Misplaced Pages

East–West MRT line

Article snapshot taken from Wikipedia with creative commons attribution-sharealike license. Give it a read and then ask your questions in the chat. We can research this topic together.
#936063

133-546: The East–West Line ( EWL ) is a high-capacity Mass Rapid Transit (MRT) line operated by SMRT in Singapore , running from Pasir Ris station in the east to Tuas Link station in the west , with an additional branch between Changi Airport and Tanah Merah stations. It is the second Mass Rapid Transit line to be built in Singapore . Coloured green on the rail map, the line serves 35 stations, 8 of which (from Lavender to Tiong Bahru and Changi Airport stations) are underground. At 57.2 kilometres (35.5 mi),

266-456: A C151 train approaching Pasir Ris station, resulting in a temporarily service delay between Tanah Merah and Pasir Ris for over two hours that affected at least 10,000 commuters. The two trainee staff had joined SMRT in January 2016 and worked as technicians under a technical team of 15 staff led by a supervisor and were tasked to go down to the tracks to investigate an alarm triggered by

399-546: A Relay interlocking system that prevents incorrect signal and track points to be set. The stretch of track between Pioneer and Tuas Link stations was equipped with the new signalling system which came into use in June 2017. As the section of track between Pioneer and Joo Koon support 'mixed-mode' of both signalling systems, trains terminating at either Joo Koon or Tuas Link would have to change signalling modes at Pioneer MRT station as trains terminating at Joo Koon would proceed to

532-580: A computer-based interlocking (CBI) system that prevents incorrect signal and track points to be set. The old signalling system has undergone decommissioning work from August 2018 and was completed on 23 November 2018. It consists of Westinghouse fixed block signalling system with Automatic train control (ATC) under Automatic train operation (ATO) GoA 2. The subsystems consist of Automatic train protection (ATP) to govern train speed, Automatic Train Supervision (ATS) to track and schedule trains and

665-497: A "sculptural and dynamic" manner, which the designers believed would give the impression of "gateways" into the neighbourhood. The station was praised for its "excellent design" for its "refined" detailing and ingenious usage of colours and textures, while fulfilling the "restrictive" demands around the area. The station design won the Singapore Institute of Architects Design Awards 2020, with the institute's jury citing

798-487: A 2-station shuttle service from Tanah Merah station, then briefly converted to a through service from Boon Lay station when the branch extended to Changi Airport station. However, due to ridership falling below expectations, the service was reverted into shuttle mode on 22 July 2003. On the DTL, the station is the current terminus on the line, with the next station being Upper Changi station. The DTL extension to Sungei Bedok

931-555: A comprehensive rail network as the backbone of the country's public transportation system , averaging a daily ridership of 3.45 million in 2023. The MRT network encompasses approximately 241 km (150 mi) of grade-separated route on standard gauge . As of 2024, there are currently 141 operational stations dispersed across six operational lines arrayed in a circle-radial topology . Two more lines and 46 stations are currently under construction, in addition to ongoing extension works on existing lines. In total, this will schedule

1064-567: A few days of the weekend. The nightly closures are used for maintenance. During the COVID-19 pandemic across the country , train services ended earlier from 7 April 2020 to 1 June 2020 and service extensions on the eves of public holidays ceased from 7 April 2020 until 28 September 2024 except New Year's Eve. Train service extensions were reinstated back to before the pandemic began in 2020 as mentioned earlier. Train frequencies are 2 - 3 mins during peak hours and 5 - 6 mins during off-peak hours. If

1197-770: A few paintings or sculptures representing the recent past of Singapore, mounted in major stations. The opening of the Woodlands Extension introduced bolder pieces of artwork, such as a 4,000 kg sculpture in Woodlands . With the opening of the North East Line in 2003, a series of artworks under a programme called "Art in Transit" were commissioned by the Land Transport Authority (LTA). Created by 19 local artists and integrated into

1330-683: A more common feature worldwide. They were first installed at Jurong East , Pasir Ris , and Yishun stations in 2009 as trial runs . On 31 August 2011, the LTA announced completion of the installation of PSDs along the East–West Line, with Expo being the last station on the line to receive the PSDs. Installation of PSDs across both the North–South and East–West lines (NSEWL) were completed on 14 March 2012, 3 months ahead of schedule. The timber sleepers on

1463-528: A new infill station located between Buona Vista station and Clementi station , namely Dover station , began in June 1998. It is the first station in the MRT network to be built as an infill station. The building of the station was met with reservations by some members of the public over the small area it serviced and there were criticisms over the spending of " taxpayers' money " chiefly for use only by students of one educational institution. Despite some opposition,

SECTION 10

#1732775838937

1596-504: A new platform will be constructed at Tanah Merah, enabling faster travel and shorter waiting times for commuters heading towards Expo and Changi Airport on the Changi Airport branch line of the East–West Line. On 26 October 2016, the Land Transport Authority awarded the civil contract to Lum Chang Building Contractors Pte. Ltd. to build a new platform at Tanah Merah and viaducts for a contract sum of S$ 325 million. In addition to

1729-556: A plan to introduce dual speeds to escalators along the North–South and East–West lines, to make it safer for senior citizens using them. As a result, all escalators on the two lines, through a refurbishment programme, will be able to operate at a different speed of 0.5 m/s during off-peak hours, with completion being targeted for 2022. All stations constructed before 2001 initially lacked barrier-free facilities and wider AFC faregates such as lifts, ramps and tactile guidance systems for

1862-430: A possible signalling equipment fault close by the station. An operator cited that they were granted access to the tracks, but did not coordinate with a Signal Unit in the station to ensure trains could not travel in the area where the team was. Patrick Nathan, SMRT vice-president, promised that "SMRT will review all safety protocols particularly those involving track access". SMRT chief executive Desmond Kuek apologised for

1995-578: A preference. The Land Transport Authority (LTA) had considered other naming methods in June 2007, whether by name, colour or numbers. After the survey, however, the naming scheme was retained and used for subsequent future MRT lines. Except for the partly at-grade Bishan MRT station ( North–South Line ), the entirety of the MRT is either elevated or underground. Most below-ground stations are deep and hardened enough to withstand conventional aerial bomb attacks and to serve as bomb shelters . Mobile phone, 3G, 4G and 5G services are available in every part of

2128-399: A section between Jurong East and Clementi station and five tracks nearby Changi Depot and Tanah Merah station. Some stations are commonly placed at the middle of the roads such as Tanah Merah , Bedok , Queenstown , Commonwealth , Dover , Clementi , Pioneer , Joo Koon , Gul Circle , Tuas Crescent and Tuas West Road . The line runs mostly on overhead viaducts but goes underground in

2261-467: A single track before turning eastwards to Expo station. After Expo station , it goes underground and curves south before terminating at Changi Airport station. The East–West Line was constructed along the North–South Line . As such, both lines used identical signalling equipment and rolling stock . The line serves 35 stations across 57.2 kilometres (35.5 mi) of track, and station codes for

2394-499: A station interlocking system. The ATO drives the train in automatic mode, providing the traction and braking control demands to the train rolling stock system, adjusts its speed upon approaching the station, and provides the control of opening and closing of train and platform screen doors once the train has stopped at the station. The ATP ensures safe train separation by using the ATP track circuit status and by location determination, monitors

2527-640: A stretch near Clementi MRT station . A defective train axle box on one of the first generation C151 trains , which had been deadheading to Ulu Pandan Depot after it was withdrawn at Clementi station, dropped onto the tracks near Dover station and caused the wheels of a bogie - an undercarriage - to come off the running rail and hit track equipment, including stretches of the third rail , 3 point machines as well as power cables and rail clips. In an update at about 9:30pm on 25 September 2024, LTA and SMRT announced that train services between Buona Vista and Jurong East would remain suspended on 26 September 2024,

2660-637: A turn back siding which was built as part of the TWE which only supports the new signalling system. Eastbound trains towards Pasir Ris would have to change back to the old signalling system at Pioneer MRT station. This procedure was removed after the train collision at Joo Koon as trains terminated at Joo Koon. The new signalling system became fully operational on 28 May 2018. When the line was first opened, full-height platform screen doors supplied by Westinghouse were installed at underground stations. These doors serve to prevent suicides, enable climate control within

2793-518: A two-year contract for consultancy in November 1982. The Mass Rapid Transit Corporation (MRTC)—later renamed SMRT Corporation—was established on 14 October 1983 and took over the roles and responsibilities of the former provisional Mass Rapid Transit Authority. On 7 November 1987, the first section of the North–South Line started operations, consisting of five stations over six kilometres. Within

SECTION 20

#1732775838937

2926-489: A year, 20 more stations had been added to the network and a direct service existed between Yishun and Lakeside stations, linking up Central Singapore to Jurong in the west by the end of 1988. The direct service was eventually split into the North–South and East–West lines after the latter's completion of the eastern sector to Tanah Merah station. By the end of 1990, the Branch line has further linked Choa Chu Kang to

3059-439: Is 2 to 3 minutes while during non-peak hours the frequency is reduced to 5 minutes throughout the entire route. The first train departs from these places: Train services on the East–West Line are also subjected to maintenance and renewal works, usually on selected Fridays, Saturdays or Sundays. Shuttle bus services may be provided throughout the duration of the early closures and late openings for affected commuters. Operations of

3192-597: Is a Mass Rapid Transit (MRT) interchange station on the East West line (EWL) and Downtown line (DTL) in the Tampines planning area , Singapore. The station lies between Changi City Point and the Singapore Expo , located along Changi South Avenue 1 at the junction of Expo Drive. The station is part of the two-station branch line which extends from Tanah Merah to Changi Airport station . Plans to connect

3325-588: Is able to support bidirectional train operations on a single track, enabling trains to be diverted onto another track in the event of a fault on one track. The CBTC system also permits for improved braking performance in wet weather as compared to the original fixed-block ATC. All new MRT lines built since the North East Line in 2003 were equipped with CBTC from the outset, and have the capability to be completely driverless and automated, requiring no on-board staffing. Operations are monitored remotely from

3458-769: Is currently used for the Downtown line . While major operations were shifted to the main Gali Batu Depot in 2015, the Tai Seng Facility Building resumed stabling operations with the extension of the Downtown line in 2017. It currently operates independently from Kim Chuan Depot. Gali Batu Depot is the first MRT depot in Singapore to achieve the certification of Building and Construction Authority (BCA) Green Mark Gold. In August 2014, plans for

3591-491: Is planned to begin operations in 2026, adding an additional 2.2 kilometres (1.4 miles) and 2 stations to the line, terminating at Sungei Bedok and interchanging with the Thomson–East Coast Line. Upon opening, the entire line will be 44 kilometres (27 miles) long and have 37 stations in total. A proposal has been further mooted to extend the line from Bukit Panjang towards Sungei Kadut which will interchange with

3724-408: Is scheduled to open in 2026; the next station in that direction will be Xilin. The elevated EWL station is designed by British architectural firm Foster and Partners . The station contains a stainless-steel roof over the concourse and ticket level, measuring 40 metres (130 ft) in diameter, which overlaps with a 130-metre (430 ft) long titanium roof over the platform level. The roof above

3857-554: Is set to be completed by mid-2024. On 5 August 1993, before opening, a maintenance vehicle spilt oil on the tracks between Clementi and Jurong East . The first ten eastbound trains reported braking problems, then the eleventh train from Jurong stopped at the Clementi station for two minutes longer than scheduled due to it using its emergency brakes to stop at the station at 7.50 am, before being hit by another eastbound train when it failed to stop in time. 156 passengers were injured by

3990-602: The East Coast Integrated Depot , the world's first four-in-one train and bus depot were announced. It will be built at Tanah Merah beside the original Changi Depot site to serve the East–West , Downtown , and Thomson–East Coast lines. The new 36 ha depot can house about 220 trains and 550 buses and integrating the depot for both buses and trains will help save close to 66.12 acres (26.76 ha), or 60 football fields of land. The Tengah Depot for

4123-700: The Jurong Region Line will be situated at the western perimeter of Tengah , and an additional depot facility will be added near Peng Kang Hill station to support the operations of the JRL. Rolling stock for the Jurong Region Line will be stabled at both facilities. Tengah Depot will house the JRL Operations Control Centre and have a bus depot integrated with it to optimise land use. The Changi East Depot will serve

East–West MRT line - Misplaced Pages Continue

4256-496: The Land Transport Authority proceeded with the construction to serve commuters along Singapore Polytechnic with Dover housing estate. The station opened on 18 October 2001. Prior to opening, test runs were conducted from 13 to 17 October 2001 when the trains stopped at the station but did not open their doors. The idea of extending the Mass Rapid Transit system to Changi Airport was reconsidered when Terminal 3 of

4389-532: The Light Rail Transit (LRT) system — which, along with public buses , complement the mainline by providing a last mile link between MRT stations and HDB public housing estates . The MRT is the oldest, busiest, and most comprehensive metro system in Southeast Asia . Capital expenditure on its rail infrastructure reached a cumulative S$ 150 billion in 2021, making the network one of

4522-664: The National Fire Protection Association in the United States . Full-height platform screen doors were already installed in underground stations since 1987, supplied by Westinghouse . There were calls for platform screen doors to be installed at elevated stations after several incidents in which passengers were killed by oncoming trains when they fell onto the railway tracks at elevated stations. The authorities initially rejected such calls by casting doubts over functionality and concerns about

4655-633: The Workplace Safety and Health Act for lapses which led to the accident, and were fined $ 400,000 respectively. and $ 55,000. On 20 July 2018, the Land Transport Authority fined the operator S$ 1.9 million (US$ 1.41 million) for this incident and the Bishan tunnel flooding . A second train collision occurred on 15 November 2017 at approximately 8.18am, where two C151A trains collided at Joo Koon MRT station. A train fault caused

4788-470: The 1st day of the PSLE exams, while service between Boon Lay and Jurong East, and Queenstown and Buona Vista, would each run their own separate shuttle services every 10 minutes. On Thursday night, SMRT announced that no trains will run between Jurong East and Buona Vista for a third straight day, with full service expected to resume the following Monday. However, in an update at about 4:30pm on 29 September 2024,

4921-481: The Christmas and New Year's Eve falls on the weekday, train frequencies will remain the same as weekdays only during morning peak whereas it will become 5 - 6 mins until 3pm and standardised to 5 min frequency throughout the whole period until the last train. Early stages of the MRT's construction paid scant attention to station design, with an emphasis on functionality over aesthetics. This is particularly evident in

5054-509: The EWL to Changi Airport were finalised in 1996 and construction began in 1999. The station opened on 10 January 2001, a year earlier than Changi Airport station. It later became the terminus for the DTL upon the completion of Stage 3 of that line in 2017. On 25 May 2019, it was announced that the station will be incorporated into the Thomson–East Coast line (TEL), which is planned to extend to

5187-542: The East–West Line are affected by the COVID-19 pandemic , leading to the drop of ridership. As its name implies, the East–West Line connects central Singapore to both eastern and western parts of the island, with an additional branch between Changi Airport and Tanah Merah , which operates as a separate shuttle service. It is 57.2 kilometers (35.5 miles) long and it is predominantly double-tracked, but certain short sections at Tanah Merah, Outram Park and Joo Koon widens to three tracks, four tracks nearby Jurong East station and

5320-559: The East–West Line was required to be replaced as they were near the end of their 25-year lifespan. The replacement sleepers, made of concrete, have a significantly longer lifespan. To speed up works, train services on the East–West Line was adjusted to end earlier. The work was divided into three phases: Phase 1 (Bugis – Tanah Merah), Phase 2 (Joo Koon – Jurong East, Tanah Merah – Pasir Ris) and Phase 3 (Jurong East – Outram Park). The sleepers were fully replaced on 18 February 2017. A new moving-block signalling system, supplied by Thales, replaced

5453-773: The East–West Line with its own maintenance facility, while Mandai Depot services trains for the Thomson–East Coast line. The underground Kim Chuan Depot houses trains for the Circle and Downtown lines, now jointly managed by the two MRT operators. SBS Transit has three depots: Sengkang Depot houses trains for the North East line , the Sengkang LRT line , and the Punggol LRT line . Tai Seng Facility Building , connected to and located east of Kim Chuan Depot ,

East–West MRT line - Misplaced Pages Continue

5586-498: The Founders' Memorial in 2028. In addition, this line and Canberra MRT station were the first to use top-up kiosks (TUK) that only allows cashless payments, while GTMs were retained for traditional modes of payment. In addition to the previously announced alignment of the Thomson–East Coast Line, an extension has been proposed to connect it to Changi Airport , with the line passing through Terminal 5 , and eventually absorbing

5719-465: The LTA called a tender to modify the existing station, along with Tanah Merah and Changi Airport stations, in preparation for their conversion to being part of the TEL. As the name suggests, the station serves the convention centre of Singapore Expo. The elevated EWL station is located along Changi South Avenue 1 while the DTL station is underneath the junction of the road and Expo Drive. In addition to

5852-429: The MRT that did not require paintwork as the interior is mainly stone, glass or metal. The station contains a lift in a transparent shaft, as well as highly illuminated energy-saving escalators, which complement the "futuristic outlook" of the station. The futuristic design is intended to reflect the country's willingness to experiment with new ideas and technology, symbolising the "thriving world-class city" that Singapore

5985-538: The Marina Bay Extension on 14 January 2012. Stage 1 of Downtown line opened on 22 December 2013 with its official opening made on 21 December 2013 by Prime Minister Lee Hsien Loong . Stage 2 opened on 27 December 2015, after being officially opened on 26 December by Prime Minister Lee. The Tuas West Extension of the East–West Line, consisting of Gul Circle , Tuas Crescent , Tuas West Road , and Tuas Link stations, opened on 18 June 2017. Stage 3,

6118-522: The Marina Line Architectural Design Competition, which was jointly organised by the Land Transport Authority and the Singapore Institute of Architects. The competition did not require any prior architectural experience from competitors and is acknowledged by the industry as one of the most impartial competitions held in Singapore to date. The winner of both stations was WOHA . In 2009, "Best Transport Building"

6251-614: The Mass Rapid Transit (MRT) were derived from a forecast by the country's planners back in 1967 which stated the need for a rail-based urban transport system by 1992. In 1972, a study was conducted by the American firms Wilbur Smith and Associates, Parsons Brinckerhoff, Tudor, and Bechtel, which was accounted for by the World Bank on behalf of the United Nations Development Programme . The study

6384-535: The North–South Line between City Hall and Raffles Place stations, which are cross-platform interchanges to the North–South Line . After Tanjong Pagar, the line curves northwestwards towards Outram Park. After Tiong Bahru , the line continues above ground starting with Redhill station and follows the direction of Commonwealth Avenue, Commonwealth Avenue West and Boon Lay Way. Between Clementi and Jurong East station, three branches (one going east and two going west) to Ulu Pandan Depot are deployed. At Jurong East station ,

6517-579: The North–South Line, with both MRT lines having its signalling fully upgraded, converting it from semi-automatic to fully automatic. The first segment of what would become the East–West Line, between City Hall and Outram Park stations, was opened on 12 December 1987 as part of the North–South Line and Phase 1 of the initial system. Subsequently, it was extended westwards to Clementi station on 12 March 1988 and to Lakeside on 5 November 1988. The 15-kilometre (9.3 mi) eastern extension to Tanah Merah station opened on 4 November 1989, which also marked

6650-496: The North–South Line. On 14 March 2012, platform screen doors became operational at all elevated stations on the East–West Line. Stations along the TWE had half-height platform screen doors manufactured by Fangda installed during the station's construction. Mass Rapid Transit (Singapore) [REDACTED] The Mass Rapid Transit system, locally known by the initialism MRT , is a rapid transit system in Singapore and

6783-546: The North–South Line. The extension is expected to be completed by the mid-2030s. Stage 5 from Bedok South to Sungei Bedok is planned to be operational by 2026. The northern terminus of Woodlands North is expected to interchange with the Johor Bahru–Singapore Rapid Transit System for greater connectivity between Johor Bahru and Woodlands , while Founders' Memorial station is an infill station along Stage 4, scheduled to open in tandem with

SECTION 50

#1732775838937

6916-607: The Singapore Expo, the station serves the retail development of Changi City Point, as well as various offices in Changi Business Park such as UE Bizhub East, IBM Place and DBS Asia Hub. The station is an interchange station on the EWL and DTL. On the EWL, the station is between the Tanah Merah and Changi Airport stations on the Changi Airport branch. Train services to Expo station initially operated as

7049-458: The Tuas West extension, an extension of the East–West Line from Joo Koon to Tuas Link was announced. The extension has a span of 7.5 kilometres (4.7 mi), which spans a twin-tracked MRT viaduct, four above-ground stations and a 26-hectare depot to provide stabling and maintenance facilities for the additional trains that will be bought for the extension and to cater for future expansion of

7182-536: The adjacent East Coast Integrated Depot . The extension is expected to provide better public transport service to Changi Business Park. On 25 May 2019, as part of the Land Transport Masterplan 2040, the LTA announced that the stretch between Tanah Merah and Changi Airport would also be part of the proposed Thomson–East Coast line (TEL) extension to Changi Airport from Sungei Bedok station via the future Changi Airport Terminal 5. On 29 April 2024,

7315-480: The airport was being built. Earlier plans had long been made for a new line branching off from the existing East–West Line at Tanah Merah , with some conceptual plans showing a tentative route alignment up to the airport along Airport Boulevard, continuing beyond the airport to Changi Point, before turning southwest back towards the city along the eastern coasts. The plans were finally announced by then Deputy Prime Minister Lee Hsien Loong on 15 November 1996. However,

7448-573: The airport's Terminal 5 by 2040. In 1994, there were plans to build a new rail connection to Changi Airport. The alignment of the two-station branch, which included Expo station, was finalised through an announcement by Deputy Prime Minister Lee Hsien Loong on 15 November 1996. Contract 502 for the construction of Expo station and 1.4 kilometres (0.87 miles) of track was awarded to a joint venture between Penta-Ocean Construction Limited and L&M Prestressing Pte Ltd for S$ 62.6 million (US$ 37.4 million). The station opened on 10 January 2001 upon

7581-540: The assets owned by the Land Transport Authority , a statutory board of the Government of Singapore . The network was planned to be constructed and opened in stages, even as plans had already indicated the decision for two main arterial lines. The North–South Line was given priority because it passed through the Central Area that has a high demand for public transport. De Leuw Cather was appointed to undertake

7714-610: The capacity on both the North–South and the East–West lines in order to cope with increasing ridership. Both the North–South and the East–West lines utilized identical rolling stock up until the 2010s, when the C151A trains were temporary suspended from operating on the North–South Line from January 2012 until November 2013 following the 2011 train disruptions. The C151B trains, which were introduced in April 2017, did not begin revenue service on

7847-587: The city area between Kallang and Redhill , Bedok and Kembangan , and between Expo and Changi Airport . Travelling from one end of the line to the other takes about 85 minutes. The line begins above ground at Pasir Ris station from where it continues to head south towards Simei station. The line curves between Simei to Tanah Merah stations and continues westwards, joining the Changi Airport branch, paralleling New Upper Changi Road. Two branch lines to Changi Depot and to Changi Airport station exists between Simei and Tanah Merah stations. At Tanah Merah station ,

7980-544: The collision. During the evening peak hours on 7 July 2015, train services on the East–West and North–South Lines were temporarily disrupted due to massive power trips detected along both lines. The cause of the disruption was due to damaged insulators which had resulted in the failure of the power supply. For this disruption that brought inconvenience to 413,000 commuters, LTA imposed a 'record' fine of S$ 5.4 million on SMRT. At about 11:08 a.m. on 22 March 2016, two SMRT track-maintenance trainee staff were run over and killed by

8113-400: The concourse reflects sunlight into the station, reducing the need for artificial lighting, while the platform canopy deflects heat from the sun, cooling the platform by up to 4 °C (7.2 °F) compared to its surroundings. The materials of the roofs were adapted to Singapore's climate. The station's large interior allows natural lighting and ventilation. Expo station is the first on

SECTION 60

#1732775838937

8246-418: The deaths of four workers. On 15 November 2017, two trains, one being empty, collided at low speed at Joo Koon station due to a malfunction with the communications-based train control (CBTC). Prior to the 2020 circuit breaker measures during the early stages of the COVID-19 pandemic , the public transport operators and LTA were criticised by some commuters for its delayed actions of crowd control and

8379-517: The doors and are operational. These doors prevent suicides and unauthorised access to restricted areas. There were a few major incidents in the history of the MRT, which opened in 1987. On 5 August 1993, two trains collided at Clementi station because of an oil spillage on the track, which resulted in 132 injuries. During the construction of the Circle Line on 20 April 2004, a tunnel being constructed under Nicoll Highway collapsed and led to

8512-675: The early network is elevated above ground on concrete viaducts , with a small portion running at-grade; newer lines are largely subterranean, incorporating several of the lengthiest continuous subway tunnel sections in the world. A number of underground stations double as purpose-built air raid shelters under the operational authority of the Singapore Civil Defence Force (SCDF); these stations incorporate deep-level station boxes cast with hardened concrete and blast doors fashioned out of reinforced steel to withstand conventional aerial and chemical ordnance. The origins of

8645-435: The eastern terminus of the line, was announced by the Land Transport Authority on 29 Jun 2018. It would extend the railway viaduct past the station by 148 metres. The turnback will allow for an increase in service frequency during peak times from 30 to 36 trains per hour as trains will be able to change directions faster to head westwards on the line, to meet future increases in ridership demand. Construction started in 2019 and

8778-403: The elderly and disabled. A retrofitting programme was completed in 2006, with every station provided with at least one barrier-free access route. Over the years, additional barrier-free facilities have been constructed in stations. Since 2020, newer MRT stations have been fitted with a minimum of two lifts. Operators and authorities have stated that numerous measures had been taken to ensure

8911-484: The enforcement of social distancing on public transport. In response, the LTA rolled out a series of precautionary measures, such as social distancing measures and making the wearing of masks in public transport mandatory. Social distancing markers were progressively implemented in the MRT trains and stations which commuters must adhere to; enforced by auxiliary officers and transport ambassadors. The significant reduction of commuters as remote work increased resulted in

9044-502: The entire day on 16 November 2017, and westbound trains temporarily terminated at Joo Koon . An update by the Land Transport Authority (LTA) & SMRT on 16 November 2017 stated that LTA and SMRT had decided to isolate for up to one month the operations of the Tuas West extension, which runs on the new signalling system, from the rest of the East–West Line, which runs on the old signalling system, enabling LTA engineers to carry out further assurance checks together with Thales. The train

9177-421: The exception of selected periods, such as New Year's Eve , Chinese New Year , Deepavali , Hari Raya , Christmas , eves of public holidays and special occasions such as the state funeral of Lee Kuan Yew (2015), when most of the lines stay open throughout the night or extended till later (before the COVID-19 pandemic began in 2020). Additionally, some stretches of the line end earlier, open later and close on

9310-496: The existing Changi Airport branch on the East–West Line . With such an extension, there would be a direct connection between Changi Airport and the city. This extension is expected to start operating by 2040. Tunneling works are tendered out by the Land Transport Authority (LTA) Singapore and Shanghai Tunnel Engineering Corporation was awarded with the tunneling package for Terminal 5. Expo MRT station Expo MRT station

9443-548: The final stage of the Downtown Line, opened on 21 October 2017 with its official opening made on 20 October 2017 by Coordinating Minister for Infrastructure and Minister for Transport Khaw Boon Wan . The second infill station, Canberra station opened on 2 November 2019. Stage 1 of the Thomson–East Coast Line opened on 31 January 2020. Stage 2 of the Thomson–East Coast Line opened on 28 August 2021, extending

9576-493: The first few stages of the North–South and East–West lines that opened between 1987 and 1988 from Yio Chu Kang to Clementi . An exception to this was Orchard , chosen by its designers to be a "showpiece" of the system and built initially with a domed roof. Architectural themes became more important only in subsequent stages, and resulted in such designs as the cylindrical station shapes on all stations between Kallang and Pasir Ris except Eunos , and west of Boon Lay , and

9709-577: The first line operated by SBS Transit, opened on 20 June 2003, is one of the first fully automated heavy rail lines in the world. On 15 January 2006, after intense two-and-a-half years lobbying by the public, Buangkok station was opened, followed by Woodleigh station much later on 20 June 2011. The Boon Lay Extension of the East–West Line, consisting of Pioneer and Joo Koon stations, opened on 28 February 2009. The Circle Line opened in four stages with Stage 3 on 28 May 2009, Stages 1 and 2 on 17 April 2010, Stages 4 and 5 on 8 October 2011 and

9842-699: The first rolling stock on the East–West Line to be manufactured by Bombardier (Bought by Alstom in 2021), which has also supplied trains for the Downtown Line . The first train entered service on the East–West Line on 4 June 2023. The East–West Line is equipped with Thales SelTrac communications-based train control (CBTC) moving block signalling system with automatic train control (ATC) under automatic train operation (ATO) Grades of Automation (GoA) 3. The subsystems consist of automatic train protection (ATP) to govern train speed, NetTrac MT Automatic Train Supervision (ATS) to track and schedule trains and

9975-406: The first train heading in the direction of Tuas Link to stall at the station. A minute later, a second train stopped behind the first and then "moved forward unexpectedly," hitting the other train. Thirty-eight people, including two SMRT staff, were hospitalized. Train services between Tuas Link and Joo Koon stations were temporally suspended in both directions for two hours on the day itself and

10108-487: The former ageing fixed-block signalling system on the East–West Line. The new signalling system, costing $ 195 million, reduces waiting times for trains during peak periods from 120 seconds then to 100 seconds now. The new system became operational between Pioneer and Tuas Link stations on 18 June 2017. Newer rolling stocks, such as the C151B and C151C , are equipped for use solely on the new signalling system. Since 27 May 2018,

10241-731: The full stretch of the East–West Line until the line's trial of the CBTC signalling system in May 2018. The C151C trains, despite their introduction on 30 September 2018 on the North–South Line, only made their full day debut on the East–West Line on 4 November 2023. Another generation of rolling stock, the R151 trains, will be delivered from 2022 to 2026, to replace all 66 first-generation C151 trains which will be retired by 2026, as well as all 19 second-generation C651 and 21 third-generation C751B trains which have been fully phased out. The R151 trains are

10374-535: The future Cross Island Line , and the depot is to be placed at the eastern end of the line. A Singapore Rail Test Centre (formerly known as Integrated Train Testing Centre) with several test tracks for different situations and workshops for maintenance and refurbishment is also to be built at Tuas by 2022, with the main function being to test trains and integrated systems robustly before they are deployed on operational lines. The following table lists

10507-523: The government's intentions for the future of the transport network in Singapore. The latest plan, the Land Transport Master Plan 2040, was announced on 25 May 2019, and provides for line extensions to the Downtown and Thomson–East Coast lines, a new MRT line under study, and 2 new stations on the North–South Line . Hume is an infill station between Hillview and Beauty World and expected to open by 2025. An extension from Expo

10640-400: The government's intentions to greatly expand the system. It called for the expansion of the 67 kilometres of track in 1995 to 360 in 2030. It was expected that daily ridership in 2030 would grow to 6.0 million from the 1.4 million passengers at that time. New lines and extensions are mostly announced as part of the Land Transport Master Plan, which is announced every five years and outlines

10773-421: The high installation costs. Nevertheless, the LTA reversed its decision and made plans to install half-height platform screen doors in all elevated stations on 25 January 2008. The first platform screen doors by ST Electronics were installed at Jurong East , Pasir Ris , and Yishun stations in 2009 under trials to test their feasibility. By 14 March 2012, all elevated stations have been retrofitted with

10906-421: The horizontal integration of the broader public transportation network. The MRT is fully automated and has an extensive driverless rapid transit system . Asset renewal works are periodically carried out to modernise the network and ensure its continued reliability; all stations feature platform screen doors , Wi-Fi connectivity , lifts , climate control , and accessibility provisions, among others. Much of

11039-511: The incident and said SMRT will investigate how "the [two men] got hit by the train". SMRT fired both an engineer responsible for leading with the team and the train driver who was involved at the scene of the incident. The engineer who led the inspection team was charged with negligence causing death under the Penal Code and was subsequently sentenced to 4 weeks in jail. SMRT Trains and one member of SMRT management were charged for violating

11172-506: The initial construction of the system. An MRT System Designs Option Study was also conducted to refine the technical details and the recommended measures for the MRT system - these include: Singapore's MRT infrastructure is built, operated, and managed in accordance with a hybridised quasi- nationalised regulatory framework called the New Rail Financing Framework (NRFF), in which the lines are constructed and

11305-505: The introduction of the Light Rail Transit (LRT) lines connecting with the MRT network. On 6 November 1999, the first LRT trains on the Bukit Panjang LRT went into operation. The Expo and Changi Airport stations were opened on 10 January 2001 and 8 February 2002 respectively. The very first infill station of the MRT network to be built on an existing line, Dover station opened on 18 October 2001. The North East Line ,

11438-441: The island country's principal mode of railway transportation . The system commenced operations in November 1987 after two decades of planning with an initial 6 km (3.7 mi) stretch consisting of five stations. The network has since grown to span the length and breadth of the country's main island – with the exception of the forested core and the rural northwestern region – in accordance with Singapore's aim of developing

11571-418: The length of the station platform. This complements a smaller 40-metre reflective stainless-steel disc overlapping the titanium ellipse and visually floats over a glass elevator shaft and the main entrance. The other station with similar architecture is Dover . Changi Airport station, the easternmost station on the MRT network, has the widest platform in any underground MRT station in Singapore. In 2011, it

11704-477: The line are green, corresponding to the line's colour on the system map. 8 stations, including Changi Airport , and 7 other stations on the stretch from Lavender to Tiong Bahru are underground, with the rest being elevated. With the exception of Dover, all stations have island platforms. Legend List SMRT used to operate the branch sector of Tanah Merah to Changi Airport as a through service from Boon Lay from 18 November 2001 until 22 July 2003, when it

11837-470: The line extends again to four tracks due to its interchange with the North-South line but then, separates into two before heading west to Chinese Garden station. After Pioneer station , the line heads south-west before curving westwards towards Joo Koon station. The line terminates at Tuas Link with a branch heading towards Tuas Depot . The Changi Airport extension starts at Tanah Merah station as

11970-584: The line extends to four tracks due to its interchange with the Changi branch before turning back into two tracks in a western direction. From Bedok station to Kembangan station, the line goes underground but then goes above-ground, and follows the route of Sims Avenue and Sims Avenue East in an opposite direction. After Kallang station, the line goes underground through the Central Area and runs heads south-west towards City Hall station. It then runs parallel to

12103-472: The line from Woodlands South to Caldecott. Stage 3 of the Thomson–East Coast Line opened on 13 November 2022, extending the line from Caldecott to Gardens by the Bay. On 23 June 2024, the line was extended eastwards terminating at Bayshore. The lines are named based on their directions and/or locations. The names were envisioned to be user-friendly, as shown in a survey in which 70% of the respondents expressed such

12236-450: The line is the longest on the MRT network. Constructed and opened as part of the North–South Line (NSL) in the early stages of development, the East–West Line was the second rail line formed in Singapore after NSL, with the opening of the eastern extension to Tanah Merah on the EWL in 1989. Nevertheless, both lines use identical signalling equipment and rolling stock . The East–West Line signalling systems have been upgraded along with

12369-423: The line. The viaduct is integrated with part of a 4.8-kilometre-long (3.0 mi) road viaduct along Pioneer Road, which will increase the road capacity to cope with anticipated increase in traffic. The stations are Gul Circle , Tuas Crescent , Tuas West Road , and Tuas Link . On 4 May 2012, the Land Transport Authority marked the start of construction of the Tuas West extension with a groundbreaking ceremony at

12502-405: The major ones, have additional amenities and services, such as retail shops and kiosks, supermarkets, convenience stores, automatic teller machines, and self-service automated kiosks for a variety of services. Most heavy-duty escalators at stations carry passengers up or down at a rate of 0.75 m/s, which is 50% faster than conventional escalators. The Land Transport Authority (LTA) announced

12635-411: The network to double in length to about 460 km (290 mi) by 2040. Further studies are ongoing on potential new alignments and lines, as well as infill stations in the Land Transport Authority 's (LTA) Land Transport Masterplan 2040. The island-wide heavy rail network interchanges with a series of automated guideway transit networks localised to select suburban towns — collectively known as

12768-550: The network while the inauguration of Boon Lay station on 6 July 1990 marked the completion of the initial system two years ahead of schedule. The MRT has been continuously expanded ever since. On 10 February 1996, a S$ 1.2 billion expansion of the North–South Line into Woodlands was completed, merging the Branch Line into the North–South Line and joining Yishun and Choa Chu Kang stations. The concept of having rail lines that bring people almost directly to their homes led to

12901-417: The network. Underground stations and trains are air-conditioned, while above-ground stations have ceiling fans installed. Every station is equipped with Top Up Kiosk (TUKs), a Passenger Service Centre and LED or plasma displays that show train service information and announcements. All stations are equipped with restrooms and payphones; some restrooms are located at street level. Some stations, especially

13034-470: The new platforms, the existing East–West Line tracks will be extended to connect the line to the new four-in-one East Coast Integrated Depot at Changi. When completed in 2024, it will be the second station to have triple island platforms after Jurong East . There were calls for platform screen doors (PSDs) to be installed at above-ground stations after several incidents in which passengers were killed or seriously injured by oncoming trains when they fell onto

13167-429: The new route alignment showed a deviation from previous plans, where the final plan involved in building only the first two stations of Expo , and Changi Airport, the latter being the underground station built between Terminal 2 and Terminal 3 . The alignment of the station at the airport also switched perpendicularly to an east–west direction, such that the station leads to two of the terminals directly from either end of

13300-417: The new signalling system has been operating full-day on the entire East–West Line. Replacement works on the third rail, which provides electricity to the trains, were carried out between September 2015 and August 2017. The new third rail replaced its 30-year-old predecessor and is expected to increase reliability of the East–West line's electrical system. A new railway turnback located at Pasir Ris station ,

13433-437: The operations control centre of the respective lines. Trains are equipped with intercoms to allow passengers to communicate with staff during emergencies. SMRT Corporation has six train depots: Bishan Depot is the central maintenance depot for the North–South Line with train overhaul facilities, while Changi Depot and Ulu Pandan Depot inspect and house trains overnight. The newer Tuas Depot , opened in 2017, provides

13566-474: The perched roofs at Boon Lay, Lakeside , Chinese Garden , Bukit Batok , Bukit Gombak , Choa Chu Kang , Khatib , Yishun , and Eunos stations. Expo station , located on the Changi Airport branch of the East–West Line , is adjacent to the 100,000-square-metre Singapore Expo exhibition facility. Designed by Foster and Partners and completed in January 2001, the station features a large, pillarless, titanium-clad roof in an elliptical shape that sheathes

13699-418: The programme due to financial grounds and concerns of jobs saturation in the construction industry. Dr Goh instead endorsed the idea of an all-bus system recommended by Harvard University specialists, who argued this would reduce the cost by 50% compared to the proposed MRT system. Public opinion was split on the matter: several expressed concerns about the high cost while others were more focused on increasing

13832-433: The railway tracks at above-ground stations. Underground stations already featured the doors since 1987. The authorities initially rejected the proposal by casting doubts over functionality and concerns about the high installation costs, but made an about-turn later with the government announcing plans to install half-height platform screen doors on the elevated stations on 25 January 2008, citing lower costs due to it becoming

13965-514: The request of Singapore Expo, a year before the opening of Changi Airport station. As part of the President's Challenge 2001 in September, a part of a charity walk went through the tunnel between Expo and Changi Airport stations. The branch line was later extended to Changi Airport when that station opened on 8 February 2002. As with most of the older above-ground stations along the EWL,

14098-400: The safety of passengers, and SBS Transit publicised the safety precautions on the driverless North East Line before and after its opening. Safety campaign posters are highly visible in trains and stations, and the operators frequently broadcast safety announcements to passengers and to commuters waiting for trains. Fire safety standards are consistent and equivalent with the guidelines of

14231-597: The signalling system on the MRT is the automatic train control (ATC) system, which in turn is made up of two sub-systems: the automatic train operation (ATO) and automatic train protection (ATP). The ATC has trackside and trainborne components working together to provide safe train separation by using train detection, localisation, and end of authority protection. It also provides safe train operation and movement by using train speed determination, monitoring, over-speed protection and emergency braking. The safety of alighting and departing passengers will also be provided by using

14364-399: The site of the future Tuas Link station. The extension began service on 18 June 2017. During initial stages after opening, the westbound trains will alternate their terminus between Joo Koon and Tuas Link , where for every two trains, one train will terminate at the former, while the other train will terminate at the latter. On 25 August 2014, the Land Transport Authority announced that

14497-430: The speed of the train to maintain safe braking distance, and initiate emergency braking in the event of overspeed. The MRT also uses an automatic train supervision system to supervise the overall operation of the train service according to a prescribed timetable or train interval. The oldest lines, the North–South Line and East–West Line , were the only lines running with fixed block signalling . The North–South Line

14630-430: The spirit of free trade. According to the sculptor, "Expo is where business is done, the speech balloons show the kind of conversations and dialogues which people have, and the chairs show where business takes place." With the surrounding colours of the station reflected in the artwork's shiny surfaces, it transformed them into two sets of "magnificent kaleidoscopes " which also symbolises cultural exchange. The station

14763-403: The standard of living. Following a debate on whether a bus-only system would be more cost-effective, Communications Minister Ong Teng Cheong came to the conclusion that an all-bus system would be inadequate, as it would have to compete for road space in a land-scarce country. Ong was an architect and town planner by training and through his perseverance and dedication became the main figure behind

14896-407: The start of independent operations as the East–West Line. The opening ceremony was attended by then First Deputy Prime Minister Goh Chok Tong . The 6-kilometre (3.7 mi) line extension to Pasir Ris station was opened ahead of schedule on 16 December 1989 with a sneak preview beforehand. Boon Lay station opened on 6 July 1990, marking the completion of the initial MRT system. Construction on

15029-420: The station also involved the underpinning of two existing Expo MRT viaduct pier foundations. A transfer-beam was constructed before the excavation to support the two pillars and hydraulic jacks were installed on the transfer beam. Subsequently, the existing pilers were cut away. The underpinning works were carried out successfully without disruption to the EWL's operations. On 31 May 2017, the LTA announced that

15162-415: The station was built without platform screen doors (PSDs). Expo station was the last EWL station to have the half-height PSDs installed on 31 August 2011. On 20 August 2010, the Land Transport Authority (LTA) that Stage 3 of the DTL (DTL3) would terminate at Expo station, where the DTL would interchange with the EWL. Contract 922 for the design and construction of Expo station and the overrun tunnels

15295-472: The station's "elegant resolution of architecture". The artwork "A Banquet" by Yeo Chee Kiong was commissioned at the DTL station as part of the MRT network's Art-in-Transit programme, a showcase that integrates public artwork in the MRT network. The large 3D artwork depicts two reflective isometric chairs and a bulbous speech balloon , which signifies not only the importance of communication during periods of technological advancement and digital media, but also

15428-677: The station, better security control by restricting access to the tunnels and tracks and for overall passenger safety considerations. The authorities initially rejected calls for platform screen doors to be installed at elevated stations by casting doubts over functionality and concerns about the high installation costs. Nevertheless, the LTA reversed its decision and made plans to install half-height platform screen doors on elevated stations on 25 January 2008. The first platform screen doors by ST Electronics were installed at Pasir Ris, Jurong East and Yishun stations in 2009 as trial runs. Subsequently, installation began in May 2011 at Ang Mo Kio station on

15561-477: The station, together with the rest of DTL3, would be opened on 21 October that year. Passengers were offered a preview of the station along with the other DTL 3 stations through an open house on 15 October. The DTL is projected to be extended from Expo station via Xilin to Sungei Bedok MRT station as part of the DTL3 extension (DTL3e). Expected to be completed in 2026, the extension was constructed in tandem with

15694-407: The station. The station's designs were unveiled on 10 February 1998 with construction starting on 29 January 1999. Expo and Changi Airport were opened on 10 January 2001 and 8 February 2002 respectively and operates under a shuttle service. Prior to 22 July 2003, train services from Boon Lay commences after the opening, but were later reverted to shuttle services due to low patronage. On 25 May 2019, it

15827-481: The stations' interior architecture, these works aim to promote the appreciation of public art in high-traffic environments. The artwork for each station is designed to suit the station's identity. Subsequently, all stations on the North East, Circle and Downtown lines have taken part in this programme during their construction, with additional artworks installed at stations on other MRT lines. A key component of

15960-527: The suspension a free bridging bus service is available between the two stations. Continuous service between Pasir Ris and Gul Circle resumed on 28 May 2018, with the permanent activation of the new CBTC system; since the incident, selected portions of either the North–South Line or East–West Line were closed to conduct track renewal works with early weekend closures and later station openings. Train services between Boon Lay and Queenstown had been suspended since 9am on 25 September 2024 after trains lost power on

16093-524: The target date for restoration of full service was pushed back to Tuesday. On September 30, SMRT and LTA announced that full service would fully resume on October 1, with westbound train speeds being reduced from the usual 60-80 kilometres per hour (37.5-50mph) to 40 kilometres per hour (25mph) until October 3, as part of a standard process after rail replacements. Train services on the East–West Line operates from approximately 5:30   am to around midnight daily. In general, during peak hours, train frequency

16226-492: The transport operators reducing train frequencies and closing stations earlier from 17 April. However, train frequencies were shortly reverted to normal upon review and feedback from the public. Since June 2020, the MRT system has resumed pre-circuit breaker operations. Regulations for social distancing on public transport are no longer applicable by law. Social distancing stickers on seats have been removed. MRT lines operate from 5:30   am to 1:00   am daily, with

16359-454: The upcoming lines and stations that have been officially announced: The MRT system relied on its two main lines, the North–South and East–West lines, for more than a decade until the opening of the North East Line in 2003. While plans for these lines as well as those currently under construction were formulated long before, the Land Transport Authority's publication of a White Paper titled " A World Class Land Transport System " in 1996 galvanised

16492-544: The world's costliest on both a per-kilometre and absolute basis. The system is managed in conformity with a semi-nationalised hybrid regulatory framework; construction and procurement fall under the purview of the Land Transport Authority (LTA), a statutory board of the government that allocates operating concessions to the for-profit private corporations SMRT and SBS Transit . These operators are responsible for asset maintenance on their respective lines, and also run bus services, facilitating operational synchronicity and

16625-678: Was announced that the Changi Airport Extension will be converted to become part of Thomson-East Coast line Extension (TELe) by 2040. The 3.8-kilometre (2.4 mi) Boon Lay extension was first announced by the LTA on 29 December 2004, set to serve residents from the Jurong West Town area and those working in the Jurong Industrial Estate. The two stations, Pioneer and Joo Koon stations, officially opened on 28 February 2009. On 11 January 2011,

16758-498: Was awarded to Samsung C&T Corporation for S$ 211.35million (US$ 168 million) in May 2011. On 28 November 2011, the LTA marked the start of construction of DTL3 with a groundbreaking ceremony at Expo station. To facilitate the construction of the DTL station and its tunnels, part of Changi South Avenue 1 towards Somapah Road and Changi South Avenue 2, together with a short section of Expo Drive, were temporarily closed to traffic from 1 September 2012 to May 2017. The construction of

16891-538: Was awarded to the designers at WOHA Architects at the World Architecture Festival for their design of Bras Basah station. Many MRT stations have specially commissioned artworks in a wide variety of art styles and mediums, including sculptures, murals and mosaics. With over 300 art pieces across 80 stations, it is Singapore's largest public art programme. In the early stages of the MRT, artworks were seldom included; primarily consisting of

17024-407: Was projected to become in the 21st century. The DTL station design by Greenhilli utilises "interconnectivity, spatial volume, asymmetry, daylight, colour [and] super-graphics" to signify transition and movement. The station is designed to allow commuters to navigate around the station easily while making it identifiable to the locality. The station's entrances and auxiliary buildings are designed in

17157-477: Was rated 10 out of 15 most beautiful subway stops in the world by BootsnAll. Various features have been incorporated into the design to make the station aesthetically pleasing to travellers. The station is designed by architectural firm Skidmore, Owings and Merrill , featuring a large interior space and an illuminated 150-metre (490 ft) link bridge spanning over the island platform. Two Circle Line stations— Bras Basah and Stadium —were commissioned through

17290-624: Was replaced with a shuttle service. By 2040, the Changi Airport line (CAL) will be converted to the Thomson-East Coast line. Five batches of rolling stock operate on the East–West Line, namely the C151 , C151A , C151B , C151C and R151 from oldest to newest, shared with the North–South Line . Trains are maintained at Changi Depot , Ulu Pandan Depot and Tuas Depot , which provide train maintenance, inspection and overhaul facilities. These models of rolling stock were introduced to boost

17423-528: Was switching systems when the collision took place. Train service on the line resumed on 20 November, with the Tuas West extension between Gul Circle and Tuas Link using the new signalling system and the section between Pasir Ris and Joo Koon, together with the Changi Airport Branch continuing to run on the old signalling system. Train services between Joo Koon and Gul Circle were temporarily suspended until its resumption on 28 May 2018; between

17556-460: Was undertaken for eight years, including the phases of the study in 1974 and 1977. In 1979, to prepare the third phase of the study, Halcrow , a British firm, was appointed to craft the system; meanwhile, a third phase of the study was published in 1981. However, opposition from the government on the feasibility of the MRT from prominent ministers, among them Finance Minister Goh Keng Swee and Trades and Industry Minister Tony Tan , nearly shuttered

17689-474: Was upgraded to moving block / CBTC in 2017, and the East–West line upgraded in 2018. As of 27 May 2018, all MRT lines use the CBTC/moving block system in normal daily operations and from 2 January 2019, the old signalling system ceased operations. In comparison to the original fixed block system, the CBTC can reduce train intervals from 120 seconds to 100 seconds, allowing for a 20% increase in capacity and

#936063