattan at South Ferry, and the other in Brooklyn at Henry and Joralemon Streets. Each shaft was built with dimensions of about 14 by 45 feet (4.3 by 13.7 m). The South Ferry construction shaft became a ventilation shaft and consists of a 10-foot-high (3.0 m) enclosure inside the Battery. However, the Henry Street construction shaft was infilled. A ventilation and emergency exit shaft

11700-431: The tunnels in Brooklyn had descended beneath the specified gradient, which if uncorrected would result in an uneven grade. These difficulties had come to the attention of mayor George B. McClellan Jr. by mid-1906. To prevent further delays, contractor New York Tunnel Company chose to proceed, with plans to rebuild the defective tunnel sections later. Parsons blamed the contractor for the defective tube ceilings, stating that

11817-486: The type of equipment used to install these elements, they are often used where access restrictions and or very difficult ground conditions (cobbles and boulders, construction debris, karst, environmental sensitivity) exists or to retrofit existing structures.  Occasionally, in difficult ground, they are used for new construction foundation elements. Typical applications include underpinning , bridge , transmission tower and slope stabilization projects. The use of

11934-498: The ventilation plant. Continuing with the excavations, the contractors found the remains of a ship under Joralemon Street in March 1905. By that August, the excavations had reached the midpoint of the riverbed. During this time, Parsons and his successor George S. Rice discovered that the ceilings of the tubes had flattened downward; trains could still run through the tunnels, but the roofs would be scraped at high speeds. Less urgently,

12051-626: The water jet lubricates the pile and softens the ground. The method is in use in Norway. Micropiles are small diameter, generally less than 300mm diameter, elements that are drilled and grouted in place.  They typically get their capacity from skin friction along the sides of the element, but can be end bearing in hard rock as well. Micropiles are usually heavily reinforced with steel comprising more than 40% of their cross section. They can be used as direct structural support or as ground reinforcement elements.  Due to their relatively high cost and

12168-475: The waterfront were being constructed, by the end of 1904. The property damage led the New York City government to pay out monetary compensation starting in mid-1906. Numerous other accidents occurred during the course of construction. In March 1905, one of the tubes suddenly lost pressure in a "blowout", propelling a worker through the mud and into the air, although he survived. That December, a blast caused

12285-439: Was an extension of the Interborough Rapid Transit Company (IRT)'s first subway line from the Bowling Green station in Manhattan to the IRT Eastern Parkway Line in Brooklyn. The tubes were constructed using the shield method and are each 6,550 feet (2,000 m) long and 15.5 feet (4.7 m) wide. The interiors are lined with cast-iron "rings" formed with concrete. The tubes descend 91 to 95 feet (28 to 29 m) below

12402-562: Was built inside a row house at 58 Joralemon Street , near Willow Street. 58 Joralemon Street was an actual house, built in 1847, but was purchased by the IRT in 1907 and gutted. Planning for the city's first subway line dates to the Rapid Transit Act, authorized by the New York State Legislature in 1894. The subway plans were drawn up by a team of engineers led by William Barclay Parsons, chief engineer of

12519-532: Was completed three months prior than originally planned when the new platforms opened on November 15, 1962. In April 1960, work began on a $ 3,509,000 project to lengthen platforms on the line to accommodate ten-car trains at seven stations on the line. As part of the project, the northbound platforms at Canal Street, Spring Street, Bleecker Street, and Astor Place were lengthened from 225 feet (69 m) to 525 feet (160 m). The platform extensions at these four stops opened for service on February 19, 1962, enabling

12636-427: Was demolished in 1956. Contrary to what many East Side residents thought, the demolition of the elevateds did not help the travel situation, as the Lexington Avenue Line was now the only subway transportation option on the East Side. As the elevated lines were torn down, hundreds of high-rise apartment buildings were built on the East Side, and the business districts along the line grew, resulting in overcrowding along

12753-491: Was estimated that this second route would cost $ 9 million (equivalent to $ 263 million in 2023), which the RTC could not yet fully fund. However, the RTC expected that there would be competition for the route, which connected two large business districts and the city's two most populous boroughs. The Brooklyn Rapid Transit Company , which monopolized surface and elevated transit in Brooklyn, would be obliged to bid to maintain its monopoly. The Board also knew that Belmont would submit

12870-439: Was killed or seriously injured. The Joralemon Street Tunnel was added to the National Register of Historic Places in 2006. It was one of seven East River subway tunnels flooded on October 29, 2012, as Hurricane Sandy 's storm surge inundated Lower Manhattan. The Metropolitan Transportation Authority (MTA) prioritized draining and restoring service to the Joralemon Street Tunnel and Rutgers Street Tunnel , which carried some of

12987-426: Was lengthened in 1961) as the platforms were lengthened, widened, and straightened. Originally, the island platforms narrowed at their northern ends to an unsafe width of only five feet. The project remedied this situation, lengthening the platforms from 295 feet (90 m) to 523 feet (159 m) and widening them. The platforms were extended northward by 220 feet (67 m) to just south of Reade Street. In addition,

13104-461: Was opened between 1904 and 1908, and is part of the first subway line in the city . The original subway turned west across 42nd Street at the Grand Central station, then went north at Broadway , serving the present-day IRT Broadway–Seventh Avenue Line . The second portion of the line, north of 42nd Street, was constructed as part of the Dual Contracts , which were signed between the IRT;

13221-562: Was opened on June 12, 1905, as well as the southbound platform at Fulton Street. The first revenue train on the South Ferry extension left South Ferry at 11:59 p.m. on July 9, 1905; the extension of the IRT White Plains Road Line to West Farms opened just after. The first train ran through the Joralemon Street Tunnel to Brooklyn about 12:45 a.m. on January 9, 1908. The original plan for what became

13338-418: Was part of the original IRT subway alignment. Under Lexington Avenue, the line assumes a two-over-two track configuration, with the local tracks running on the upper level and the express on the lower, although it briefly returns to a four-across layout between 96th Street and 116th Street . 125th Street returns to this two-over-two layout, although here the upper level is used by all northbound trains and

13455-429: Was performed by three groups of men, each working eight-hour shifts. After the shields were driven, temporary wooden beams were placed to reinforce the excavations until the cast-iron tubes were assembled. The cast iron lining was assembled via a hydraulically powered, traveling device with a "radial arm"; the device was supported on brackets that ran along the completed section of the lining. Once it had been positioned,

13572-455: Was the southern terminus of the original IRT subway line. The loop is still used to turn 6 and <6> service; the Lexington Avenue local tracks, which feed the loop, rise up to join the express tracks just south of Brooklyn Bridge–City Hall station. From Brooklyn Bridge, the line continues northward in a four-across track layout under Centre Street, Lafayette Street, Fourth Avenue, and Park Avenue South until 42nd Street . At this point,

13689-537: Was underway. Another element of the modernization plan was the construction of a new station entrance and control building in Bowling Green Park at Bowling Green, with new stairways to the platform. On July 23, 1959, the Board of Estimate approved the contract for the construction of express platforms at Lexington Avenue–59th Street . The new platforms were intended to reduce transfer congestion at Grand Central–42nd Street , and to allow transfers between

#27972