In civil engineering (more specifically highway engineering ), grade separation is a method of aligning a junction of two or more surface transport axes at different heights (grades) so that they will not disrupt the traffic flow on other transit routes when they cross each other. The composition of such transport axes does not have to be uniform; it can consist of a mixture of roads , footpaths , railways , canals , or airport runways . Bridges (or overpasses , also called flyovers), tunnels (or underpasses ), or a combination of both can be built at a junction to achieve the needed grade separation.

#913086

125-707: The Mumbai Trans Harbour Link , officially named as Atal Bihari Vajpayee Sewri–Nhava Sheva Atal Setu and colloquially known as Atal Setu , is a 21.8 km (13.5 mi) 6-lane grade separated expressway bridge, which connects Mumbai with Navi Mumbai , its satellite city . It is the longest sea bridge in India, and the world's 12th longest sea bridge . The bridge begins in Sewri , South Mumbai , crosses Thane Creek north of Elephanta Island , and terminates at Chirle near Nhava Sheva in Uran taluka , Navi Mumbai. The road

250-488: A 10.38-kilometre-long (6.45 mi) bridge section across the Mumbai Bay and Sewri interchange ( ₹ 6,600 crore), a 7.807-kilometre-long (4.851 mi) bridge section across Mumbai Bay and Shivaji Nagar, near Gavan interchange ( ₹ 4,900 crore), and a 3.613-kilometre-long (2.245 mi) viaduct including interchanges at SH-52, SH-54, and NH-4B near Chirle , Navi Mumbai. The MMRDA received 11 pre-qualification bids each for

375-612: A 6 km section of the MTHL. The vision barriers are intended to block the view of the Bhabha Atomic Research Centre (BARC) from the MTHL, while the noise barriers are intended to protect the movement of flamingos and migratory birds at the Sewri mudflats. The MMRDA also stated that it would declare nearly 2 km of the MTHL on the Sewri side as a "silent zone", as well as near schools and other sensitive areas on

500-592: A cement and concrete bridge. The use of steel on this stretch will raise the project cost by ₹ 4000 crores. JICA formally approved the funding agreement on 9 May 2016, and the MMRDA began the bidding process the following day. The MTHL received final environment clearance from the State Forest Department in May 2017. The MMRDA invited request for qualifications (RFQ) for civil construction of three packages –

625-416: A highway) that they cross. However, grade-separated pedestrian crossings with steps introduce accessibility problems. Some crossings have lifts , but these can be time-consuming to use. Grade-separated roads that permit for higher speed limits can actually reduce safety due to 'weaving' (see below) as well as a perceived sense of safety. The term is most widely applied to describe a road junction in which

750-554: A long way from completion. In June 2021, the MMRDA stated that it was re-examining the possibility of building metro lines on the MTHL. An official stated that there would be no need for extra construction on the MTHL for the metro line, as only the tracks would have to be added. Already, the Worli–Sewri underground metro corridor, as part of the Line 3 (Aqua Line) of Mumbai Metro , is being constructed. The Sewri metro station will connect

875-450: A mobile gantry. The foundations for the MTHL are 47 metres at its deepest points, in order to support the weight of the bridge. An automated girder launching system was utilized to lay the bridge's foundation, marking the first time the system was used in India. The Reverse Circulation Drilling (RCD) construction technique was also utilized for the first time in India, in order to reduce disturbance to migratory birds. The MMRDA estimated that

1000-414: A partial grade separation will accomplish more improvement than for a road), and because at-grade railway connections often take up significant space on their own. However, they require significant engineering effort, and are very expensive and time-consuming to construct. Grade-separated pedestrian and cycling routes often require modest space since they do not typically intersect with the facility (such as

1125-414: A precision band of 5 mm. The barge used to transport the decks was specifically built for the MTHL project by Larsen & Toubro at its Kattupalli Shipyard . The concrete section of the bridge is made up over 12,000 concrete boxes that were pre-cast in a casting yard. The concrete segments were joined to form 60 metre-long spans, and the concrete spans were then installed on the bridge's pillars using

1250-465: A result of the COVID-19 pandemic. The MMRDA stated that it had completed 76% of the total project work on 11 April 2022. On 15 September 2022, Chief Minister of Maharashtra, Eknath Shinde, stated that 84% of the total project work had been completed. The longest orthotropic deck, measuring 180 metres long and weighing 2,400 MT, was launched on 2 November 2022. Installation of vehicle crash barriers on

1375-560: A road bridge. An MMRDA official stated that a detailed study has revealed that laying the foundation for the bridge with provisions for two metro lines would hike costs, instead of saving expenses. Hence, it would be feasible to have a separate bridge for the metro in the future. Another reason given was that the Navi Mumbai International Airport and Sewri-Prabhadevi corridor of the Mumbai Metro were still

SECTION 10

#1732787321914

1500-615: A shortfall loan to be made available from the central government if traffic is 20% under the estimate. The MMRDA decided to scrap the PPP model for the project in August 2013, and instead execute it on an engineering, procurement, and construction (EPC) basis. Subsequently, the Japan International Cooperation Agency (JICA) expressed interest in providing funds for the project. In January 2014, Ashwini Bhide,

1625-422: A specialised asphalt binder. SMA increases the pavement life by 20–30% because of its high resistance to variations in temperature, better adhesion between the stone aggregate and bitumen , reduces traffic noise, has high skid resistance and enhances road surface marking visibility. The surface will remain completely smooth and intact, irrespective of weather conditions. The SMA pavements will be 100% recyclable at

1750-413: A speed limit of 100 km/h (62 mph) to prevent fatalities. Furthermore, stopping on the bridge is prohibited, with the exception of emergencies, breakdowns, or when pulled over by law enforcement. The structural steel used in the bridge is about 120,000 tonnes, enough to support the erection of four Howrah Bridges . More than 830,000 cubic metres of concrete has been used to cast the structures of

1875-419: Is fully grade-separated, i.e. traffic on one road does not have to stop at yield lines or signals on one road, but may have to do so when switching to the other: On roadways with grade-separated interchanges, weaving is a result of placing an exit ramp a short distance after an entry ramp, causing conflicts between traffic attempting to leave the roadway at the next junction and traffic attempting to enter from

2000-730: Is known as a flying junction and one which is not a level junction . In 1897, the London and South Western Railway (LSWR) made use of a flying junction at Worting Junction south of Basingstoke to allow traffic on the Salisbury and Southampton routes to converge without conflicting movements; this became known as "Battledown Flyover". Also in Britain, the Southern Railway later made extensive use of flying junctions on other parts of its busy former LSWR main line. Today in Britain,

2125-608: Is linked to the Mumbai–Pune Expressway in the east and to the Coastal Road in the west. The 6-lane highway is 27 meters in width, in addition to two emergency exit lanes, two edge strips, parallel crash barriers and noise barriers on both sides. The project costs a total of ₹ 17,843 crore (US$ 2.1 billion). The bridge has a capacity to handle 70,000 vehicles per day. Construction on the bridge began in April 2018, and

2250-522: Is located 20 minutes away from Chembur a suburban area in Mumbai and is easily accessible by both road and railways. Vashi also is a terminal railway station for Harbour Line & Trans-Harbour Line . Vashi is well known for it cosmopolitan culture & educational institutes. Turbhe also houses an Agricultural Produce Market Committee (APMC) market where all the grocery items, food items, Rice, Lentils, Wheet, and different types of Spices are sold at

2375-632: Is named after the largest village Vashi Gaon present in Vashi Node. Vashi is well-connected node of Navi Mumbai. It is also the first Navi Mumbai station after Mankhurd which is the last station of Mumbai Suburban city. Vashi is a well-organised sub-urban area that houses many commercial stores and has many residential societies. Vashi has three main and large malls, viz., Inorbit mall Vashi , Center One and Raghuleela Mall . Along with these three malls several other small shopping plazas are also developed across vashi, e.g. Satra Plaza, Vashi Plaza. Vashi

2500-817: Is why speed limits are typically higher for grade-separated roads. In addition, reducing the complexity of traffic movements reduces the risk of accidents . Grade-separated road junctions are typically space-intensive, complicated, and costly, due to the need for large physical structures such as tunnels, ramps, and bridges. Their height can be obtrusive, and this, combined with the large traffic volumes that grade-separated roads attract, tend to make them unpopular to nearby landowners and residents. For these reasons, proposals for new grade-separated roads can receive significant public opposition. Rail-over-rail grade separations take up less space than road grade separations: because shoulders are not needed, there are generally fewer branches and side road connections to accommodate (because

2625-715: The Bandra–Worli Sea Link , Coastal Road and the Eastern Freeway , due to safety considerations, two-wheelers and three-wheelers are prohibited from entering the Trans Harbor Link, along with animal-drawn carriages and slow-moving vehicles. Although pedal and electric bicycles are prohibited as well, there are no signages or written warnings to enforce the ban, though riders can be penalized by law enforcement despite no provisions under Motor Vehicles Act . The traffic division of Mumbai Police has mandated

SECTION 20

#1732787321914

2750-416: The Eastern Freeway , the at-grade Messant Road, and the proposed Sewri–Worli elevated road. The Sewri–Worli elevated road will provide onward connectivity to the Coastal Road (at Worli Seaface), Rafi Ahmed Kidwai Marg , and Acharya Donde Marg. The Sewri–Worli connector, also called Sewri–Worli elevated corridor (SWEC), will connect the Bandra–Worli Sea Link and the under-construction Coastal Road with

2875-526: The Great Central Railway , built between 1896 and 1899, was the first fully grade-separated railway of this type in the UK. This also applies to light rail and even to street cars . Attempts have been made to increase the capacity of railways by making tracks cross in a grade-separated manner, as opposed to the traditional use of flat crossings to change tracks. A grade-separated rail interchange

3000-507: The Ministry of Environment, Forest and Climate Change (MoEFCC) on 23 October 2012. The Maharashtra State Road Development Corporation (MSRDC) had obtained clearance for the project in March 2005, but the certificate was valid only for 5 years and lapsed due to the delays in the bidding process. The ministry laid down 11 conditions that the MMRDA had to follow. Some of the conditions were that

3125-519: The Navi Mumbai International Airport project. Three hundred and twenty structures in Sewri were affected by the project, of which 250 properties were residential. The MMRDA provided resettlement for the affected people by offering accommodation in either Kanjurmarg or Kurla . The majority chose to relocate to Kanjurmarg. The MMRDA also paid ₹ 6 lakh (US$ 7,200) each as compensation to 1,500 fishermen who were affected by

3250-459: The Thane Creek , but, they are too narrow and outdated to handle future traffic. As a result, all of them are constrained and are carrying traffic beyond their limits, also increasing the commute time between the two cities. So, the MMRDA planned to build a comprehensive link between the two cities so to handle more traffic and make travel more easier, faster, safer and hassle-free. The proposal

3375-656: The 1860s, subways are far more common today in Europe, especially in countries such as the Netherlands and Denmark where cycling is strongly encouraged. Long underpasses may be called tunnels . Vashi Vashi (Pronunciation: [ʋaːʃiː] ) is an upmarket residential and commercial node in Navi Mumbai, Maharashtra , across the Thane Creek of the Arabian Sea on the outskirts of city of Mumbai . Vashi

3500-540: The 2017–18 fiscal. The MMRDA stated that it had spent ₹ 135.6 crore (US$ 16 million) to reduce the environmental impact of the MTHL construction in August 2021. Prior to the submission of bids for the project, the MMRDA estimated the project cost at ₹ 14,137 crore (US$ 1.7 billion). The actual contract for the project was awarded to three bidders at a combined cost of ₹ 14,262 crore (US$ 1.7 billion) in November 2017. MMRDA officials stated that they expected

3625-565: The 7.807 km package 2 was signed with Daewoo and Tata Projects at a cost of ₹ 5,612.61 crore (US$ 670 million) at a later date. The MMRDA invited bids for Package 4 in September 2021. The tender includes the design, supply, installation, testing, and commissioning of an intelligent transport system , toll management, highway and bridge street lighting, electrical works, construction of toll plazas, and administrative buildings. The ₹ 427 crore (US$ 51 million) contract for Package 4

3750-583: The A4/M5 junction west of Bristol . Weaving can often cause side-on collisions on very fast roads with top speeds of up to 200 kilometres per hour, as well as the problem of blind spots. Where junctions have unusual designs weaving can be a problem other than on the main road. An example of this can be found at Junction 7 of the M6, where traffic joining the roundabout from the M6 Eastbound off-slip must weave with

3875-674: The Advanced Traffic Management System (ATMS), which is a centralised system that allows operators to monitor and manage traffic, incidents and emergency responses in real-time. Along with this, the Intelligent Transportation Management System (ITMS) is also present to systematically work with the ATMS together. This has given the bridge an international recognition for having advanced systems to manage traffic. Similar to

Mumbai Trans Harbour Link - Misplaced Pages Continue

4000-458: The Eastbound off-slip must leave. Weaving can be alleviated by using collector/distributor roads or braided ramps to separate entering and exiting traffic. In railway construction, grade separation also means the avoidance of level crossings by making any roads or footpaths crossing the line either pass under or over the railway on bridges . This greatly improves safety and is crucial to

4125-428: The MMRDA announced that it would provide a one-time payment of ₹ 5.68 lakh (US$ 6,800) to each fisherman affected by the project. The agency received over 3,000 claims for compensation, and it awarded payments to genuine claimants after screening the claims. The MMRDA paid a total compensation of ₹ 380 crore (US$ 46 million) to fishermen affected by the project throughout the construction period. JICA funded 85% of

4250-491: The MMRDA had to put up noise barriers, replant five times the number of mangroves destroyed, not carry out dredging or reclamation, use construction equipment with exhaust silencers and work in consultation with the Bombay Natural History Society to minimize the impact on migratory birds. Environmental activists were opposed to the clearance. They pointed out that there was no public hearing following

4375-544: The MMRDA refused the MSRDC's request to allocate funds for the expansion of the Vashi Bridge, as the former believed that the expansion would divert some ridership from the MTHL. The MMRDA appointed Arup Consultancy Engineers and KPMG to conduct the techno-economic feasibility study of the MTHL in August 2011. The MTHL project was proposed as a public–private partnership (PPP) model. The project received clearance from

4500-399: The MMRDA wanted a higher rate as they claimed the project was very risky. An internal rate of return of 17% was agreed upon. The termination clause in the concession agreement comes into effect after 30 years into the concession period. The MMRDA can invoke the clause based on certain conditions, such as the capacity being higher than expected. The conditions will be reviewed in the 20th year of

4625-481: The MTHL began on 26 December 2022. The barriers have a total height of 1,550 mm including a 900 mm concrete block with a 650 mm high steel rail. The barriers comply with the International Standard EN 1317 certification for road restraint systems. The MMRDA originally planned to install a 5 ft-tall wall as the crash barrier, but decided against it to avoid blocking the views from

4750-444: The MTHL is 110 meters long. The MMRDA chose to use steel spans in these sections to eliminate the need to construct pillars to support the bridge, which would hinder the movement of ships in the area. Only about 3% of the bridge structure was built on-site including the foundations and pouring cement over metal girders. The rest of the bridge was pre-fabricated and then transported to the construction site for installation. The parts for

4875-704: The MTHL project. According to Fadnavis, the CCCC will complete the project within 3–4 years of being appointed and will also provide 2% concessional funding for the project. In November 2015, the project was cleared by the Maharashtra Coastal Zone Management Authority (MCZMA). In January 2016, the Forest Advisory Committee (FAC) granted forest clearance, and the Experts' Appraisal Committee (EAC) attached to

5000-468: The MTHL through access paths, thereby linking it to Navi Mumbai. In September 2021, the MMRDA stated that regardless of the decision on metro lines, the agency would dedicate two lanes on the MTHL for a bus rapid transit system. The agency appointed a consultant to determine whether metro lines could be constructed on the MTHL in January 2022. The draft report of the study submitted in April 2022 found that

5125-540: The MTHL through the planned Ulwe Coastal Road. Once the planned road is constructed, it will join this interchange at Shivajinagar. Grade separation In North America, a grade-separated junction may be referred to as a grade separation or as an interchange – in contrast with an intersection , at-grade , a diamond crossing or a level crossing , which are not grade-separated. Roads with grade separation generally allow traffic to move freely, with fewer interruptions, and at higher overall speeds; this

Mumbai Trans Harbour Link - Misplaced Pages Continue

5250-452: The MTHL was built at Sewri on 18 May 2019. The MMRDA stated that it had begun pre-segment casting work, a precursor to the superstructure for bridge deck construction, on 7 August. Each segment of the viaduct weighs 75 tonnes with dimensions 14.8m x 3.32m x 3.85m. Over 10,000 such segments have been cast. The segments were built at two precast segment yards, one on the Mumbai side and another on

5375-411: The MTHL's existing pillars would not be able to support the load of a metro system. The then Metropolitan Commissioner of the MMRDA, S.V.R. Srinivas, stated that the agency was exploring solutions, such as increasing the load bearing capacity of the pillars, before making a final decision. The MTHL is 21.8 km long, including 16.5 km sea bridge and 5.5 km of viaducts on land on either end of

5500-690: The MTHL. It will be a four-lane, 17 metre-wide and 4.512 km-long cable-stayed bridge, with a height of 27 metres. The Sewri–Worli connector will begin at Sewri (East), and cross the Eastern Freeway, the Harbour Line , Rafi Ahmed Kidwai Marg, Acharya Donde Marg, the existing flyover at Ambedkar Road , Elphinstone Bridge in Parel , and the flyover at Senapati Bapat Marg before passing through Kamgar Nagar and Dr. Annie Besant Road, and terminating at Narayan Hardikar Marg at Worli. Ramps will connect

5625-420: The MTHL. The DEA recommended granting ₹ 1,920 crore (US$ 230 million) with a concession period of 35 years for the project. In the first meeting, between MMRDA and DEA officials in September 2012, the ministry had asked the authority to treat the sea link as a road and reduce the proposed concession period from 45 years to 30 years. They also expected an internal rate of return of 15% for the project. However,

5750-439: The MTHL. The drones were fitted with 360 degrees cameras that provide up to 3 mm accuracy. The aerial survey takes less time than a regular survey, achieves greater accuracy and helps protect against false claims for compensation. Over 1,000 boreholes were drilled to study the strata. The MMRDA began conducting a geological survey for the project on 15 January 2018. The project work affected 1,635 trees, of which 753 were cut and

5875-484: The MoEFCC granted CRZ clearance to the project. The CRZ came with a rider requiring the MMRDA to spend at least ₹ 335 crore towards an "environment management programme". In the same month, Fadnavis announced that the project had received all required clearances. In February 2016, JICA agreed to loan 80% of the total cost of the project to the state government at an annual interest rate of 1–1.4%. The MMRDA will bear 1.2% of

6000-470: The MoEFCC withheld its clearance for the project, stating that it would affect the existing mangroves as well as the flamingo population. The project require clearance from the ministry as it will affect 38 hectares of protected mangrove forests and 8.8 hectares of forest land on the Navi Mumbai end. The sea link's starting point poses a threat to an estimated 20,000–30,000 lesser and greater flamingos and

6125-428: The Navi Mumbai side of the MTHL. Construction equipment used during the project were fitted with silencers to reduce the potential impact of noise on migratory birds such as flamingos. The project utilized reverse circulation drilling methodology which helps reduce noise levels and helps speed up construction in marine areas. A 5.6 km long temporary access bridge had been built to transport equipments and workers for

6250-457: The Navi Mumbai side of the sea bridge, and the bridge portion on land towards Chirle, respectively. The contracts between the MMRDA and the L&;T-IHI Corporation consortium were officially signed on 27 December 2017. L&T was awarded ₹ 7,637.3 crore (US$ 920 million) for the 10.38 km package 1 and ₹ 1,013.79 crore (US$ 120 million) for the 3.61 km package 3. The contract for

6375-400: The Navi Mumbai side. The first segment was erected on the Sewri side about 6 km into the sea. MMRDA officials announced the completion of the pre-casting work on 9 August. Officials also stated that they had completed the construction of 270 permanent piles, of which 177 were in the sea. The agency had also completed the construction of a 2 km long temporary access bridge. Casting for

SECTION 50

#1732787321914

6500-473: The Sewri–Worli connector with Dr. Rafi Ahmed Kidwai Marg, west of Sewri railway station, and with Acharya Donde Marg at Mumbai Port Trust. Further, the agency will demolish the existing single-tier road over bridge at Prabhadevi railway station and replace it with a new two-tier road over bridge. The agency later paused plans for the connector due to delays with the MTHL project. The MMRDA floated new tenders for

6625-580: The Sewri–Worli connector. They were Simplex Infrastructures Ltd., Larsen & Toubro, Hindustan Construction Company (HCC), Gammon India, and the National Construction Company (NCC). Simplex Infrastructures Ltd. quoted the lowest bid (nearly 16–17% below the estimated cost of the project), followed by Larsen & Toubro (14% below the reserve price). In April 2016, DNA reported that the project had been cancelled, after previously being put "on hold" in 2015. No budgetary allocation

6750-424: The Sewri–Worli elevated corridor with Rafi Ahmed Kidwai Marg, west of Sewri railway station, and with Acharya Donde Marg at Mumbai Port Trust. The Sewri–Worli connector was first proposed by the MMRDA in 2012–2013. The project was estimated to cost ₹ 517 crore (equivalent to ₹ 826 crore or US$ 99 million in 2023), and be completed in four years. The MMRDA received bids from 5 companies to construct

6875-533: The bidding process by the MMRDA. The MMRDA stated that Home Ministry had not provided the agency with any official reason for denying security clearance. IL&FS Engineering filed an appeal against the decision in the Bombay High Court on 18 July. The Court permitted IL&FS to submit its bid, subject to a final decision by the Court. The MMRDA received bids from 17 of the 29 shortlisted contractors by

7000-415: The bridge requiring about 96,250 tonnes of steel. The steel spans weigh up to 2,600 tonnes and make up 4.7 km of the bridge length, while the rest of the bridge is made up of 60 metre-long concrete spans weighing up to 130 tonnes each. This 4.7 km section sits at the highest point of the MTHL and includes a 180-metre-long steel span, which is the longest steel span in India. The shortest steel span on

7125-468: The bridge so that it does not affect the flamingo habitat at Sewri. The Department of Atomic Energy (DAE) had directed MMRDA to construct a six-km long view barrier to cut the view of Bhabha Atomic Research Centre (BARC). The MTHL received coastal regulation zone clearance from the MoEFCC on 19 July 2013. On 31 October 2012, the Department of Economic Affairs (DEA) granted in-principle approval for

7250-433: The bridge to provide commuters with a direct communication link to emergency services. Also, Variable Message Display (VMD) systems have been installed to effectively communicate and provide real-time information to commuters. The roads on both sides of the bridge have been paved with stone mastic asphalt (SMA) The bridge is paved with stone matrix asphalt, which has a high percentage of crushed, durable stone aggregates and

7375-530: The bridge, which is six times more than the quantity used for building the Statue of Unity . The reinforced steel used is 17 times the quantity used in the Eiffel Tower . The bridge is constructed using corrosion-resistant materials to withstand weather variations, high wind speeds and tides, along with natural phenomena like earthquakes and cyclones. It can withstand earthquakes up to 6.5 magnitude, thus giving

7500-425: The bridge. It was constructed in three sections. Construction of the bridge required the use of 165,000 tonnes of reinforcement steel , 96,250 tonnes of structural steel , and 830,000 cubic metres of concrete . The bridge features the first use of orthotropic decks in India. The special steel decks enable the bridge to have longer spans than possible with regular girders. A total of 70 orthotropic decks were used on

7625-420: The cabinet meeting also stated that 95% of work on the MTHL had been completed. In December 2023, the construction work was fully completed, with load testing, painting of dividers and testing of various systems as the only remaining tasks that were ongoing. The MTHL was inaugurated and opened to the public by Prime Minister Narendra Modi on 12 January 2024. The MMRDA has installed noise and vision barriers on

SECTION 60

#1732787321914

7750-515: The capacity of a road compared to an identical road with at-grade junctions. For instance, it is extremely uncommon to find an at-grade junction on a British motorway ; it is all but impossible on a U.S. Interstate Highway , though a few do exist. If traffic can traverse the junction from any direction without being forced to come to a halt, then the junction is described as fully grade separated or free-flowing . These junctions connect two freeways: These junctions connect two roads, but only one

7875-617: The concession agreement. The DEA is the first tier of the three-tier clearance process to get viability gap funding (VGF) for the project. The project must also receive approval from an empowered committee and finally from the Finance Minister . On 9 November 2012, the State Government issued a state-support agreement and a toll notification for the project. The empowered committee approved VGF for MTHL on 12 December 2012. The then Finance Minister, P. Chidambaram , cleared

8000-408: The construction of the MTHL. In November 2021, the MMRDA announced that it had decided against demolishing the bridge and would convert it into a bird-watching platform to view flamingos and other birds. The agency noted that the decision would also save the cost of having to demolish the bridge. As an access-controlled road , to efficiently manage and regulate traffic movement across the MTHL, it has

8125-490: The construction of the project. In October 2016, the MMRDA agreed to pay MbPT a total of ₹ 1000 crores in installments over the course of 30 years, as rent for using the MbPT's land for construction of ramps for the MTHL on the Mumbai side. The MMRDA received 27.2 hectares of land on the Sewri side of the MbPT, of which 15.17 hectares were temporarily used for the casting yard. The MMRDA utilized drones to carry out survey work for

8250-558: The construction work would generate 115,419 man-months of employment. Over 14,000 workers were involved throughout the construction of the MTHL. Contractors worked round-the-clock in three 8-hour shifts. Expert consultants from 10 different countries including Brazil , Denmark, Japan, South Korea, Switzerland, the United Kingdom, the United States, and some Middle Eastern astern countries were involved in various aspects of

8375-412: The cost of the project was estimated at ₹ 4,000 crore (equivalent to ₹ 140 billion or US$ 1.6 billion in 2023). The cost was revised to ₹ 6000 crore in 2008. It was then increased to ₹ 8800 crore in November 2011 and to ₹ 9360 crore in August 2012. The MMRDA re-evaluated the cost project as about ₹ 11,000 crore (US$ 1.3 billion) at 2014 prices. In April 2017, the project cost

8500-579: The cost to reduce by 6% as a result of the Union Government's decision to lower the goods and services tax (GST) for construction work from 18% to 12%. The revised cost of the contract would now be ₹ 13,400 crore (US$ 1.6 billion). The COVID-19 pandemic caused delays to construction which escalated the project cost by around 5–15%. The total cost of the MTHL was estimated as ₹ 17,843 crore (US$ 2.1 billion) in September 2021. Cost escalation also occurred because of design changes caused by

8625-766: The cost. However, MMRDA officials expressed willingness to raise the height of the bridge to 31–35 metres. On 8 January 2012, the then Minister of Shipping and MP from South Mumbai , Milind Murli Deora , told reporters that JNPT would issue a No Objection Certificate (NOC) to the state government to go ahead with the project. In May 2012, the MMRDA shortlisted five consortia for the project: Cintra -SOMA-Srei, Gammon Infrastructure Projects Ltd. - OHL , Concessions- G.S. Engineering , GMR Infrastructure - L&T Ltd .- Samsung C&T Corporation , IRB Infrastructure Developers Ltd .- Hyundai , and Tata Realty and Infrastructure Ltd. - Autostrade Indian Infrastructure Development Pvt. Ltd. - Vinci Concessions Development Pvt. Ltd . None of

8750-402: The developer who won the bid. The concession period would have been 35 years, which included the timeframe of 5 years for the construction. However, the consortia shortlisted for the project were concerned that 15–20% of the projected traffic for the MTHL, was due to the proposed and now under-construction Navi Mumbai International Airport , which was heavily delayed. The MMRDA added provision for

8875-571: The direct flow of traffic on one or more of the roads is not disrupted. Instead of a direct connection, traffic must use on and off ramps ( United States , Australia , New Zealand ) or slip roads ( United Kingdom , Ireland ) to access the other roads at the junction. The road which carries on through the junction can also be referred to as grade separated . Typically, large freeways , highways , motorways , or dual carriageways are chosen to be grade separated, through their entire length or for part of it. Grade separation drastically increases

9000-399: The end of their service life, thus keeping the environment free of pollution. The carbon footprint from vehicular emissions will also significantly reduce by a few hundred thousand tons, as vehicles will be crossing the bridge at a maximum speed limit of 100 km/h (62 mph). Environmentalists were concerned that the lightings on the bridge would disturb marine life at night. To solve

9125-684: The example of the tunnel in Belgium ), and would also be aesthetically preferable as a sea link would obstruct the city's coastline. However, Gadkari clarified that the Government of India would accept the final decision made by the state government on this matter. Following a visit to China, the then Chief Minister of Maharashtra , Devendra Fadnavis , announced on 20 May 2015, that the China Communications Construction Company (CCCC) had expressed interest in

9250-573: The faster speed requires grade separation. Therefore, many high speed lines are elevated, especially in Taiwan and Japan , where population density alongside high speed lines is higher than in France, Italy or Germany. In the United States, a flying junction on the Nickel Plate Road through Cleveland , Ohio , United States was completed in 1913. The most frequent use was later found on

9375-408: The final bid submission date on 19 July 2017. The agency stated that it would take a month to conduct technical evaluations of the bids and to award contracts. On 9 November 2017, the MMRDA awarded contracts to a consortium of Larsen & Toubro (L&T) and Japan's IHI Corporation , a consortium of Daewoo and Tata Projects (TPL), and L&T itself to construct the Sewri side of the sea bridge,

9500-468: The first and second packages, and 17 bids for the third package. The agency stated that a single party would not be awarded the first and second packages together, although any other combination of the three packages would be permitted. The MMRDA appointed a consortium formed by AECOM Asia Co. Ltd., Padeco India Pvt. Ltd, Dar Al-Handasah , and T. Y. Lin International as the general consultant for

9625-474: The first segment of Package 3 of the project began on 12 September 2019. On the same date, MMRDA officials also stated that 20% of the total project work had been completed. The first girder, weighing 1,000 tonnes, for the MTHL was launched on 15 January 2020, marking the erection of its first span. The project faced delays due to the COVID-19 pandemic . Over 5,000 workers had been deployed on the project prior to

9750-416: The five shortlisted firms bid for the project by the deadline, which was extended to 5 August. IRB-Hyundai announced their withdrawal from the bidding process, on 31 July 2013, citing "the government's apathy and unfriendly attitude towards investors wanting to develop capital-intensive infrastructure projects". Following the failure of the tender, the MMRDA decided to abandon the PPP model and instead implement

9875-508: The former Pennsylvania Railroad main lines. The lines are included as part of the Northeast Corridor and Keystone Corridor now owned by Amtrak . The most complex of these junctions, near Philadelphia Zoo , handles railway traffic for Amtrak, SEPTA , New Jersey Transit , Norfolk Southern , CSX Transportation , and Conrail . In what is known as "area 1520" , which includes the former Soviet Union and other regions using

10000-400: The foundation stone for the project on 21 February 2021. 25.77% of work on the project was completed by November 2022. As of January 2024, 50% of work has been completed. It is expected to open by the end of 2024. The Shivajinagar interchange connects the MTHL with the Navi Mumbai International Airport , Jawaharlal Nehru Port , and local roads. It has been built to connect Ulwe directly to

10125-413: The issue, engineers have installed 1,212 special light poles that will illuminate only the carriageways, without any luminous spill onto the sea, thus positively affecting the marine life. These eco-friendly and sustainability measures have earned the bridge and the MMRDA a sustainability certificate from the Bombay Natural History Society (BNHS). The cost of the MTHL has increased several times. In 2005,

10250-716: The lifespan of the bridge to remain intact for over a century. The 70 spans of Orthotropic Steel Decks (OSDs) with lengths ranging from 65 to 180 metres and weighing up to 2,800 metric tons were erected across the Thane Creek using Japanese technology . In addition, a Comprehensive Surveillance System (CSS) utilizes a network of high-definition CCTV cameras strategically placed along the entire route. The Speed Violation Detection System (SVDS) has been installed to enforce speed limits and for ensuring enhanced road safety to commuters. A Video Incident Detection System (VIDS) that promptly detects and responds to incidents and mishaps has been installed. There are Emergency Calling Boxes (ECBs) on

10375-535: The location of underground utilities, which were different from what planners had assumed. The MTHL has three interchanges at Sewri, Shivajinagar in Ulwe, and Chirle. The MMRDA has constructed a 1.5 km long cloverleaf interchange on a 27-acre plot, leased from the Mumbai Port Trust , located east of Sewri railway station . The loop consists of two lanes branching out from the MTHL and connecting with

10500-431: The loss. The agency stated that 40% of the total project work had been completed by the end of June 2021. The then Minister of State for Urban Development and Public Works, Eknath Shinde 's Public Relation Office, stated in August 2021 that 52% of the project work had been completed. It also noted that 8,189 staff and labourers were currently deployed on the construction site, and that about 8 months of work days were lost as

10625-467: The low concession period. The MSRDC felt that the concession periods were "unrealistic" and that both bids "seemed frivolous in nature". The Government of Maharashtra called for fresh bids for the project in 2008. However, none of the 13 companies that had shown interest submitted bids. The media criticized the political feud between the ruling Nationalist Congress Party (NCP) and Indian National Congress coalition, as being responsible for "slowing down

10750-475: The mangrove habitat. The Sewri mudflats are home to 150 species of birds species, and is listed as an "Important Bird Area". The FAC instructed the state government to submit a study report on the project's impact on the flamingo population, and recommended that the government seek the help of either the Bombay Natural History Society (BNHS) or the Wildlife Institute of India , Dehradun , to conduct

10875-576: The names of all companies that bid for the project to the Home Ministry. The ministry will grant clearance after consultations with other ministries, such as the Ministry of External Affairs and intelligence agencies . The Home Ministry denied security clearance to a bid from China Railway Major Bridge Engineering Group in a joint venture with Gayatri Projects Limited, and also to a consortium of IL&FS Engineering Limited and Ranjit Buildcon Limited. Both consortia were subsequently disqualified from

11000-519: The orthotropic decks were manufactured in Japan, Myanmar , Taiwan , and Vietnam and shipped to Karanja Port in Uran for assembly. The decks were carried to the construction site by barge, and each deck required about 3 days to install in place. A programmed self-propelled transporter was utilized to load the deck onto the barge, and computer-controlled jacks were utilized to install them on the bridge within

11125-653: The pace of Mumbai's development". The city's two infrastructure agencies, the MSRDC and the Mumbai Metropolitan Region Development Authority (MMRDA), under the NCP and Congress respectively, were both planning to construct the Mumbai Trans Harbour Link (MTHL) at the same time. The project underwent two failed rounds of tendering under the MSRDC, and was stuck for nearly two years (between 2009 and 2011), before

11250-459: The pandemic, but this was reduced to around 2,000 workers by June 2020. An estimated 27% of the total project work had been completed by June 2020, and 35.29% by November 2020. The BMC Tree Authority granted permission to the MMRDA to cut 454 trees and transplant another 550 trees for the MTHL project on 2 December 2020. The MMRDA stated that it would also plant 2,000 trees in Vasai to compensate for

11375-544: The previous junction. This situation is most prevalent either where the junction designer has placed the on-slip to the road before the off-slip at a junction (for example, the cloverleaf interchange ), or in urban areas with many close-spaced junctions. The ring road of Coventry , England , is a notorious example, as are parts of the southern M25, the London orbital motorway , the M6/M5 junction north-west of Birmingham , and

11500-446: The project cost, and the remaining amount will be borne by the state government. As JICA was unwilling to loan directly to the state government, the Union Government stood as a guarantor of the loan. As part of the agreement between JICA and the state government, 2 rescue lanes will be added to the proposed plan for the MTHL, and a 4 km stretch of the bridge will be constructed as a steel-only structure instead of previous plan to build

11625-692: The project in July 2020. The project received clearance from the Maharashtra Coastal Zone Management Authority (MCZMA) on 7 July 2020, and from the Maharashtra State Environment Impact Assessment Authority (SEIAA) on 8 September 2020. J. Kumar Infraprojects Ltd. was awarded the contract to build the Sewri–Worli connector in November 2020. The project is estimated to cost ₹ 1,051.86 crore (US$ 130 million). Construction began on 13 January 2021. The then Chief Minister of Maharashtra, Uddhav Thackeray , laid

11750-556: The project in November 2017, and construction began in April 2018, which was scheduled to be completed within 4.5 years, by 2022. However, the construction was delayed by around 8 months due to the COVID-19 pandemic , and was expected to be completed by August 2023, then again by December 2023. The construction was finally completed in December 2023, and was inaugurated by Prime Minister Narendra Modi on 12 January 2024. Transportation and traffic planning for Greater Bombay (now Mumbai )

11875-406: The project on 18 January 2013. The Jawaharlal Nehru Port Trust (JNPT) asked the MMRDA to build the MTHL at a height of 51 metres, instead of the proposed 25 metres, for a span of 300 metres to accommodate its expansion plans for its fifth container terminal and to allow safe passage of bigger vessels. MMRDA expressed that a height of 51 metres would not be feasible as it would have a huge impact on

12000-427: The project on 26 November 2016. According to U.P.S. Madan, the then Metropolitan Commissioner of the MMRDA, stated that the general consultants appointed for the MTHL project would engage in various activities, such as to help MMRDA organise pre-bid meetings, examine bid documents, secure various permissions from government, semi-government, examine concept designs, monitor construction of the project and ensure quality of

12125-436: The project on cash contract basis. In January 2013, the Government of India had sanctioned ₹ 1,920 crore (US$ 230 million), which was 20% of the project cost at the time, in viability gap for the MTHL. Under the public private partnership (PPP) basis that the project was proposed to be implemented in, the state government would also contribute the same amount as the centre, while the remaining 60% would have been borne by

12250-490: The project. Prime Minister Narendra Modi laid the foundation stone for the project on 24 December 2016. Construction of the MTHL began on 24 April 2018, with engineers collecting soil samples for soil testing at each location, where piers will be built in Nhava Sheva . The then MMRDA Metropolitan Commissioner, R. A. Rajeev, stated on 28 October 2018 that about 9% of the project work had been completed. The first pier of

12375-495: The remaining 882 were replanted at other locations. Most of the affected trees were located at Sewri and Vakola . In 2010, the MMRDA appointed Rail India Technical and Economic Service (RITES) to prepare a detailed project report (DPR) for the Mumbai Trans Harbour Metro Rail Link (MTHMRL), a proposal to build a dual-track metro line under the road lanes of the MTHL. The 49-km long metro line

12500-557: The safe operation of high-speed lines. The construction of new level crossings is generally not permitted, especially for high speed railway lines and level crossings are increasingly less common due to the increase of both road and rail traffic. Efforts to remove level crossings are done in the UK by Network Rail and in Melbourne as part of the Level Crossing Removal Project . The London Extension of

12625-683: The same gauge, the most complicated grade-separation railpoint is found at Liubotyn in Ukraine . Footbridges and subways (called underpasses in North America as well as in the United Kingdom when referring to roads) may be employed to allow pedestrians and cyclists to cross busy or fast streets. They are often used over and under motorways since at grade pedestrian crossings are generally not permitted. Same can be said for railways. Though introduced to Central Park in New York City in

12750-472: The sea link was made in 2004, when Infrastructure Leasing & Financial Services (IL&FS) submitted a proposal to implement the project on a build, own, operate, and transfer (BOOT) basis. The Maharashtra State Road Development Corporation (MSRDC) also submitted a counter proposal. However, the IL&;FS proposal was sidelined by the Government of Maharashtra , for undisclosed reasons. Another attempt

12875-429: The sea link. The first of five composite steel girder spans, weighing 130 MT and 40 metres long, linking the MTHL with the Eastern Freeway at Sewri was installed on 20 February 2023. On 4 March 2023, the then MMRDA commissioner, S.V.R. Srinivas, stated that the segment casting work for Package 2 was complete, and 93% of the total project work had been completed. The steel deck span connecting Package 1 and Package 2 over

13000-420: The sea was installed on 21 June 2023, completing end-to-end connectivity on the right-hand side of the bridge. On 25 June 2023, an MMRDA official stated that no construction work would be carried out on the portion of the bridge over the sea during the monsoon season for safety reasons. On 28 June 2023, the state cabinet decided to rename the MTHL after former Prime Minister Atal Bihari Vajpayee . A note from

13125-417: The second application for environmental clearance. They still believe that the sea link is not allowed as per the new Coastal Regulation Zone (CRZ) notification of 2011. They also claim that the sea link would damage a huge mudflat and mangrove tract towards Sewri and Nhava Sheva , which is a habitat for migratory birds like flamingos. Nevertheless, the MMRDA finalised the plan to construct sound barriers on

13250-738: The shortlisted bidders, and was again forced to postpone the date to 17 July in order to respond to all queries. The MMRDA applied for security clearance from the Union Ministry of Home Affairs to carry out construction near the Bhabha Atomic Research Centre, the Mumbai Port Trust and the Jawaharlal Nehru Port Trust. These facilities have restricted areas that are covered by the Official Secrets Act . The MMRDA also submitted

13375-484: The state government decided to hand over the mandate to MMRDA. Following the decision, the MSRDC asked MMRDA to pay ₹ 25 crore (US$ 3.0 million) if it wanted access to any of the studies on the project conducted by the former. After the MMRDA was tasked with executing the MTHL, the MSRDC took up the expansion of the Vashi Bridge by adding six more lanes to ease congestion at the entrance to Navi Mumbai. However,

13500-513: The study. The cost of the study would be borne by the MMRDA, which would also have to come with safeguards to cause the least disturbance to the flamingos at Sewri. On 17 April 2015, the Minister of Road Transport and Highways, Nitin Gadkari , stated that he favoured the construction of a submarine tunnel instead of a sea link. Gadkari stated that the tunnel would cost less than a bridge (citing

13625-443: The then Chief Minister of Maharashtra , Prithviraj Chavan , on 22 October 2012. The Times of India described the MTHL's delay as being "symbolic of all that is wrong with infrastructure planning and implementation in Mumbai". The newspaper daily also stated that a project being "on the drawing board after more than forty years would be in the realm of fiction in any other country". The project received environmental clearance from

13750-463: The then MMRDA additional metropolitan commissioner, told The Indian Express that the state government had sent a formal proposal to the DEA for its approval to get funds from JICA. In June 2014, Business Line reported that Jawaharlal Nehru Port Trust authorities had agreed to pick up a stake in the project. The project ran into a major hurdle in April 2015, when the forest advisory committee (FAC) of

13875-400: The tightly grouped nest of flying junctions to the north of Clapham Junction railway station —although technically a combination of many junctions—handle more than 4,000 trains per day (about one train every 15 seconds). Virtually all major railway lines no longer cross (forming an 'X' shape ) at flat level (although many diverge - i.e. 'Y' shape). On almost all high-speed railway lines,

14000-409: The total cost through a loan at a concessional rate of Yen - London Interbank Offered Rate plus 0.1% for the project activities, and 0.01% for consulting services, with a 30-year repayment period, including a 10-year grace period. JICA and the MMRDA signed the agreement to disburse the first tranche of the loan on 31 March 2017. The first tranche of ₹ 7,912 crore (US$ 950 million) was about 45% of

14125-404: The total project cost. The second tranche of ₹ 4,262 crore (US$ 510 million) was extended on 27 March 2020, and the third tranche of ₹ 1,297 crore (US$ 160 million) was extended on 3 March 2023. The MMRDA bore 1.2% of the project cost, and the remaining amount was borne by the state government. The MMRDA allocated ₹ 1,200 crore (US$ 140 million) towards the project in its budget for

14250-548: The traffic already on the roundabout wishing to use the M6 Westbound on-slip. This is as a result of the slip roads on the west side of the junction connecting to the roundabout on the inside of the eastern arc rather than the outside of the western arc as is normal. The two slip-roads are connected by a single lane on the inside of the roundabout, which traffic wishing to use the Westbound on-slip must join, and traffic from

14375-481: The work among other things. After evaluating the bids, in January 2017, the MMRDA shortlisted a total of 29 contractors for the three packages and floated tenders for the request for proposal (RFP) stage, the final stage of the bidding process. The agency fixed 5 April 2017 as the final date for submissions of the RFP bids. The submission date was later postponed to 5 June. However, the agency received over 3,000 queries from

14500-490: Was awarded to a joint venture between Strabag Infrastructure & Safety Solutions GmbH and Strabag AG, both owned by the Austrian construction company, Strabag . The project required 130 hectares of land. The City and Industrial Development Corporation (CIDCO) contributed 88 hectares. The remaining land was privately owned. According to MMRDA officials, land owners were given the same compensation package as that given in

14625-488: Was commissioned for Wilbur Smith and Associates (WSA) (now ( CDM Smith ) in mid-1962. The firm's report, based on extensive studies conducted over 18 months, was handed over to the Ministry of Road Transport and Highways (MoRTH) on 19 December 1963. Among other projects, the report proposed the construction of a sea link, known as the Uran Bridge, to connect Mumbai with the mainland near the town of Uran . However, WSA

14750-412: Was estimated at ₹ 17,843 crore (US$ 2.1 billion), which includes ₹ 70 crore compensation to fishermen, ₹ 45 crore for installing noise barriers after opening the sea link, a ₹ 25 crore deposit as seed money to mangrove fund, another ₹ 25 crore for a compensatory mangrove restoration plan, and a mandatory expenditure of at least ₹ 335 crore for an "environment management programme". In July 2017,

14875-505: Was inaugurated by Prime Minister Narendra Modi on 12 January 2024. In the 1990s, keeping the future of the Mumbai Metropolitan Region in mind, the Mumbai Metropolitan Region Development Authority (MMRDA) began studies on how to decongest the rising traffic and congestion in Mumbai , and accidents and mishaps as their direct consequences. There are currently six bridges connecting Mumbai and Navi Mumbai across

15000-540: Was initially disqualified at the technical bid stage, as Hyundai did not meet the criteria of $ 200 million net worth specified in the bid document. However, the consortium challenged the disqualification in the Supreme Court , and the Court granted them 90 days to submit their bid that ended on 15 December 2007. The consortium eventually won the bid in February 2008. However, the MSRDC was not sure about viability of

15125-459: Was made for the project in the 2015–16 fiscal, and the MMRDA had no future plans to construct the connector. The agency floated tenders again in 2017 at an estimated cost of ₹ 1,276 crore (US$ 150 million). Apart from delays, the cost increase was also the result of some major design changes. The proposed connector will be built with a steel super structure instead of cement as per the original plan. The MMRDA also proposed additional ramps to link

15250-647: Was made in 2005, when the MSRDC invited bids for the project. The bids submitted by the Ambani brothers were considered to be unrealistic. A consortium of the Anil Dhirubhai Ambani Group , Reliance Energy (REL) and Hyundai Engineering & Construction quoted a concession period of nine years and 11 months, against 75 years quoted by Mukesh Ambani 's Sea King Infrastructure (the only other shortlisted bidder left, after Larsen & Toubro - Gammon and IFFCO opted out). The REL-Hyundai consortium

15375-553: Was proposed to connect Prabhadevi and Dushmi, about 20 km away from Chirle. The metro line was to be extended to the proposed Navi Mumbai International Airport , and connected to the proposed Ranjanpada - Seawoods - Kharkopar corridor of the Navi Mumbai Metro and the proposed Sewri-Prabhadevi corridor of the Mumbai Metro . However, the MMRDA scrapped plans for the metro line in 2012, and decided to build only

15500-414: Was sent to the Government of Maharashtra for consideration in 2012. In 2015, the project was approved by the Government of India and the Ministry of Road Transport and Highways (MoRTH). Hence, the foundation stone for the construction of the project was laid by Prime Minister Narendra Modi on 24 December 2016. Initially, it was expected to be completed by 2021. Then, the MMRDA awarded contracts for

15625-483: Was unsure of the link's feasibility. Citing poor traffic expectations in Uran even in 1981, WSA's report advised a more detailed study of this connection and recommended waiting until the Trans- Thane area would develop further and more community services would be extended to Uran." In 1973, the Vashi Bridge linking Mankhurd in Mumbai with Vashi in Navi Mumbai was opened. The first concrete attempt to build