Misplaced Pages

S-IVB

Article snapshot taken from Wikipedia with creative commons attribution-sharealike license. Give it a read and then ask your questions in the chat. We can research this topic together.

The S-IVB (pronounced "S-four-B") was the third stage on the Saturn V and second stage on the Saturn IB launch vehicles. Built by the Douglas Aircraft Company , it had one J-2 rocket engine. For lunar missions it was fired twice: first for Earth orbit insertion after second stage cutoff, and then for translunar injection (TLI).

#675324

102-621: The S-IVB evolved from the upper stage of the Saturn I rocket (the S-IV ) and was the first stage of the Saturn V to be designed. The S-IV used a cluster of six RL-10 engines but used the same fuels as the S-IVB – liquid hydrogen and liquid oxygen . It was also originally meant to be the fourth stage of a planned rocket called the C-4 , hence the name S-IV. Eleven companies submitted proposals for being

204-511: A central Jupiter rocket tank containing LOX, surrounded by a cluster of eight Redstone rocket tanks: four painted white, containing LOX; and four painted black, containing the RP-1 fuel. The four outboard engines were mounted on gimbals , allowing them to be steered to guide the rocket. On the Block II vehicles (SA-5 through SA-10), eight fins provided aerodynamic stability in the flight through

306-409: A change request was received from ARPA to upgrade the upper stage to a much more powerful design using four new 20,000 lbf (89 kN) liquid hydrogen / liquid oxygen powered engines in a larger-diameter 160-inch (4.1 m) second stage, with an upgraded Centaur using two engines of the same design for the third stage. On this change Medaris noted: In order to reach some sort of accommodation,

408-583: A common bulkhead to separate the propellants. The S-V stage was flown four times on missions SA-1 through SA-4 ; all four of these missions had the S-V's tanks filled with water to be used a ballast during launch. The stage was never flown in an active configuration on any Saturn launch vehicle. This stage was also used on the Atlas-LV3C as the Centaur, modern derivatives of which are still flown today, making it

510-594: A contractor owned and operated (COGO) facility and modifications for the Delta IV H were determined to be similar to those required for Ares I. The ESAS launch safety estimates for the Ares were based on the Space Shuttle, despite the differences, and included only launches after the post-Challenger Space Shuttle redesign. The estimate counted each Shuttle launch as two safe launches of the Ares booster. The safety of

612-793: A crew capsule, similar in design to the Apollo program capsule, to transport astronauts to the International Space Station , the Moon , and eventually Mars . Ares I might have also delivered some (limited) resources to orbit , including supplies for the International Space Station or subsequent delivery to the planned lunar base . NASA selected Alliant Techsystems, the builder of the Space Shuttle Solid Rocket Boosters , as

714-539: A fifth segment to the solid-rocket first stage, and replace the single SSME with the Apollo-derived J-2X motor. While the change from a four-segment first stage to a five-segment version would allow NASA to construct virtually identical motors, the main reason for the change to the five-segment booster was the move to the J-2X. The Exploration Systems Architecture Study concluded that the cost and safety of

816-444: A flame 200 feet (61 meters) in length, and preliminary data showed the igniter performed as planned. Development of the Ares I propulsion elements continued to make strong progress. On September 10, 2009, the first Ares I development motor (DM-1) was successfully tested in a full-scale, full-duration test firing. This test was followed by two more development motor tests, DM-2 on August 31, 2010, and DM-3 on September 8, 2011. For DM-2

918-789: A group pulled from NASA, Air Force, ARPA, ABMA, and the Office of the Department of Defense Research and Engineering formed under the Silverstein Committee in December. von Braun was skeptical of liquid hydrogen as an upper stage fuel, but the Committee convinced him that it was the way to go on future upper stage development. Once these changes had been made, NASA's booster project was now entirely free of any dependence on military developments. At that point any sort of upper stage

1020-569: A large lunar rocket in Earth orbit, and the Air Force's Lunex Project which planned on launching a single huge lander using the largest of the SLS configurations. As if this were not enough, NASA's own engineers had started the design of their own Nova design series, planning to use it in the direct ascent profile similar to the Air Force's approach. Von Braun was asked to chair a committee to study

1122-450: A maximum of about 3,900 pounds (1,800 kg) in orbit, but might be expanded to as much as 9,900 pounds (4,500 kg) with new high-energy upper stages. In any event, these upper stages would not be available until 1961 at the earliest, and would still not meet the DoD requirements for heavy loads. Wernher von Braun 's team at the U.S. Army Ballistic Missile Agency (ABMA) started studying

SECTION 10

#1732790227676

1224-521: A new 200-foot (61 m)-long stage. A Centaur would be used as a third stage, which was expected to be ready for operational use in 1963, right when the lower two stages would have completed their testing. The resulting three-stage design was much taller and skinnier than the Saturn design that was eventually built. Advanced Research Projects Agency (ARPA) was formed in February 1958 as part of DoD and

1326-627: A new launch system, like the Apollo or Space Shuttle systems, it was normal for such problems to arise during the development stage. According to NASA, analysis of the data and telemetry from the Ares I-X flight showed that vibrations from thrust oscillation were within the normal range for a Space Shuttle flight. A study released in July 2009 by the 45th Space Wing of the US Air Force concluded that an abort 30–60 seconds after launch would have

1428-567: A nuclear strike and might invite a response-in-kind. The S-V third stage was developed as the Centaur rocket stage, It was flown inactively four times on the Saturn I with the tanks filled with water. It never flew an active mission. The S-V would become an upper stage for the Atlas-Centaur and Titan III launch vehicles and their derivatives. The S-I first stage was powered by eight H-1 rocket engines burning RP-1 fuel with liquid oxygen (LOX) as oxidizer. The propellant tanks consisted of

1530-567: A simplified Space Shuttle Main Engine (SSME) for the second stage. An uncrewed version was to use a five-segment booster with the same second stage. Shortly after the initial design was approved, additional tests revealed that the Orion spacecraft would be too heavy for the four-segment booster to lift, and in January 2006 NASA announced they would slightly reduce the size of the Orion spacecraft, add

1632-444: A test launch on October 28, 2009. Launch Pad 39B was damaged more than with a Space Shuttle launch. During descent, one of the three parachutes of the Ares I-X's first stage failed to open, and another opened only partially, causing the booster to splash down harder and suffer structural damage. The launch accomplished all primary test objectives. NASA completed the Ares I system requirements review in January 2007. Project design

1734-611: A very familiar local landmark. Ares I Ares I was the crew launch vehicle that was being developed by NASA as part of the Constellation program . The name "Ares" refers to the Greek deity Ares , who is identified with the Roman god Mars . Ares I was originally known as the "Crew Launch Vehicle" (CLV). NASA planned to use Ares I to launch Orion , the spacecraft intended for NASA human spaceflight missions after

1836-433: A ≈100% chance of killing all crew, due to the capsule being engulfed until ground impact by a cloud of 4,000 °F (2,200 °C) solid propellant fragments, which would melt the capsule's nylon parachute material. NASA's study showed the crew capsule would have flown beyond the more severe danger. The Ares I igniter was an advanced version of the flight-proven igniter used on the Space Shuttle's solid rocket boosters. It

1938-415: Is hereby agreed that this program should now be extended to provide for a propulsion flight test of this booster by approximately September 1960". Further, they wanted ABMA to produce three additional boosters, the last two of which would be "capable of placing limited payloads in orbit". von Braun had high hopes for the design, feeling it would make an excellent test-bed for other propulsion systems, notably

2040-545: The Atlas V and Delta IV was estimated from the failure rates of all Delta II , Atlas-Centaur , and Titan launches since 1992, although they are not similar designs. Ares I was the crew launch component of the Constellation program. Originally named the "Crew Launch Vehicle" or CLV, the Ares name was chosen from the Greek deity Ares . Unlike the Space Shuttle, where both crew and cargo were launched simultaneously on

2142-523: The Complex 34 launch sites started at Cape Canaveral in June. Then, quite unexpectedly, on 9 June 1959, Herbert York , Director of Department of Defense Research and Engineering, announced that he had decided to terminate the Saturn program. He later stated that he was concerned that the project was taking ARPA money from more pressing projects, and that as it seemed upgrades to existing ICBMs would provide

SECTION 20

#1732790227676

2244-736: The J-2S engines and Space Shuttle Main Engines (SSMEs) for the second stage. The variants also assumed use of the Advanced Solid Rocket Motor (ASRM) as a first stage, but the ASRM was cancelled in 1993 due to significant cost overruns. President George W. Bush had announced the Vision for Space Exploration in January 2004, and NASA under Sean O'Keefe had solicited plans for a Crew Exploration Vehicle from multiple bidders, with

2346-648: The Marshall Space Flight Center decided to use the C-5 rocket (later called the Saturn V), which had three stages and would be topped with an uprated S-IV called the S-IVB featuring a single J-2 engine, as opposed to the cluster of 6 RL-10 engines on the S-IV. Douglas was awarded the contract for the S-IVB because of the similarities between it and the S-IV. At the same time, it was decided to create

2448-522: The Michoud Assembly Facility for fit testing, before being returned to Alabama. Now on horizontal display, next to the static test tower at Marshall Space Flight Center. In 2019, it was reported that this stage has been made available by NASA for donation to an organization, with the only provision being an approximately $ 250,000 "shipping fee" for transportation costs. With apparently no inquiries by qualified institutions to obtain

2550-522: The Redstone stage strapped around a central larger tank derived from a Jupiter rocket. The design and diameter similarities would enable the use of the same tooling and facilities used to produce the older tanks, speeding up the design and production phases of the new stage. Contrary to what was reported to the press at the time (and propagated commonly ever since), the tanks were not simply Redstone and Jupiter tanks, but much longer versions built anew at

2652-584: The Space Launch System as its new vehicle for human exploration beyond Earth's orbit. In 1995 Lockheed Martin produced an Advanced Transportation System Studies (ATSS) report for the Marshall Space Flight Center . A section of the ATSS report describes several possible vehicles much like the Ares I design, with liquid rocket second stages stacked above segmented solid rocket booster (SRB) first stages. The variants that were considered included both

2754-577: The Space Shuttle was retired in 2011. Ares I was to complement the larger, uncrewed Ares V , which was the cargo launch vehicle for Constellation. NASA selected the Ares designs for their anticipated overall safety, reliability and cost-effectiveness. However, the Constellation program, including Ares I, was cancelled by U.S. president Barack Obama in October 2010 with the passage of his 2010 NASA authorization bill. In September 2011, NASA detailed

2856-487: The Space Shuttle External Tank , the new LH 2 and LOX tanks would have been separated by a common bulkhead like that employed on the Saturn V S-II and S-IVB stages. This would have provided a significant mass saving and eliminated the need to design a second stage interstage unit that would have had to carry the weight of the Orion spacecraft with it. In January 2008, NASA Watch revealed that

2958-493: The instrument unit (IU) , just ahead of the S-IV stage. The first version of the IU was 154 inches (3.9 m) in diameter and 58 inches (150 cm) high, and was both designed and built by Marshall Space Flight Center . Guidance, telemetry, tracking, and power components were contained in four pressurized, cylindrical containers attached like spokes to a central hub. This version flew on SA-5, SA-6, and SA-7. MSFC flew version 2 of

3060-851: The 500 series, the interstage flared out to match the larger diameter of the S-II stage of the Saturn V. The 200 series also had three solid rockets for separating the S-IVB from the S-IB during staging. On the 500 series this was reduced to two, and two small Auxiliary Propulsion System (APS) thruster modules were added as ullage motors for restarting the J-2 engine and to provide attitude control during coast phases of flight. The S-IVB carried 73,280 litres (19,360 US gal) of liquid oxygen (LOX), massing 87,200 kilograms (192,200 lb). It carried 252,750 litres (66,770 US gal) of liquid hydrogen (LH2), massing 18,000 kilograms (40,000 lb). Empty mass

3162-735: The Apollo CSM , proving invaluable during the Apollo Project . In the end, the Titan C was never delivered, and the Air Force instead turned to "thrust augmented" Titan IIs using clustered solid-fuel rockets . These new designs, the Titan IIIs , became the DoD's main heavy-lift launch vehicle for decades afterward as it cost significantly less to manufacture and fly, in part due to using hypergolic propellants that could be stored at room temperature. An important factor in this decision

S-IVB - Misplaced Pages Continue

3264-467: The Apollo program. With the need for flexibility in launch configuration removed, most of these designs were subsequently dropped. Only the S-V survived in its original form, while the S-IV would appear in modified form and the Saturn V would feature an entirely different S-II stage. The Saturn I made its maiden flight on 27 October 1961 with a dummy upper stage and partially fueled first stage. Tension in

3366-473: The Ares I development schedule due to budgetary pressures and unforeseen engineering and technical difficulties would have increased the gap between the end of the Space Shuttle program and the first operational flight of Ares I. Because the Constellation program was never allocated the funding originally projected, the total estimated cost to develop the Ares I through 2015 rose from $ 28 billion in 2006 to more than $ 40 billion in 2009. The Ares I-X project cost

3468-569: The Ares I rated the vehicle as almost twice as safe as an Atlas or Delta IV-derived design. The first stage was to have been a more powerful and reusable solid fuel rocket derived from the Space Shuttle Solid Rocket Booster (SRB). Compared with the Solid Rocket Booster, which had four segments, the most notable difference was the addition of a fifth segment. This fifth segment would have enabled

3570-409: The Ares I to produce more thrust. Other changes made to the Solid Rocket Booster were to have been the removal of the Space Shuttle External Tank (ET) attachment points and the replacement of the Solid Rocket Booster nosecone with a new forward adapter that would have interfaced with the liquid-fueled second stage. The adapter was to have been equipped with solid-fueled separation motors to facilitate

3672-414: The Ares I would have cost $ 1 billion or more to operate per flight had the Ares I flown just once a year. If the Ares I system were flown multiple times a year the marginal costs could have fallen to as low as $ 138 million per launch. In March 2010, NASA administrator Charlie Bolden testified to congress that the Ares I would cost $ 4–4.5 billion a year, and $ 1.6 billion per flight. The Ares I marginal cost

3774-489: The Ares was superior to that of either of the Evolved Expendable Launch Vehicle (EELVs). The cost estimates in the study were based on the assumption that new launch pads would be needed for human-rated EELVs. The facilities for the current EELVs (LC-37 for Delta IV, LC-41 for Atlas V) are in place and could be modified, but this may not have been the most cost effective solution as LC-37 is

3876-511: The Army at distances up to 6400 kilometers. von Braun also proposed using the Juno V as the basis of a crewed lunar mission as part of Project Horizon . Juno could lift up to 20,000 pounds (9,000 kg) into low Earth orbit, and he proposed launching 15 of them to build a 200,000 lb (91,000 kg) lunar spacecraft in Earth orbit. Even by this point the name "Saturn", as "the one after Jupiter"

3978-546: The C-IB rocket (Saturn IB) that would also use the S-IVB as its second stage and could be used for testing the Apollo spacecraft in low Earth orbit. 12 200-series and 16 500-series S-IVB stages were built, alongside 3 test stages. NASA was working on acquiring 4 additional 200-series stages (as part of 4 new Saturn IB rockets, SA-213 to 216), but funding never materialized and the order was canceled in August 1968 before S-IVB hardware

4080-538: The F-1 if it matured. He outlined uses for the Juno V as a general carrier vehicle for research and development of "offensive and defensive space weapons". Specific uses were forecast for each of the military services, including navigation satellites for the Navy; reconnaissance, communications, and meteorological satellites for the Army and Air Force; support for Air Force crewed missions; and surface-to-surface logistics supply for

4182-507: The IU on SA-8, SA-9, and SA-10. Version 2 was the same diameter as version 1, but only 34 inches (86 cm) high. Instead of pressurized containers, the components were hung on the inside of the cylindrical wall, achieving a reduction in weight. The guidance computer for Block II was the IBM ASC-15 . Other instruments carried by the IU included active components, that guided the vehicle; and passenger components, that telemetered data to

S-IVB - Misplaced Pages Continue

4284-511: The NASA authorization bill for 2010 was signed into law which canceled Constellation. Previous legislation kept Constellation contracts in force until passage of a new funding bill for 2011. Ares I had a payload capability in the 25-tonne (28-short-ton; 25-long-ton) class and was comparable to vehicles such as the Delta IV and the Atlas V . The NASA study group that selected what would become

4386-588: The S-I first stage, and included the ST-90 stabilized platform, made by Ford Instrument Company and used in the Redstone missile. These first four vehicles followed ballistic, non-orbital trajectories, and the dummy upper stages did not separate from the single powered stage. The Block II vehicles (SA-5 to SA-10) included two powered stages, and went into orbits. Beginning with SA-5, the guidance instruments were carried on

4488-473: The S-III and S-IV on top. The C models easily outperformed the A's and B's, with the added advantage that they were interchangeable and could be built up in order to fit any needed payload requirement. Of these new stage designs, only the S-IV would ever be delivered, and not in the form that was drawn up in the Committee report. In order to meet development schedules a cluster of six Centaur engines were placed in

4590-679: The SA-T stage, the booster was demolished on or around April 4, 2022. SA-D Saturn I Block 1 Dynamic Test Vehicle. Manufactured at MSFC, used in several MSFC dynamic tests through 1962. Now on display in a vertical position with dummy upper stage in the rocket garden near MSFC headquarters, alongside several examples of heritage vehicles such as the V-2 rocket (A4), Redstone, Jupiter-C and Jupiter IRBM. SA-D5 Block 2 Dynamic Test Vehicle - consists of S-I-D5 Booster stage and S-IV-H/D hydrostatic/dynamic upper stage, used in tests at MSFC dynamic stand in 1962. It

4692-717: The Saturn I was the boilerplate version of the Apollo Command and Service Modules and Launch Escape System . The final three also carried Pegasus micrometeoroid satellites in the second stage-spacecraft adapter. The Saturn I was considered for launch of the X-20 Dyna-Soar spaceplane, and later, for launching a Gemini capsule on a proposed circumlunar mission . With funding of the Dyna-Soar cut in 1963 and Apollo development already far progressed, these proposals were however never realized. Much later, Saturn I

4794-603: The Saturn designs proposed prior to the meeting; the original design using Titan and Centaur upper stages became the A-1, while another model replacing the Titan with a cluster of IRBMs became A-2. The B-1 design proposed a new second stage replacing the A-2s cluster with a new four-engine design using the H-1 like the lower stage. Finally, there were three C-series models that replaced all of the upper stages with liquid hydrogen ones. The C-1 used

4896-427: The Saturn, and finally, the ultimate development, a cluster using the F-1 with 6 million pounds-force (27 MN) of thrust. The report went on to outline a crewed exploration program using these rockets as they become available; using existing ICBMs a small four-man space station could be operational 1961, the clusters would support a crewed lunar landing in 1965-1966 and a larger 50-man space station by 1967, while

4998-477: The Space Shuttle. This review was the first major milestone in the design process, and was intended to ensure that the Ares I launch system met all the requirements necessary for the Constellation Program. In addition to the release of the review, NASA also announced that a redesign in the tank hardware was made. Instead of separate LH 2 and LO 2 tanks, separated by an "intertank" like that of

5100-537: The Vega and Centaur upper stages, as well as the Juno V and their own Nova boosters. Vega was later cancelled when information on the formerly secret Agena upper stage was released (then known as "Hustler"), and it had performance roughly comparable to NASA's design. Progress on the Saturn design seemed to go smoothly. In April 1959, the first H-1 engines started arriving at ABMA, and test firings started in May. Construction of

5202-601: The atmosphere. General characteristics Engine The S-IV second stage was powered by six RL10 rocket engines burning liquid hydrogen (LH 2 ) as fuel with LOX as oxidizer, mounted on gimbals. The propellant tanks used a single, common bulkhead to separate the LOX and LH 2 propellant tanks, saving 20% of structural weight along with the associated length and complexity of construction. General characteristics Engine Saturn I Block I vehicles (SA-1 to SA-4) were guided by instruments carried in canisters on top of

SECTION 50

#1732790227676

5304-474: The blockhouse was high as no launch vehicle to date had been successful on the first attempt and there was the widespread fear of a pad explosion. As the Saturn was the largest booster yet flown, such an event was sure to be extremely destructive, possibly putting the launch complex out of use for six months. In the end, however, these worries subsided as the booster lifted and performed a flawless test flight. Three more flights with dummy upper stages followed over

5406-514: The disconnection of the stages during ascent. The grain design was also changed, and so were the insulation and liner. By the Ares I first stage ground test, the case, grain design, number of segments, insulation, liner, throat diameter, thermal protection systems and nozzle had all changed. The upper stage, derived from the Shuttle's External Tank (ET) and based on the S-IVB stage of the Saturn V,

5508-691: The engines would save about $ 60 million and as much as two years of research and development time. von Braun had earlier referred to Redstone and Jupiter rockets being used as space launchers as the Juno I and Juno II , respectively, and had submitted proposals for multi-stage versions as the Juno III and IV. He changed the name of the new design to Juno V . The total development cost of $ 850 million ($ 5.6 billion in year-2007 dollars) between 1958 and 1963 also covered 30 research and development flights, some carrying crewed and uncrewed space payloads. Satisfied with

5610-448: The existing S-I clustered lower, adding the new S-IV stage with four new 15,000 to 20,000 lbf (67 to 89 kN) engines, and keeping the two-engine Centaur on top, now to be known as the S-V stage. The C-2 model added a new S-III stage with two new 150,000 to 200,000 lbf (670 to 890 kN) engines, keeping the S-IV and S-V on top. Finally, the C-3 configuration added the S-II stage with four of these same engines, keeping only

5712-402: The existing efforts and write up recommendations. The committee presented their report on 18 July 1958, starting with a criticism of how the US program had been mishandled to date and pointing out that the Soviet program was definitely ahead. It went on to describe five "generations" of rockets, starting with the early Vanguard, through the Juno, ICBMs like Atlas and Titan, clustered designs like

5814-418: The first stage solid rocket of the Ares I could have created high vibrations during the first few minutes of ascent. The vibrations would have been caused by thrust oscillations inside the first stage. NASA officials had identified the potential problem at the Ares I system design review in late October 2007, stating in a press release that it wanted to solve it by March 2008. NASA admitted that this problem

5916-495: The ground for test and evaluation for use in later flights. The ST-90 stabilized platform was the active IMU for SA-5 and the first stage of SA-6. The ST-124 was the passenger on SA-5 and active for the second stage of SA-6 and subsequent missions. The IU had an optical window to allow alignment of the inertial platform before launch. The S-V stage was intended to be powered by two RL-10A-1 engines burning liquid hydrogen as fuel and liquid oxygen as oxidizer. The propellant tanks used

6018-432: The idea of taking over the team. As the parties continued discussions over the next week an agreement was hammered out; von Braun's team at ABMA would be kept together and continue working as the lead developers of Saturn, but the entire organization would be transferred to NASA's management. By a presidential executive order on 15 March 1960, ABMA became NASA's George C. Marshall Space Flight Center (MSFC). In July 1959,

6120-401: The largest of the rockets would support large Moon expeditions in 1972, set up a permanent Moon base in 1973–1974, and launch crewed interplanetary trips in 1977. In December 1958, all of the teams gathered to present their designs. NASA selected von Braun's proposal on 6 January 1959, giving it a vital boost. At the end of January, NASA outlined their complete development program. This included

6222-402: The lead contractor on the stage by the deadline of 29 February 1960. NASA administrator T. Keith Glennan decided on 19 April that Douglas Aircraft Company would be awarded the contract. Convair had come in a close second but Glennan did not want to monopolize the liquid hydrogen-fueled rocket market as Convair was already building the Centaur stage of the Atlas-Centaur rocket. In the end,

SECTION 60

#1732790227676

6324-401: The lunar interior. (* See List of artificial objects on the Moon for location.) The second stage of the Ares I rocket and the proposed Earth Departure Stage (EDS) would have had some of the characteristics of the S-IVB stage, as both would have had an uprated J-2 engine, called the J-2X, with the latter performing the same functions as that of the Series 500 version of the stage (placing

6426-464: The motor was cooled to a core temperature of 40 degrees Fahrenheit (4 degrees Celsius), and for DM-3 it was heated to above 90 degrees Fahrenheit (32 degrees Celsius). In addition to other objectives, these two tests validated Ares motor performance at extreme temperatures. NASA conducted a successful 500-second test firing of the J-2X rocket engine at John C. Stennis Space Center in November 2011. The Ares I prototype, Ares I-X , successfully completed

6528-482: The needed heavy-lift capability in the short term. As ABMA commander John B. Medaris put it: Looking to head off the cancellation, Saturn supporters from the DoD and ARPA drafted their own memo arguing against the cancellation. Working against them was the fact that neither the Army nor NASA had any in-writing requirement for the booster at that time. A three-day meeting between 16 and 18 September 1959 followed, where York and Dryden reviewed Saturn's future and discussed

6630-410: The new 220-inch (5.6 m) stage to produce the "new" S-IV of roughly the same performance as the original four upgraded engines. A large number of small engines are less efficient and more problematic than a smaller number of large engines, and this made it a target for an early upgrade to a single J-2 . The resulting stage, the S-IVB , improved performance so much that the Saturn was able to launch

6732-424: The new design, then known simply as "Super-Jupiter". Several variations were proposed, using a common clustered first stage, and upper stages based on either the Atlas or Titan I . ABMA favored the Titan as the Atlas production was extremely high-priority and there was little or no excess capacity to spare. They proposed using the existing Titan tooling at 120-inch (3.0 m) diameter, but lengthening it to produce

6834-433: The next 17 months, which were all completely or mostly successful. Two of them had the S-IV filled with water and detonated at high altitude after stage separation to form an ice cloud that was then photographed. Flight #5 in January 1964 was the first to carry a live S-IV, which restarted its engine in orbit to boost to a high altitude where it would remain until decaying two years later. Another two flights followed during

6936-446: The only Saturn rocket stage still currently operating. General characteristics Engine For further launches of Saturn-1 series vehicles, see the Saturn IB page. As of 2021 , there are three locations where Saturn I test vehicles (or parts thereof) are on display: SA-T First Saturn I Static Test stage. Manufactured at Marshall Space Flight Center, used in several MSFC static firing tests from 1960, then shipped and used at

7038-399: The outcome, ARPA Order Number 14-59, dated 15 August 1958, ordered the program into existence: This was followed on 11 September 1958 with another contract with Rocketdyne to start work on the H-1. On 23 September 1958, ARPA and the Army Ordnance Missile Command (AOMC) drew up an additional agreement enlarging the scope of the program, stating "In addition to the captive dynamic firing..., it

7140-408: The payload into orbit, and later firing the spacecraft into trans-lunar space). The MS-IVB was a proposed modification of the S-IVB that would have been used on a Mars flyby, but it was never produced. Saturn I The Saturn I was a rocket designed as the United States' first medium lift launch vehicle for up to 20,000-pound (9,100 kg) low Earth orbit payloads . Its development

7242-417: The plan for having two competing teams. These plans were discarded by incoming administrator Michael Griffin , and on April 29, 2005, NASA chartered the Exploration Systems Architecture Study to accomplish specific goals: A Shuttle-derived launch architecture was selected by NASA for the Ares I. Originally, the crewed vehicle would have used a four-segment solid rocket booster (SRB) for the first stage, and

7344-613: The point where US lift capability would surpass the Soviets, after being behind since Sputnik . The Saturn project was started as one of a number of proposals to meet a new Department of Defense (DoD) requirement for a heavy-lift vehicle to orbit a new class of communications and "other" satellites. The requirements called for a vehicle capable of putting 20,000 to 40,000 pounds (9,100 to 18,100 kg) into orbit, or accelerating 13,200 to 26,200 pounds (6,000 to 11,900 kg) to trans-lunar injection . Existing U.S. launchers could place

7446-498: The prime contractor for the Ares I first stage. NASA announced that Rocketdyne would be the main subcontractor for the J-2X rocket engine on July 16, 2007. NASA selected Boeing to provide and install the avionics for the Ares I rocket on December 12, 2007. On August 28, 2007, NASA awarded the Ares I Upper Stage manufacturing contract to Boeing. The upper stage of Ares I was to have been built at Michoud Aerospace Factory , which

7548-598: The problem in April 1957. They calculated that a rocket with the required performance would require a lower-stage booster with a thrust of about 1.5 million pound-force (6.7 MN) thrust at takeoff. As it happened, the Air Force had recently started work on just such an engine, eventually emerging as the F-1 . But the F-1 would not be available in the time frame that the DoD was demanding and would be limited to about 1 million lbf in

7650-450: The roles of the Titan C and Nova. The outcome was equally unexpected; York agreed to defer the cancellation and continue short-term funding, but only if NASA agreed to take over the ABMA team and continue development without the help of the DoD. NASA was equally concerned that by relying on third parties for their boosters they were putting their entire program in jeopardy, and were very open to

7752-552: The same diameter. However, the perception was that the first stage was a cluster of propellant tanks engineered from older rocket designs, leading critics to jokingly refer to it as " Cluster's Last Stand" , a play on the nickname for the Battle of the Little Bighorn , "Custer's Last Stand". Von Braun returned the design to DoD in December 1957 as A National Integrated Missile and Space Vehicle Development Program , outlining

7854-488: The same rocket, the plans for Project Constellation outlined having two separate launch vehicles, the Ares I and the Ares V, for crew and cargo, respectively. Having two separate launch vehicles allows for more specialized designs for the crew and heavy cargo launch rockets. The Ares I rocket was specifically being designed to launch the Orion Multi-Purpose Crew Vehicle . Orion was intended as

7956-502: The short term anyway. Another possibility was a Rocketdyne engine, then known as the E-1 , which provided about 360,000 to 380,000 lbf (1,600 to 1,700 kN), four of which would reach the required thrust levels. This approach became the favorite and was paired with a first stage built from a cluster of nine tanks placed atop a thrust plate where the engines and plumbing would be attached. The design envisaged eight rocket tanks similar to

8058-445: The spray-on foam insulation to keep venting to a minimum. The only new hardware on the original ET-derived second stage would have been the thrust assembly for the J-2X engine, new fill/drain/vent disconnects for the fuel and oxidizer, and mounting interfaces for the solid-fueled first stage and the Orion spacecraft. Using a concept going back to the Apollo program, the "intertank" structure was dropped to decrease mass, and in its place,

8160-454: The time, both the Air Force and US Army had teams developing such vehicles, the Army's Saturn and the Air Force's Space Launching System (SLS). The SLS used a set of common modular components with solid fuel boosters and hydrogen/oxygen upper stages to allow a wide variety of launch configurations and payload weights. Both groups had also developed plans for crewed lunar bases, ABMA's Horizon with its Earth Orbit Rendezvous method of building

8262-528: The year with boilerplate Apollo CSMs. By this point, however, the advent of the Titan III had robbed the Saturn of a role as a DoD launcher and with the newer, improved Saturn IB in development (as the Apollo CSM ended up being heavier than originally expected and so needed a more powerful launch vehicle), the booster quickly became orphaned and no practical use could be found for it. The main payload of

8364-651: Was $ 445 million. Originally scheduled for first test flights in 2011, the independent analysis by the Augustine Commission found in late 2009 that due to technical and financial problems Ares I was not likely to have had its first crewed launch until 2017–2019 under the current budget, or late 2016 with an unconstrained budget. The Augustine Commission also stated that Ares I and Orion would have an estimated recurring cost of almost $ 1 billion per flight. However, later financial analysis in March 2010 showed that

8466-769: Was 10,000 kilograms (22,000 lb) Attitude control was provided by J-2 engine gimbaling during powered flight and by the two APS modules during coast. APS modules were used for three-axis control during coast phases, roll control during J-2 firings, and ullage for the second ignition of the J-2 engine. Each APS module contained two 150-pound-force (670 N) thrusters providing thrust for roll and pitch, another 150-pound-force thruster for yaw, and one 70-pound-force (310 N) thruster for ullage. Each module contained its own propellant tanks of 150 pounds (68 kg) dinitrogen tetroxide and 115 pounds (52 kg) monomethyl hydrazine as well as compressed helium to pressurize its propellants. A surplus S-IVB tank, serial number 212,

8568-454: Was also considered as a short range ballistic missile system in the TABAS concept. TABAS armed the Saturn with 25 metric tons (55,000 lb) of conventional weapons in a mechanical carrier system that ensured that the missile would hit and destroy an enemy runway, knocking it out of action for three days. The system was considered too dangerous to deploy; when launched it would appear to be

8670-474: Was also shipped and used for checkout at LC-37B at Cape Canaveral in 1963. It was returned to Alabama and modified for use as an S-IB dynamic test stage. Donated by NASA/MSFC to the State of Alabama at the same time as the Saturn V dynamic test vehicle and now on display in a vertical position at the U.S. Space and Rocket Center (formerly Alabama Space and Rocket Center), Huntsville, Alabama, where it has become

8772-429: Was approximately 18 inches (46 cm) in diameter and 36 inches (91 cm) long, and took advantage of upgraded insulation materials that had improved thermal properties to protect the igniter's case from the burning solid propellant. NASA successfully completed test firing of the igniter for the Ares I engines on March 10, 2009, at ATK Launch Systems test facilities near Promontory, Utah . The igniter test generated

8874-485: Was assembled. Similarly, an order for two additional 500-series stages (for Saturn V rockets 516 and 517) was canceled around the same time. Douglas built two distinct versions of the S-IVB, the 200 series and the 500 series. The 200 series was used by the Saturn IB and differed from the 500 in that it did not have a flared interstage and it had less helium pressurization on board since it did not have to be restarted. In

8976-469: Was being used. One early ARPA report noted: "The SATURN is considered to be the first real space vehicle as the Douglas DC-3 was the first real airliner and durable work-horse in aeronautics". The name change became official in February 1959. The formation of NASA on 29 July 1958 led to an effort to collect the existing heavy-launch rocket programs and select a single set of designs for future work. At

9078-421: Was converted into the hull for Skylab , the first American space station . Skylab was launched on a Saturn V on May 14, 1973, and it eventually reentered the atmosphere on July 11, 1979. A second S-IVB, serial number 515, was also converted into a backup Skylab , but this one never flew. From Apollo 13 onward, the S-IVB stages were crashed into the Moon to perform seismic measurements used for characterizing

9180-484: Was critical, especially in the original J-2 engine used on the Saturn V's S-IVB stage, to propel the Apollo spacecraft to the Moon. The Space Shuttle Main Engine, on the other hand, would have required extensive modifications to add an air-start capability On January 4, 2007, NASA announced that the Ares I had completed its system requirements review, the first such review completed for any crewed spacecraft design since

9282-452: Was fair game, and "If these propellants are to be accepted for the difficult top-stage applications", the committee concluded, "there seem to be no valid engineering reasons for not accepting the use of high-energy propellants for the less difficult application to intermediate stages". The Committee outlined a number of different potential launch configurations, grouped into three broad categories. The "A" group were low-risk versions similar to

9384-555: Was in charge of the requirements. ARPA asked for only one change to the design; concerned that the E-1 was still in early development, they suggested looking at alternatives in order to ensure the rocket would enter production as soon as possible. ABMA quickly responded with a slightly modified design replacing the four E-1's with eight H-1 engines, a minor upgrade to the S-3D engine used on Thor and Jupiter missiles. They estimated that changing

9486-427: Was predicted to have been a fraction of the Shuttle's marginal costs even had it flown multiple times per year. By comparison, the cost of launching three astronauts on a crewed Russian Soyuz is $ 153 million. Representative Robert Aderholt stated in March 2010 that he had received a letter from NASA which claimed that it would have cost $ 1.1 billion to fly the Ares I rocket three times a year. On February 8, 2011, it

9588-460: Was replaced by the heavy lift derivative Saturn IB , which used a larger, higher total impulse second stage and an improved guidance and control system . It also led the way to development of the super-heavy lift Saturn V which carried the first men to landings on the Moon in the Apollo program . President John F. Kennedy identified the Saturn I, and the SA-5 launch in particular, as being

9690-532: Was reported that Alliant Techsystems and Astrium proposed to use Ares I's first stage with a second stage derived from the Ariane 5 core stage to form a new rocket named Liberty . On February 1, 2010, President Barack Obama announced a proposal to cancel the Constellation program effective with the U.S. 2011 fiscal year budget, but later announced changes to the proposal in a major space policy speech at Kennedy Space Center on April 15, 2010. In October 2010,

9792-558: Was taken over from the Advanced Research Projects Agency (ARPA) in 1958 by the newly formed civilian NASA . Its design proved sound and flexible. It was successful in initiating the development of liquid hydrogen -fueled rocket propulsion, launching the Pegasus satellites , and flight verification of the Apollo command and service module launch phase aerodynamics. Ten Saturn I rockets were flown before it

9894-417: Was that the DoD preferred to have a launch vehicle that they were in complete control of instead of having to share the Saturn with NASA (of all Titan III/ IV vehicles launched during its 40-year run, only a handful carried NASA payloads). Likewise, the development of the Titan III eliminated the need for the "flexible" staging concepts of the Saturn, which was now only intended to be used for crewed launches in

9996-450: Was the prime contractor for the original J-2 engines used in the Apollo program. Although its J-2X engine was derived from an established design, the upper stage itself would have been wholly new. Originally to have been based on both the internal and external structure of the ET, the original design called for separate fuel and oxidizer tanks, joined by an "intertank" structure, and covered with

10098-441: Was to be propelled by a single J-2X rocket engine fueled by liquid hydrogen (LH 2 ) and liquid oxygen (LOX). The J-2X was derived from the original J-2 engine used during the Apollo program, but with more thrust (≈294,000 lbf or 1.31 MN) and fewer parts than the original engine. On July 16, 2007, NASA awarded Rocketdyne a sole-source contract for the J-2X engines to be used for ground and flight tests. Rocketdyne

10200-410: Was to have continued through the end of 2009, with development and qualification testing running concurrently through 2012. As of July 2009 , flight articles were to have begun production towards the end of 2009 for a first launch in June 2011. Since 2006 the first launch of a human was planned for no later than 2014, which is four years after the planned retirement of the Space Shuttle. Delays in

10302-618: Was used for the Space Shuttle's External Tank and the Saturn V's S-IC first stage. At approximately US$ 20–25 million per engine, the Rocketdyne-designed and produced J-2X would have cost less than half as much as the more complex RS-25 engine (around $ 55 million). Unlike the Space Shuttle Main Engine, which was designed to start on the ground, the J-2X was designed from inception to be started in both mid-air and in near-vacuum. This air-start capability

10404-427: Was very severe, rating it four out of five on a risk scale, but the agency was very confident in solving it. The mitigation approach developed by the Ares engineering team included active and passive vibration damping, adding an active tuned-mass absorber and a passive "compliance structure" – essentially a spring-loaded ring that would have detuned the Ares I stack. NASA also pointed out that, since this would have been

#675324